Dyno Group, Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 11, 2014
DocketASBCA No. 59074
StatusPublished

This text of Dyno Group, Inc. (Dyno Group, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dyno Group, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Dyno Group, Inc. ) ASBCA No. 59074 ) Under Contract No. W912P4-11-C-0016 )

APPEARANCE FOR THE APPELLANT: Edward Everett Vaill, Esq. Malibu, CA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Lauren M. Turner, Esq. Assistant District Counsel U.S. Army Engineer District, Buffalo

OPINION BY ADMINISTRATIVE JUDGE MELNICK

The United States Corps of Engineers withheld liquidated damages due to the late completion of a contract by Dyno Group, Inc. (Dyno). Dyno challenged that assessment in a claim submitted to the contracting officer, which was denied. Dyno has now appealed and elected to proceed under the Board's Expedited Procedure (Rule 12.2). 1 The appeal is denied.

FINDINGS OF FACT

1. On 22 September 2011, the United States Army Corps of Engineers awarded Contract No. W912P4-11-C-0016 to Dyno (R4, tab 5). The contract was for the removal and replacement of staircases inside the Mount Morris Dam in Mount Morris, New York. The Scope of Work contained a base bid item that required the removal and replacement of two sections of the south gallery staircase, and five additional optional items, designated A through E, for the removal and replacement of additional staircases and the replacement of stair landings. (!d. at 279) The contract was signed for Dyno by Christopher Wan, its president (id. at 257).

2. Part 1.3 of the section of the contract addressing procedures required Dyno to "complete the entire work ready for use not later than one-hundred eighty ( 180) calendar

1 The Contract Disputes Act, 41 U.S.C. §§ 7101-7109, implemented by Board Rule 12.2, provides that this decision will have no value as precedent, and in the absence of fraud shall be final and conclusive and may not be appealed or set aside. days from the date of receipt by the Contractor of the Notice to Proceed." It added that "[ t]or each Option awarded, the Contractor will be given an additional one hundred fifty (150) days to complete that option." It noted that "[o]ptions may be awarded at any time within one year of original contract award and options may be awarded concurrently." (R4, tab 5 at 324)

3. The contract contained 13 contract line item numbers (CLINs). CLINs 1 through 3 were for the base work. The initial award also exercised Options C through E, reflected in CLINs 8 through 13. (R4, tab 5 at 259-64) The scheduled period of performance for CLINs 1 through 3 was 180 days, and for CLINs 8 through 13 it was 329 days (id. at 265-66). 2 The contract contained the FAR 52.211-12, LIQUIDATED DAMAGES-CONSTRUCTION (SEP 2000) clause. In the event Dyno failed to complete the work within the time specified in the contract, that clause required Dyno to pay $450 in liquidated damages to the government for each calendar day of delay until the work was completed or accepted. (!d. at 275) The contract also incorporated the FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) clause, and the FAR 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984) clause (id. at 268).

4. On 30 September 2011, after the contract was awarded, Mr. Wan sent an email to Brian Steils, the contracting officer representative (COR) (R4, tab 9; compl., tab 17, ,-r 4 ). The email asked whether "the completion timeframe for this job [was] 180 calendar days?" It noted the "[a]ward amount consists of Base bid and Options C, D, and E" and asked "do these options give more time for completion (ie does Dyno have 150 days x 3 = 450 additional days), or is it still180 days?" (R4, tab 9) Mr. Steils's 3 October 2011 response referred Mr. Wan to an email from Mr. Walter Kamad from "Contracting." Mr. Kamad had advised the following:

Just looked over the specs, base bid is 180 days. Since options C, D and E are awarded with base bid, the breakdown would be 180 for base bid and an additional 150 days for the options. The NTP would read 180 days for base bid and to complete all options in 330 days[.]

(R4, tab 10) Mr. Steils commented that "[t]he contract states 330 days, however USACE would expect Dyno group to complete the project as soon as possible" (id.). On 3 October 2011, the contracting officer issued a Notice to Proceed to Dyno, which Dyno acknowledged receiving that day, stating Dyno could commence performance on 4 October and had until 1 April2012 (180 days) to complete the work (R4, tab 6).

2 It is not clear why the scheduled period for CLINs 8 through 13 was not 330 days, as Part 1.3 suggests it should have been.

2 5. On 10 February 2012, the contracting officer sent Dyno a letter expressing concern about whether Dyno could complete the project by 31 March 2012. The letter noted there were still outstanding submittal issues requiring resolution before work could start on the site. The letter sought an updated schedule showing anticipated completion of deliverables and construction by 17 February 2012. (R4, tab 17)

6. On 16 February 2012, Dyno requested a 150-day extension of contract completion to 29 August 2012. Among other things, Dyno argued that the 1 April2012 completion date in the Notice to Proceed was inconsistent with the contract, suggesting that the 180 days allotted only accounted for the base work, and added no time for the options. It claimed to be entitled to at least an additional 150 days. (R4, tab 19) On 5 April2012, the contracting officer executed Modification No. P00001, effective 3 April 2012. The document purports to change the deadline for completion of each of the active CLINs to 2 July 2012. 3 This would add additional days to perform the base work contained in CLINs 1 through 3, while reducing the days permitted for Options C through E in CLINs 8 through 13. This document is not executed by Dyno. (R4, tab 24) However, Dyno concedes in its submittal that "[a]n extension of the contract was granted on April3, 2012," citing an unexecuted document purporting to make the same changes in the performance periods contained in Modification No. P00001 (compl. at 6, tab 14).

7. On 28 June 2012, Mr. Wan and the contracting officer executed a bilateral modification to the contract, effective 25 June 2012. The modification exercised Options A and B, designated as CLINs 4 through 7, which involved additional removal and replacement of stairs. It designated the period for performing those CLINs to be from 26 June through 24 September 2012, which was 90 days. The modification also changed the deadline for completing the base work and Options C through E, CLINs 1 through 3 and 8 through 13, to 1 August 2012. (R4, tab 29)

8. On 26 July 2012, Dyno requested a 31-day extension oftime to complete the base work, and Options C through E, from 1 August to 1 September 2012. Dyno provided two reasons for the request. First, Dyno stated that it had encountered uneven concrete pitch in the north stairs, requiring adjustment and adding additional labor and fabrication time. However, Dyno did not indicate that this added work had delayed completion of the job beyond the current deadline. The only item requiring additional time was installation of new fiberglass railings due to fabrication delays. (R4, tab 30) There is no record the request was acted upon by the government.

9. On 22 August 2012, the contracting officer sent another letter to Dyno, expressing concern about Dyno's timely completion of the contract work. The letter observed that the government had expected the base work to be completed by 1 August

3 The first page of the modification purports to change each CLIN's deadline to 2 July, while the subsequent Summary Changes refer to 1 July.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise v. United States
249 U.S. 361 (Supreme Court, 1919)
Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
Croman Corp. v. United States
724 F.3d 1357 (Federal Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Dyno Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dyno-group-inc-asbca-2014.