Sauer Incorporated

CourtArmed Services Board of Contract Appeals
DecidedApril 16, 2021
DocketASBCA No. 62395
StatusPublished

This text of Sauer Incorporated (Sauer Incorporated) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauer Incorporated, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Sauer Incorporated ) ASBCA No. 62395 ) Under Contract No. W91278-07-D-0030 )

APPEARANCE FOR THE APPELLANT: Gina P. Grimsley, Esq. Counsel

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Laura J. Arnett, Esq. Engineer Trial Attorney U.S. Army District, Savannah

OPINION BY ADMINISTRATIVE JUDGE STINSON ON THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

Appellant Sauer Inc., (Sauer), appeals a contracting officer’s denial of its September 6, 2019, claim, in the amount of $144,780, seeking remission of liquidated damages (R4, tab 2.01). We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. The parties submitted cross-motions for summary judgment, response and reply briefs, and exhibits, to be considered in deciding this appeal. 1 For the reasons stated below, the government’s motion for summary judgment is denied and appellant’s cross-motion for summary judgment is granted-in-part.

1 We refer to the parties’ motions and briefs as follows: “gov’t mot. ___” refers to the government’s motion for summary judgment; “app. cross-mot. ___” refers to appellant’s memorandum in opposition to respondent’s motion for summary judgment and appellant’s cross-motion summary judgment; “gov’t resp. ___” refers to the government’s response to appellant’s statement of undisputed material facts and opposition to appellant’s cross-motion for summary judgment; “gov’t reply ___” refers to the government’s reply in support of its motion for summary judgment; and “app. reply ___” refers to appellant’s reply in support of its cross-motion for summary judgment. STATEMENT OF FACTS (SOF) FOR THE PURPOSES OF THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

Unless otherwise noted, the following facts are undisputed or uncontroverted.

1. On August 18, 2006, the U.S. Army Engineer District, Mobile, issued Solicitation No. W91278-06-R-0105, contemplating the award of a Multiple Award Task Order Contract (MATOC), a regional geographic multiple awards indefinite delivery type contract in support of military construction in the South Atlantic Division (R4, tab 3.01 at 0004). In 2007, the government awarded Sauer MATOC No. W91278-07-D-0030.2

2. On January 12, 2011, the government issued a Request for Proposal (RFP), pursuant to the MATOC, for design and construction of the 82nd Airborne Division Headquarters, in Fort Bragg, North Carolina, Project Number 44968 (the Project) (R4, tab 3.02 at 0002). The RFP stated that “[t]he scope of work for this Design Build project includes construction and design of a standard design command and control headquarters building” (R4, tab 3.02 at 0003).

3. The RFP scope of work identified a “primary facility,” which included “command headquarters, a joint operations center, a sensitive compartmented information facility (SCIF), conference rooms, classroom space, equipment storage, general storage, mechanical and communications rooms, installation of intrusion detection system (IDS) and connection to energy monitoring and control system (EMCS)” (id.).

4. The RFP scope of work also identified “supporting facilities,” which included, “water and sewer service, electric service, paving and walks, fire protection and alarm systems, exterior lighting, storm drainage, erosion control measures, asbestos removal & lead-based paint remediation as part of demolition, information systems, parking and site improvements” (id.).

5. Section 3.1.1 of the Task Order Statement of Work provided, in part, “[t]he preferred Command and Control Facility (C2F) is a multi-story stand-alone facility organized around the central core consisting of stairs, elevators, men’s and women’s restrooms, telecommunication rooms and other support spaces such as break rooms,

2 In response to the Board’s request for a copy of the MATOC, the government submitted a copy of the solicitation that resulted in its award (R4, tab 3.01). In the accompanying March 27, 2020 letter, entitled Respondent’s Corrected Rule 4 Submission, the government informed the Board that it “is unable to locate a viable copy of the award document. However, the Government does not anticipate a dispute about Appellant’s status as a member of the MATOC pool since it was awarded numerous task orders against the MATOC.”

2 storage, recycle rooms, etc., as depicted in the preferred functional layout included with this RFP” (R4, tab 3.02 at 0035).

6. Section 6.17.1 of the Task Order Statement of Work provided, in part, “[t]he Government will identify buildings and other existing features to be demolished in the site plans, as applicable to the project” (R4, tab 3.02 at 0180).

7. The RFP included a liquidated damages provision based upon the Federal Acquisition Regulation (FAR), which stated, “[i]n accordance with FAR Clause 52.211-12, Liquidated Damages-Construction, liquidated damages in the amount of $4,365.81 per day shall be assessed if the Contractor fails to complete the work within the time specified in this task order” (R4, tab 3.02 at 0007). The RFP set a duration date of 540 days after receipt of the notice to proceed (id.).

8. By letter dated February 7, 2011, the government issued RFP Revision No. 02, which included the following:

A. CONTRACT CHANGES: The phasing requirement for this project is as follows:

1. Phase I: Construction of new Headquarters (540 days)

2. Phase II: Installation of furniture and move into new building (60 days)

3. Phase III: Demolition of existing building and completion of parking lot areas (100 days)

4. The overall construction duration for this project has changed from 540 calendar days to 700 calendar days. The paragraph below has been revised to reflect contract duration to 700 calendar days.

a. In accordance with FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work, the Contractor shall commence work within 5 calendar days after receipt of notice to proceed, shall prosecute the work diligently and shall complete all work ordered under this task order within the time proposed by the offeror, but not to exceed the maximum allowed 700 calendar days after receipt of notice to proceed.

(R4, tab 3.03 at 0001-0002)

3 9. On March 1, 2011, Sauer submitted a proposal in response to the RFP (R4, tab 3.04 at 0002). Sauer’s proposal included the same liquidated damages provision set forth in the RFP (R4, tab 3.02 at 0007, tab 3.04 at 0006; SOF ¶ 7).

10. By letter dated March 28, 2011, the government informed Sauer that its offer was in the competitive range. The government opened discussions for the purpose of allowing clarifications and submission of a revised cost proposal (R4, tab 3.05).

11. By letter dated April 15, 2011, Sauer submitted its revised proposal (R4, tab 3.07). Sauer’s revised proposal included the same liquidated damages provision as set forth in, and required by, the RFP, and as contained in Sauer’s initial proposal (R4, tab 3.02 at 0007, tab 3.04 at 0006, tab 3.07 at 0003; SOF ¶¶ 7, 9).

12. On June 13, 2011, the government awarded Sauer MATOC Task Order CV02 (the Task Order) (R4, tab 3.08). The Task Order contained a scope of work nearly identical to the one specified in the RFP (R4, tab 3.02 at 0003, tab 3.08 at 0005; SOF ¶¶ 3-4).

13. The Task Order contained three Contract Line Item Numbers (CLINs) (R4, tabs 3.02 at 0006, 3.08 at 0002-0003). The three CLINs were not specifically tied to each of the Task Order’s three phases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Sauer Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauer-incorporated-asbca-2021.