McGlone v. United States

96 Ct. Cl. 507, 1942 U.S. Ct. Cl. LEXIS 94, 1942 WL 4468
CourtUnited States Court of Claims
DecidedApril 6, 1942
DocketNo. 43828
StatusPublished

This text of 96 Ct. Cl. 507 (McGlone v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGlone v. United States, 96 Ct. Cl. 507, 1942 U.S. Ct. Cl. LEXIS 94, 1942 WL 4468 (cc 1942).

Opinion

JoNes, Judge,

delivered the opinion of the court:

Plaintiff by contract with defendant undertook to build 3.528 miles of road in Hot Springs National Park in Arkansas, to furnish all labor and materials and to perform all work in grading and surfacing same in accordance with drawings and specifications.

The general excavation was to be paid for at the rate of 70 cents per cubic yard. Other types of work were to be paid for at special named prices. The total price of the various units of material and labor was estimated to be approximately $184,292.25, and performance bond was executed in that amount.

Notice to proceed was received by the contractor April 10, 1935, thus fixing the date for completion in compliance with the terms of the contract as not later than November 21, 1935.

Plaintiff alleges breach of contract by defendant, uncompensated changes in construction requirements, damages for delay and unpaid balance, the total of the various items claimed being $135,787.68, for which he sues.

The road was to be built up the mountain-side adjacent to Hot Springs and within the park.

There is no doubt that considerable extra work was done. The evidence, however, is conflicting, some of the claims are indefinite, the blame not always easily fixed, and the record voluminous.

We have undertaken to sort the claims, to select those in which the amounts are proven with reasonable certainty, and in reference to which responsibility. can be definitely fixed, and to disregard the others.

The evidence does not show that the contracting officer exercised any contractual authority other than the signing of the contract. The contract designated the Chief Engineer [535]*535of the Bureau of Public Eoads and the District Engineer of such Bureau as authorized representatives of the contracting officer. Contractual authority on this project was exercised by the District Engineer acting through local engineers, the latter having charge of the work and plaintiff’s working contact being with them. For convenience they will be referred to as the Engineer.

All the first bids exceeded the estimate made by the Engineer and were rejected. Some restrictions were removed and new bids called for. Plaintiff, who had bid on both invitations, was the low bidder in the second and was awarded the contract.

Between the two bid's plaintiff had gone over the site with the Engineer. The project consisted of a roadway around the mountain in the form of an elongated major bend known as the Main Line and was about 2.1 miles long. From a point along the Main Line a spur line about 1.4 miles in length diverged and ran up the mountain having a loop or turn-around at its detached end. The Main Line was in effect the relocation of an existing road.

It was the duty of defendant’s surveyors to stake the job for structures, inlets, drains, pipes, cuts, and fills.

There was some shifting of stakes on parts of the road without any change order and there were other changes in alignment from the contract plans in the same portion of the road. The net effect as to changes in excavation are not satisfactorily proved. They also had the effect of delaying construction, to what extent is indeterminable.

On another part of the road plaintiff was required to 'and did excavate rock for a ditch, also at picnic grounds and parking areas, none of which were shown on or required by the original plans. Plaintiff has been paid for this work at the rate of 70 cents per cubic yard, the rate stipulated for general excavation. The record strongly indicates that it was worth more and that plaintiff was paid less than adequate compensation. However, there was no formal change order and no agreement as to price. Plaintiff did not pursue the method plainly laid down in his contract in order to estab[536]*536lish whatever rights he may have had, and therefore, cannot recover additional compensation for this work.1

The 4,010 cubic yards of rock fall into a different category. This was a part of the general excavation and was a part of the building of the road. While it involved a change in the original contract plans such a change was authorized by the terms of the contract. These terms stipulated that the rate of pay for cuts and fills in the building of the road, regardless of classification, should be 70 cents per cubic yard. Plaintiff was paid at this rale. No other price was agreed upon and plaintiff did not protect his rights by pursuing the method set out in the contract. He is not entitled to recover any additional amount for this work.

Defendant disputes the question of whether there was an actual increase in the rock excavation when all the road that was affected by the change is taken into consideration, but even asserts there was a net decrease rather than an increase. However, since plaintiff is not entitled to recover on this item this becomes unimportant.

Additional subgrade excavation claimed by plaintiff is not satisfactorily proved.

The contract provided for payment for the hauling of material as directed more than 1,000 feet. The agreed price for overhaul was one cent per station yard. There is a balance due on this item of $2,653.26.

On another part of the road plaintiff, acting on plans that had been discarded by the Government (other plans having been duly furnished plaintiff) did considerable blasting before the error was discovered by his engineer. This wasted blasting was in no way the fault of defendant.

At Station 44 a retaining wall was built. This required considerably more excavation than had been anticipated, the Engineer requiring continuation until a good foundation was reached. Another change was made, at the suggestion of the Engineer but without change order, so that the wall was built of concerté with stone facing instead of wholly of stone. Also the plans for the retaining wall required that [537]*537“At least. 50% of all exposed masonry shall be weathered surface.” Without formal .change order the Engineer required plaintiff to construct the exposed masonry of the wall entirely of weathered surface. This entailed extra expense and labor in searching for and transporting weathered stone. The amount of the extra cost, however, is not proved. All this work delayed the completion of the contract.

A large part of the excavation was through rock requiring drilling by jackhammer and air compressor. Plaintiff planned to do this work by night to make way for shovel operations. After the first night he was stopped by the Engineer, the reason being that night drilling disturbed the people of Hot Springs. Thereafter plaintiff was not allowed to drill at night. In an effort to make up for lost- time, the drilling being a slow process, the plaintiff arranged- for an extra compressor and jackhammers. The reasonable rental cost for the use of these for the period required was $1,140.00, which plaintiff incurred. The work was delayed but the extent is not shown by the record.'

There was some delay on the part of the defendant in setting stakes and some of the grade and slope stakes were set by plaintiff, with permission of the defendant’s representative. No material loss or delay is shown.

■The defendant was responsible for some delays in moving the shovel due to error in staking for a pipe and other changes required by the Engineer. This entailed some extra expense but the amount is not definitely proved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hawkins v. United States
96 U.S. 689 (Supreme Court, 1877)
Plumley v. United States
226 U.S. 545 (Supreme Court, 1913)
Hunt v. United States
257 U.S. 125 (Supreme Court, 1921)
Sun Shipbuilding & Dry Dock Co. v. United States
76 Ct. Cl. 154 (Court of Claims, 1932)
Price v. Chicago, S. F. & C. Ry. Co.
38 F. 304 (U.S. Circuit Court for the Northern District of Illnois, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
96 Ct. Cl. 507, 1942 U.S. Ct. Cl. LEXIS 94, 1942 WL 4468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcglone-v-united-states-cc-1942.