Sauer Incorporated

CourtArmed Services Board of Contract Appeals
DecidedMarch 2, 2022
DocketASBCA No. 62395
StatusPublished

This text of Sauer Incorporated (Sauer Incorporated) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauer Incorporated, (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Sauer Incorporated ) ASBCA No. 62395 ) Under Contract No. W91278-07-D-0030 )

APPEARANCE FOR THE APPELLANT: Gina P. Grimsley, Esq. Counsel

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Laura J. Arnett, Esq. Engineer Trial Attorney U.S. Army Engineer District, Savannah

OPINION BY ADMINISTRATIVE JUDGE STINSON ON APPELLANT’S MOTION FOR LEAVE TO FILE AFFIRMATIVE DEFENSES

Appellant Sauer Inc. (Sauer) requests leave to file what it has termed three affirmative defenses to the government’s claim for liquidated damages: (1) “Failure to state a Claim Upon Which Relief Can Be Granted;” (2) “The Liquidated Damages Rate is Unreasonable and/or Unenforceable as a Penalty;” and (3) “Liquidated Damages Should Be Apportioned if Not Remitted Entirely” (app. mot. at 1-2; app. aff. def. at 1-2).

I. Introduction

Appellant filed its motion in response to our decision granting, in part, appellant’s cross-motion for summary judgment, based upon appellant’s substantial completion of Phases I and II of the Task Order. Sauer, Inc., ASBCA No. 62395, 21-1 BCA ¶ 37,845. In that decision, we found that Sauer “has the right to assert what is, in essence, an affirmative defense to the government’s assessment of liquidated damages,” stating that “[r]egardless of the discovery appellant claims is necessary as to the reasonableness of government’s determination of the liquidated damages rate pre-award, or the government’s jurisdictional argument as to that determination, appellant here also challenges the reasonableness of the government’s decision not to apportion that rate, even though appellant had completed Phases I and II.” Id. at 183,759. In its reply to appellant’s cross-motion for summary judgment, the government argued that we lacked “jurisdiction to consider the reasonableness of its liquidated damages rate, including ‘who calculated the rate or how it was derived,’ because it was not first the subject of a claim submitted by appellant or a contracting officer’s final decision.” Id. 1

In Sauer, we explained that “[o]ur decision on the parties’ cross-motions for summary judgment turns not on the reasonableness of the liquidated damages rate as established by the government pre-award (nor are we able to decide that factual dispute on summary judgment), but, rather, on the government’s failure to apportion its liquidated damages at the time it assessed those damages.” Id. at 183,759-760. We noted that “Board Rule 6(d) provides for amendment of pleadings ‘upon conditions fair to both parties,’” and that, “[g]iven our decision here, appellant must decide what additional steps, if any, are necessary to properly tee up its affirmative defense for resolution in this appeal.” Id. at 183,760. Our suggestion that appellant consider what steps were necessary to properly assert its affirmative defense was stated in the context of the government’s jurisdictional challenge to appellant’s arguments regarding assessment of liquidated damages, which the government argued were not properly before us.

II. Contention of the Parties

In its motion for leave to file its affirmative defenses, appellant states that it believes the defenses it asserts “are properly encompassed within the scope of the appeal as framed in the Notice of Appeal, COFD [contracting officer’s final decision], complaint and even as addressed by the parties in the summary judgment motions,” but seeks leave to file “in an abundance of caution” (app. mot. at 2). With the filing of its motion for leave, appellant now has placed squarely before us its challenge to the reasonableness of the liquidated damages rate set forth in the task order, specifically with the submission of its second affirmative defense alleging that “The Liquidated Damages Rate is Unreasonable and/or Unenforceable as a Penalty” (app. aff. def. at 1). Appellant argues that this defense already is subsumed in its appeal given the alleged “broad relief” it sought in challenging to the government’s imposition of that rate (app. mot. at 1).

The government opposes appellant’s motion for leave, stating that the three affirmative defenses “are all attempts to have the Board address whether the liquidated damages (LD) rate was reasonable and enforceable” (gov’t opp’n at 1). According to the government, we “may not consider the enforceability, reasonableness, or apportionment of the LD rate at this time because Sauer did not submit any of these issues to the contracting officer for decision” (id. at 2). 2 The government argues that because

1 On May 14, 2021, the government filed a motion for reconsideration of our April 16, 2021, decision. Some of the issues raised in that motion overlap with issues discussed here. We address in a separate order issues raised by the government in its motion for reconsideration. 2 Appellant did not file a reply to the government’s opposition to appellant’s motion for leave to file its affirmative defenses. 2 appellant allegedly failed to raise the issues in its claim, the contracting officer did not have an opportunity to decide the issues (id.).

III. Affirmative Defenses Alleging the Liquidated Damages Rate is Unreasonable and/or Unenforceable as a Penalty and Should Be Apportioned if Not Remitted Entirely

As discussed above, our decision in this appeal did not turn on the reasonableness of the rate, only the enforceability of the rate based upon completion of the first two phases of the project. The error in the government’s argument here is it combines two separate claims - the reasonableness of the contractual rate set forth in the task order and the enforceability of that rate where two phases of the project were completed. As we discuss below, appellant’s claim submitted to the contracting officer encompassed the issue of enforceability of the government’s liquidated damages claim because it challenged the propriety of liquidated damages in light of appellant’s substantial completion of the project.

A. Unenforceability of Liquidated Damages

The government cites M. Maropakis Carpentry, Inc., v. United States, 609 F.3d 1323, 1331 (Fed. Cir. 2010), for the proposition that “defenses to liquidated damages should be considered claims that need to be first submitted to a contracting officer for decision” (gov’t opp’n at 3). In that case, the contractor failed to present its Contract Disputes Act (CDA) claim to the contracting officer, and the Court of Federal Claims held that it lacked jurisdiction to consider the contractor’s claim, but did have jurisdiction to consider the government’s counterclaim for liquidated damages, which was the subject of a final decision. Maropakis, 609 F.3d at 1325. The Court of Appeals for the Federal Circuit affirmed, holding “that a contractor seeking an adjustment of contract terms must meet the jurisdictional requirements and procedural prerequisites of the CDA, whether asserting the claim against the government as an affirmative claim or as a defense to a government action.” Id. at 1331.

Unlike the contractor in Maropakis, however, there is no dispute here that appellant submitted a claim to the contracting officer challenging the government’s assessment of liquidated damages on the basis that appellant had substantially completed contract performance. There also is no dispute that the contracting officer issued a decision denying appellant’s claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
Daniel A. Lindsay v. United States
295 F.3d 1252 (Federal Circuit, 2002)
Godfredson v. JBC Legal Group, P.C.
387 F. Supp. 2d 543 (E.D. North Carolina, 2005)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Lee's Ford Dock, Inc. v. Secretary of the Army
865 F.3d 1361 (Federal Circuit, 2017)
Young Associates, Inc. v. United States
471 F.2d 618 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
Sauer Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauer-incorporated-asbca-2022.