U.S. Coating Specialties & Supplies, LLC

CourtArmed Services Board of Contract Appeals
DecidedSeptember 28, 2020
DocketASBCA No. 58245
StatusPublished

This text of U.S. Coating Specialties & Supplies, LLC (U.S. Coating Specialties & Supplies, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. Coating Specialties & Supplies, LLC, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) U.S. Coating Specialties & Supplies, LLC ) ASBCA No. 58245 ) Under Contract No. W912EE-10-C-0019 )

APPEARANCE FOR THE APPELLANT: Louis H. Watson Jr., Esq. Watson & Norris, PLLC Jackson, MS

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Steven H. Finch, Esq. John M. Breland, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Vicksburg

OPINION BY ADMINISTRATIVE JUDGE WOODROW

This appeal arises from the termination for default of a contract to construct a building to house a large unclassified supercomputer at the Army’s Engineering Research and Design Center (ERDC). On April 9, 2015, the Board issued a decision denying the government’s amended motion to dismiss or, in the alternative, for summary judgment. U.S. Coating Specialties & Supplies, LLC, ASBCA No. 58245, 15-1 BCA ¶ 35,957 (U.S. Coating I). On January 21, 2016, the government filed a renewed motion for summary judgment, contending that the parol evidence rule barred evidence of an alleged prior oral agreement between appellant and the Assistant U.S. Attorney (AUSA) during appellant’s Chapter 11 bankruptcy proceedings, and alternatively, that the AUSA lacked actual authority to enter into the alleged agreement. On April 6, 2017, the Board issued a decision denying the government’s motion. U.S. Coating Specialties & Supplies, LLC, ASBCA No. 58245, 17-1 BCA ¶ 36,710 (U.S. Coating II).

In U.S. Coating II, we held that the record was insufficient to determine whether the April 25, 2012 bankruptcy agreement was a fully integrated agreement and that genuine issues of material fact existed regarding whether there was a separate oral agreement with the government to terminate the contract for convenience. 17-1 BCA ¶ 36,710 at 178,760. We further held the AUSA possessed the necessary authority to bind the government when the parties entered into the April 25, 2012 bankruptcy settlement agreement. Id. at 178,761. Subsequently, the parties agreed to the submission of the appeal on the record without a hearing pursuant to Board Rule 11. Based on the briefs and evidence submitted, we conclude that appellant has not met its burden of demonstrating that the parties entered into a separate oral agreement to terminate the contract for convenience. We further conclude that the contracting officer (CO) reasonably exercised her discretion when she terminated the contract for default. Accordingly, we deny the appeal.

FINDINGS OF FACT

I. The Contract

1. On June 21, 2010, the U.S. Army Corps of Engineers (Corps) awarded Contract No. W912EE-10-C-0019 (contract) to appellant, U.S. Coating Specialties & Supplies, LLC (U.S. Coating) in the amount of $11,383,000 for the construction of a U.S. Army Engineer Research and Development Center Information Technology Laboratory office building and computer facility in Vicksburg, Mississippi (ERDC Project) (R4, tab 3 at 5-6 1).

2. The contract included the standard Federal Acquisition Regulation (FAR) default clause, 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984), which provided, in pertinent part:

(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed. . . . ....

(c) If, after termination of the Contractor’s right to proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government.

(Id. at 132-34)

3. U.S. Coating’s principal subcontractor was Mid-State Construction Company, Inc. (Mid-State) (gov’t br., ex. A at 2).

1 Citations to the Rule 4 file are to the consecutively-numbered pages unless otherwise indicated.

2 4. Because U.S. Coating lacked the requisite bonding capacity for the project, Mid-State agreed to serve as a major subcontractor for the Project and to indemnify the bonds of U.S. Coating and Earl Washington, U.S. Coating’s President and CEO. Mid-State Construction Company, Inc. provided the bonding for U.S. Coating’s bid and contract on the ERDC Project. (Gov’t br., ex. A at 2)

5. On November 19, 2010, U.S. Coating entered into a subcontract agreement with Mid-State to perform the work on the ERDC Project. Pursuant to the terms of an escrow agreement between U.S. Coating and Mid-State, U.S. Coating was to deposit all of the project payments it received from the government into an escrow account. (Id. at 3)

6. Mid-State performed work on the ERDC Project pursuant to the terms of the subcontract agreement with U.S. Coating (id. at 3). U.S. Coating paid Mid-State up until March 2011, but did not pay Mid-State for the April, May, and June 2011 subcontract billings, despite having been paid by the government for the work Mid-State performed (id. at 4).

7. On June 7, 2011, Mid-State provided notice to U.S. Coating that it would exercise its rights pursuant to the subcontract agreement within seven days unless the defaults were cured. U.S. Coating did not cure the default, and on June 14, 2011, Mid-State terminated the subcontract agreement and stopped work on the Project. (Id. at 5)

8. In a letter to U.S. Coating, dated August 17, 2011, the CO, Jeri H. McGuffie (CO McGuffie), described a host of performance problems, including: a 90-day delay in schedule, including multiple critical path items; the failure to maintain the site following rain events; the failure timely to provide the structural steel erection plan; the failure to reach firm agreements with various subcontractors; changing management personnel without notice; the failure to ensure adequate materials and equipment are onsite; and multiple failures to promptly pay subcontractors. (Gov’t reply br., ex. E)

9. On November 22, 2011, Mid-State won a $1.2 million arbitration award against U.S. Coating determining that U.S. Coating failed to tender payments to Mid-State (gov’t br., ex. A at 11). The arbitrator found that U.S. Coating had materially breached the contract for failure to pay Mid-State, stating U.S. Coating had “offered no valid explanation as to why [Mid-State]” was not paid (id. at 7).

II. Bankruptcy Proceedings

10. On January 13, 2012, during performance of the contract, U.S. Coating sought bankruptcy protection, filing a Chapter 11 voluntary petition in the United States Bankruptcy Court for the Southern District of Mississippi (Bankruptcy Court) (R4, tab 4).

3 11. On February 24, 2012, Travelers Casualty and Surety Company of America (Travelers), U.S. Coating’s surety for the contract, filed a motion (“Dkt. #38”) in the Bankruptcy Court, seeking relief from the automatic stay imposed by U.S. Coating’s bankruptcy filing to enforce its rights under a General Agreement of Indemnity between Travelers and U.S. Coating (R4, tab 5). Travelers also filed another motion (“Dkt. #39”) on the same date to compel rejection of the contract, or alternatively, to compel U.S. Coating to assume or reject the contract pursuant to 11 U.S.C. § 365 (gov’t supp. R4, tab 1).2

12. On March 13, 2012, Mid-State, U.S. Coating’s subcontractor, filed a response and limited objection to Travelers’ motion for relief from the automatic stay (“Dkt. #52”) (R4, tab 7). Mid-State also filed a response and limited objection to Travelers’ motion to compel on the same date (“Dkt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Crop Ins. Corp. v. Merrill
332 U.S. 380 (Supreme Court, 1947)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
William M. Hanlin v. United States
316 F.3d 1325 (Federal Circuit, 2003)
Road & Highway Builders, LLC v. United States
702 F.3d 1365 (Federal Circuit, 2012)
Anderson v. United States
344 F.3d 1343 (Federal Circuit, 2003)
Russell Corp. v. United States
537 F.2d 474 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
U.S. Coating Specialties & Supplies, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-coating-specialties-supplies-llc-asbca-2020.