Maruf Sharif Construction Company

CourtArmed Services Board of Contract Appeals
DecidedJanuary 16, 2019
DocketASBCA No. 61802
StatusPublished

This text of Maruf Sharif Construction Company (Maruf Sharif Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maruf Sharif Construction Company, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Maruf Sharif Construction Company ) ASBCA No. 61802 ) Under Contract No. N33191-14-D-1053 )

APPEARANCE FOR THE APPELLANT: Mr. Mohammad Asif Stanekzai President

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Rawn M. James, Jr., Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE THRASHER

This appeal involves a contract for renovation of an entry control point (ECP) and quarter deck of a building on a naval facility in Bahrain. The government found that appellant finished the contract 131 days late and assessed liquidated damages (LDs) in the amount of $26,200.00, later reduced by the contracting officer's (CO's) decision to $17,000. Appellant elected to proceed under the Board's Small Claims (Expedited) procedures, Board Rule 12.2. The Contract Disputes Act, 41 U.S.C. § 7106(b)(4)(5), as implemented by Board Rule 12.2, provides that this decision shall have no precedential value, and in the absence of fraud shall be final and conclusive and may not be appealed or set aside. The parties have jointly agreed that the appeal shall be heard on the record, per Board Rule 11.

SUMMARY FINDINGS OF FACT

1. On September 7, 2016, Naval Facilities Engineering Command, Europe, Africa, Southwest Asia (the government) competitively awarded Maruf Sharif Construction Company (MACEC), 1 Task Order No. 0010, under an indefinite-delivery/indefinite-quantity (ID/IQ), design/build contract, No. N33 l 91-14-D-1053 for the renovation of the ECP and quarter deck of Building 262, on NSA-1 Bahrain. The task order was a firm-fixed-price contract in the amount of$286,750.00. (Compl. ,r,r 1-4)

1 MACEC is located in Kabul, Afghanistan. 2. The contract's Statement of Work described the Project Objectives as:

Objective of the project is to ensure that personnel do not access the building without a badge/proper authorization.

This project will create an ECP that meets security criteria by locating cell phone storage outside of the existing quarter deck area and creates defined entrance and exit system while still allowing for emergency egress.

(R4, tab 4 at 54, 12)

3. The Request for Proposal (RFP) included Federal Acquisition Regulation (FAR) clause 52.211-12, LIQUIDATED DAMAGES - CONSTRUCTION (SEP 2000). The LDs amount stated in the RFP and included in the executed task order is $200.00 for each calendar day until the work is completed or accepted. (R4, tab 4 at 9)

Late Completion, Government Assessment of LDs and Appellant's Response

4. The combined design and construction period totaled 276 calendar days from task order award date with a contract completion date (CCD), as awarded, of June 10, 2017 (R4, tab 4 at 9). On August 9, 2017, the government issued a letter of concern stating appellant had only completed 45% of the project by the CCD, the government would begin assessing LDs from the day after CCD, June 11, 2017, and would begin withholding 10% on progress payment invoices (R4, tab 8). Appellant responded by letter on August 19, 2017. The body of the letter alleged two instances of government-caused excusable delay. Additionally the letter included six attachments, one of which was a Project Narrative Report including a Detailed Schedule, dated August 18, 2017. This project narrative asserted five instances of government-caused delays and stated the project was at 87. 76% complete as of the date of the schedule. (R4, tab 15)

5. On December 11, 2017, the government forwarded a letter to MACEC stating:

A final inspection of the reference[ d] contract work was conducted on October 19, 2017 .... [N]o discrepancies remain to be corrected by your firm and no punch list is required. Since there are no remaining discrepancies that significantly impact the use of the facility, the Government accepts the facility for beneficial occupancy as of October 19, 2017.

(R4, tab 5)

2 6. The government issued a notice of assessment of LDs to appellant on January 5, 2018, for 131 calendar days in the amount of $200 per day in the amount of $26,200.00 (R4, tab 2). Appellant responded on January 25, 2018, stating that the government miscalculated the number of days by not including a period of 168 days of government delay and asserted the LDs are a penalty because the government did not incur any actual damages due to the delay. Like appellant's August 19, 2017 letter, this letter also attached a Schedule Narrative Report dated January 25, 2018, that stated the project was 100% complete and asserted seven instances of government-caused delay. (R4, tab 3)

Appellant's Claim and Contracting Officer's Final Decision (COFD)

7. Appellant submitted a claim to the CO on March 3, 2018, requesting a final decision. In response, the CO issued a final decision reducing the number of assessed days to 85 in the amount of $17,000, the current amount in dispute, as a result of miscalculation (131, actually 130-day delay) and recognizing 44 days of government- caused delay associated with design review that delayed the Notice to Proceed (NIP), establishing a new completion date of July 25, 2017. (R4, tab 1)

Affidavit Testimony

8. The only testimony submitted by the government is an affidavit by Ms. Carmel Sanchez, who was a contract specialist on this task order during MACEC's performance of the work. Ms. Sanchez's testimony is a detailed estimate of actual government damages in the amount of $12,476.80 resulting from MACEC's inability to complete the contract on time. This amount is based upon cost estimated for the period between the original completion date (June 10, 2017), and the final inspection government acceptance of the project (October 19, 2017), incurred as a result of continuing contract administration. (R4, tab 11) Although it described ongoing contract work, it is silent as to whether the project was being used for its intended purpose at any time during the period in question.

9. Appellant submitted two affidavits from Mr. Victor Moller, MACEC's project manager during performance of this contract. The first, dated October 15, 2018, provided testimony that MACEC: (1) incurred 44 days of delay as a result of the government's delay in issuing the NIP, stating:

The final design package was submitted on Jan 7, 2017. The Request for proposal (RFP) mentioned that the Notice to Proceed (NTP) will be issued 7 days after the receiving of the final design. The NIP was only issued on Feb 26, 2017. This is 44 days of delay caused by the government from the

3 start of the project that impacted the contract completion date (CCD).

(R4, tab 12 at 2); (2) incurred 12 days of excusable delay related to a signage issue, stating:

I summitted [sic] RFl-003 "Signage" for government review on Sep 7, 2017. After 81 days including 3 days for RFI response mentioned in the request for proposal (RFP) and several follow ups we received a response back from Government on Nov 27, 2017 stating that the government will provide the new signage and MACEC remain responsible for the installation. We only received the government furnished equipment on Dec 8, 2017. This added an additional 12 days delay after the resolution provided to RFI-003. These delays caused by the government impacted the CCD of the project.

(Id.); and (3) that the contract was substantially completed for its intended purpose on August 30, 2017, 2 stating:

The project objective was to ensure that un-authorized personnel do not access the building without a badge/proper authorization.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise v. United States
249 U.S. 361 (Supreme Court, 1919)
Priebe & Sons, Inc. v. United States
332 U.S. 407 (Supreme Court, 1947)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Maruf Sharif Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maruf-sharif-construction-company-asbca-2019.