John Shaw LLC d/b/a Shaw Building Maintenance

CourtArmed Services Board of Contract Appeals
DecidedApril 15, 2021
DocketASBCA No. 61379, 61585
StatusPublished

This text of John Shaw LLC d/b/a Shaw Building Maintenance (John Shaw LLC d/b/a Shaw Building Maintenance) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Shaw LLC d/b/a Shaw Building Maintenance, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) John Shaw LLC d/b/a Shaw Building Maintenance ) ASBCA Nos. 61379, 61585 ) Under Contract No. AAFES REZ-09-002-10-026 )

APPEARANCE FOR THE APPELLANT: Ian Morris, Esq. Morris Law Charlotte Huntersville, NC

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney CPT Richard W. Hagner, JA Robert B. Neill, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT

Appellant John Shaw LLC d/b/a Shaw Building Maintenance (Shaw LLC or appellant) claims costs associated with its federal and state tax liability, interest from late payment of invoices, the cost of lost equipment, and Mr. Shaw’s hourly rate for phone calls placed in pursuit of these costs. These allegedly result from a 3-year delay in payment of 2 of its 36 invoices related to a janitorial services contract with the Army & Air Force Exchange Service (Army or government). For the reasons discussed below, we deny these appeals.

FINDINGS OF FACT

We have previously issued three decisions in these appeals: John Shaw LLC d/b/a Shaw Building Maintenance, ASBCA No. 61379, 18-1 BCA ¶ 37,003; John Shaw LLC d/b/a Shaw Building Maintenance, ASBCA No. 61379, 18-1 BCA ¶ 37,026; and John Shaw LLC d/b/a Shaw Building Maintenance, ASBCA Nos. 61379, 61585, 19-1 BCA ¶ 37,216. Familiarity with those decisions and the facts discussed therein is presumed. However, we reiterate several relevant facts here for clarity.

1. On May 2, 2010, the Army awarded Contract No. AAFES REZ-09-002-10-026 to Shaw LLC, valued at $358,000 (R4, tab 1 at 3). The contract was to furnish all personnel, supervision, equipment, tools, materials, and supplies for janitorial services in the shoppette and shopping center at Eielson Air Force Base in Alaska (id. at 7, 36). The contract contained a clause subjecting this contract to the Contract Disputes Act (CDA) of 1978, stating “all disputes arising under or relating to this contract shall be resolved under this clause” (id. at 13). Exhibit C, Section 6.b(2)(a) stated payment was required within 30 days “after receipt of a proper invoice” (id at 30). Section 6.b(10) stated “[a]ny interest penalties due to contractors will be computed in accordance with the Prompt Payment Act, 31 U.S.C. §§ 3901-3906, as amended” (id. at 31).

2. On May 31, 2012, the government issued “Amendment 1,” exercising the first option year in the contract to extend services to cover June 1, 2012, through May 31, 2013 (R4, tab 2 at 1).

3. Appellant sent invoice no. 2701 to the government on November 25, 2012. Appellant also sent invoice no. 2863 on April 29, 2013. Each was for $15,913.35. (R4, tabs 15, 27 at 1-2)

4. The contract expired on May 31, 2013, and was not renewed by the contracting officer (CO) (R4, tab 2 at 1; tr. 73-75). At this time, invoice nos. 2701 and 2863 were still outstanding (R4, tab 25).

5. The government issued a check for $31,826.70 for the two outstanding invoices on September 30, 2016, and appellant cashed it on October 3, 2016. The government also calculated 47 days of Prompt Payment Act (PPA) interest and issued a check for $76.30 for both invoices on October 26, 2016, which appellant cashed on November 3, 2016. (R4, tab 25 at 2, 4, tab 37 at 1-3)

6. On March 20, 2017, Shaw LLC submitted a claim to the Army CO for $419,781.01. This was calculated by attributing $9,045.84 for loss of explosion-proof equipment, $2,009.77 in PPA interest, and the rest in punitive damages. While the claim recognized the government “paid good faith amount of $31,826.70 to offset a portion of losses,” the claim also alleged that the government had failed to timely pay two of appellant’s invoices, resulting in appellant’s use of funds from an unrelated contract. Also as a result, appellant was required to pay for storage of its explosion-proof equipment in Alaska that it could not ship back to North Carolina, where Shaw LLC was based. Appellant further alleged that its failure to pay those storage fees resulted in the storage company selling the equipment to cover those costs. (R4, tab 13 at 3-4)

7. On August 16, 2017, the CO denied the claim in full. The CO determined that appellant was not timely paid these two invoices because it had contacted Exchange personnel regarding updating its payment account information, but not the Army CO, as required by the contract. The CO further found no basis in the contract for punitive damages for appellant failing to secure future contracts, and thus there was no basis for the punitive damages claim. (R4, tab 14) Appellant timely appealed this decision, and the Board docketed it as ASBCA No. 61379.

2 8. The Board granted the government’s motion to dismiss the claim for punitive damages in an earlier opinion issued in this appeal on March 8, 2018. Shaw LLC, 18-1 BCA ¶ 37,026. On March 27, 2018, Shaw LLC submitted an amended claim to the CO for $2,916,323.61. This included the $31,826.70 for outstanding invoices which it previously stated had been paid, and added $2,986.81 for taxes owed to the state of Alaska, $14,636.00 for federal taxes owed to the IRS, $4,662 for labor in making telephone calls to pursue this claim, $645,154.49 in exemplary damages, and $2,206,002 for “missed opportunities.” (R4, tab 23 at 1-2)

9. On March 29, 2018, the CO denied the amended claim in full. The CO cited his previous decision for the equipment and PPA interest claims and the ASBCA’s decision dismissing the “missed opportunities” claim. The CO observed that the invoice claims were for invoices that had been paid in 2016. Finally, the claims for federal and state taxes, telephone bills, and exemplary damages failed “to provide a basis in the contract to support the total losses [appellant has] identified.” (R4, tab 31) Appellant appealed this denial to the Board on April 9, 2018. The Board docketed this as ASBCA No. 61585.

10. The government issued two checks to appellant on April 19, 2018, and May 1, 2018, for one year of PPA interest for both invoices minus the amount previously paid in 2016. The interest for invoice no. 2701 was $486.81, while the amount for invoice no. 2863 was $486.16. (R4, tab 37 at 3) However, the government used the rate of 3.25%, rather than what it believes were the correct rates for two different parts of the year, 1.75% and 1.375% (R4, tab 37 at 2).

DECISION

We previously granted the government’s pre-hearing motion to dismiss the claims for the unpaid invoices, “missed opportunities,” and exemplary damages. Shaw LLC, 19-1 BCA ¶ 37,216. The remaining requests for relief concern $9,045.84 for loss of appellant’s equipment; $2,986.81 for taxes owed to the state of Alaska; $14,636 in federal taxes owed to the IRS; $4,662 in the labor costs of making telephone calls; and $2,009.77 in PPA interest, totaling $33,340.42. Appellant argues in its pre-hearing brief 1 that these losses were due to a breach by the government of the duty of good faith and fair dealing implied in every contract. The Army argues that while many of these costs

1 At the hearing, the parties agreed appellant would file a post-hearing brief, the government would then respond, and appellant would submit a reply (tr. 100). Appellant failed to submit an initial brief or a reply to the government’s post-hearing brief. We thus review appellant’s arguments articulated in its pre-hearing brief and during the hearing. 3 amount to consequential damages and thus are not allowed, none are causally connected to the alleged breach anyway.

Appellant, as the proponent of the claim, has the burden of proof. Horton Constr. Co., ASBCA No. 61085, 18-1 BCA ¶ 36,979 at 180,129. Every contract imposes upon each party a covenant of good faith and fair dealing in its performance and enforcement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Metcalf Construction Company v. United States