Coastal Environmental Group, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 17, 2018
DocketASBCA No. 60410
StatusPublished

This text of Coastal Environmental Group, Inc. (Coastal Environmental Group, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coastal Environmental Group, Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Coastal Environmental Group, Inc. ) ASBCA No. 60410 ) Under Contract No. N40085-I3-C-6541 )

APPEARANCES FOR THE APPELLANT: John M. Manfredonia, Esq. James Petersen, Esq. Manfredonia Law Offices, LLC Cresskill, NJ

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Matthew D. Bordelon, Esq. Robert R. Kiepura, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

FINDINGS OF FACT

On September 23, 2013, the parties contracted for appellant to make repairs to the Security Boat Marina at Naval Weapons Station Earle, Leonardo, New Jersey (R4, tab 5 at 204, 206). Specifically, the work consisted of work to three in-water features; namely, a "short wall," a "long wall;' and a buoy (id. at 233-34, ,r 6; tr. 3/46). The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984), which provides:

(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed.

(R4, tab 5 at 209) The contract provided 13 5 days from the date of award to complete the work; that is, through February 5, 2014 (see id. at 203). Unless otherwise indicated, the following events all occurred in 2015. On January 8, the government ordered appellant to stop work, stating that "no work shall commence until you receive further notice from the Government" (app. supp. R4, tab 66 at 1-2 ). On July 31, in Modification No. 5, the parties agreed ( 1) to an increase in the contract price; (2) that "[i]n conjunction with the work specified in the subject contract," appellant would "[r]epair additional damage to the wave screen ... that occurred since contract award"; and (3) that the contract completion date would be November 26, 2015 (R4, tab 7 at 381-82). The modification included the following "Contractor's release":

Acceptance of this modification by the contractor constitutes an accord and satisfaction and represents payment in full for both time and money and for any and all costs, impact effect, and for delays and disruptions arising out of, or incidental to, the work as herein revised.

(Id. at 382,, 5 (emphasis added)) 1

On September 15, the government requested that appellant provide an updated project schedule by the following day (R4, tab 20 at 428). Two days later, on September 17, the government told appellant that it "must contact this office in writing by 4:00 p.m. today if you plan to meet the terms of your contract by the scheduled completion date" (id. at 427-28). The government stated further that "[i]fthe requested information is not provided today or if you have determined that you are no longer able to meet the obligations within your contract, the Government intends to move forward and terminate your contract for default" (id. at 428). Minutes before the 4:00 p.m. deadline, appellant provided to the government a project schedule that indicated (among other things) that it would take three days to complete the mobilization of equipment and materials to the site, and that if mobilization were complete by September 30, appellant would complete the contract work on November 26, 58 days later (see id. at 429, lines 22-23, 60).

On October 5, the government complained to appellant that appellant had not "completed or met one single item" on its September 17, 2015 schedule (R4, tab 22 at 434 ). Appellant responded on the same day, acknowledging that it was "behind schedule" and that it had not yet mobilized to the site, explaining that that it had "intentions of mobilizing within the next two weeks" (id. at 433). Appellant explained that "whaler systems ... are waiting to be delivered onsite," that "additional sheet

1 Prior to the execution of Modification No. 5, the parties had bilaterally executed Modification Nos. 2 through 4 which collectively had extended the contract completion date to December 30, 2014. Each of those modifications included the same release language as in No. 5. (App. supp. R4, tabs 10-12)

2 piles ... are awaiting confirmation oflead time and delivery," and that "[m]iscellaneous steel and timber capping shall be provided by the Subcontractor" (id.). Appellant further stated that it was "working to confirm exact dates in order to provide an updated schedule" to the government (id. (emphasis added)). By October 8, 2015, appellant had not mobilized its equipment and materials to the site (see tr. 3/169-70).

On October 8, with 50 days remaining before the November 26 contract completion deadline, the contracting officer terminated the contract for default, citing "continued lack of progress thereby endangering completion as required by the contract" (R4, tab 25). Appellant appealed to the Board on January 8, 2016. Appellant is a New York corporation that dissolved on June 29, 2016 (tr. 3/110, 114).

The project manager of a maritime construction company that appellant had planned to hire to perform the onsite work testified at the hearing of the appeal that the company was prepared to perform the work and complete it by November 26, 2015, working only 8 hours per day, but that~ "ifthere was any kind of need to escalate, we had 24 hours a day to work" (tr. 4/13-14). The project manager provided a breakdown of how the work would have progressed, including that most of the work would have progressed simultaneously (tr. 4/20-21, 29, 33).

DECISION

Appellant wants the termination for default converted to one for the convenience of the government. The government says that the Board does not possess jurisdiction to entertain the appeal because appellant is a New York corporation that has been dissolved since June 29, 2016 (see gov't br. at 25). We look to the law of the state of incorporation to answer that question. See TPS, Inc., ASBCA No. 52421, 01-1 BCA ,i 31,375 at 154,916. Under New York law, "[t]he dissolution ofa corporation shall not affect any remedy available to or against such corporation ... for any right or claim existing ... before such dissolution." N.Y. Bus. Corp. Law§ 1006(b) (McKinney 2018). The "right or claim" here, appellant's challenge to the government's termination of its contract, arose on the date of that termination: October 8, 2015. The subsequent dissolution of appellant does not affect appellant's capacity to appeal from the termination of the contract, or our jurisdiction to entertain that appeal.

Regarding the termination of the contract for default for failure to make progress ("continued lack of progress," as the contracting officer put it), the question is whether the government has demonstrated that on October 8, 2015 (the termination date), it was reasonable to conclude that there was no reasonable likelihood that appellant would complete the project by November 26, 2015 (the contract completion date). See Securiforce International America, LLC v. United States, 879 F.3d 1354, 1364 (Fed. Cir. 2018); Empire Energy Management Systems, Inc. v. Roche, 362 F.3d 1343, 1357 (Fed. Cir. 2004); Nelson, Inc., ASBCA Nos. 57201, 58166, 16-1 BCA ,i 36,195 at 176,588 (involving

3 FAR 52.249-IO(a)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Coastal Environmental Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/coastal-environmental-group-inc-asbca-2018.