In Re SECRETARY OF THE ARMY

CourtCourt of Appeals for the Federal Circuit
DecidedDecember 26, 2024
Docket23-2067
StatusPublished

This text of In Re SECRETARY OF THE ARMY (In Re SECRETARY OF THE ARMY) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re SECRETARY OF THE ARMY, (Fed. Cir. 2024).

Opinion

Case: 23-2067 Document: 29 Page: 1 Filed: 12/26/2024

United States Court of Appeals for the Federal Circuit ______________________

IN RE: SECRETARY OF THE ARMY, Appellant ______________________

2023-2067 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in No. 60451-EAJA, Administrative Judge J. Reid Prouty, Administrative Judge Arthur M. Taylor, Adminis- trative Judge Richard Shackleford. ______________________

Decided: December 26, 2024 ______________________

TANYA KOENIG, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washing- ton, DC, argued for appellant. Also represented by BRIAN M. BOYNTON, WILLIAM JAMES GRIMALDI, PATRICIA M. MCCARTHY. ______________________

Before REYNA, TARANTO, and CUNNINGHAM, Circuit Judges. TARANTO, Circuit Judge. This appeal presents a question about the framework for determining the availability of an award of attorney’s fees and expenses against the federal government under the Equal Access to Justice Act (EAJA), which provides for such an award to a prevailing party unless (as relevant Case: 23-2067 Document: 29 Page: 2 Filed: 12/26/2024

2 IN RE: SECRETARY OF THE ARMY

here) the position of the government was substantially jus- tified. See 5 U.S.C. § 504 (provision governing agency ad- judications, applicable here); 28 U.S.C. § 2412 (similar provision governing court cases). We address the threshold framing of the substantial-justification inquiry, and our ruling is a limited one. We reverse the categorical narrow- ing of the inquiry into substantial justification that ap- pears in the decision on appeal, in which the Armed Services Board of Contract Appeals determined that the government did not establish the required substantial jus- tification and awarded fees and expenses to the prevailing, non-government party. CKY, Inc., ASBCA No. 60451- EAJA, 23-1 BCA ¶ 38,310, pp. 186,012–19, 2023 WL 2778410 (Feb. 15, 2023) (Fees Decision). We remand for the Board to redetermine, without the categorical narrowing we reject, how to exercise its discretion in resolving the substantial-justification issue. We do not decide what re- sults might be within the range of available discretion in this case. I The EAJA issue arises from a case brought by CKY, Inc. in the Board against the United States Army Corps of Engineers (Corps) under the Contract Disputes Act. 41 U.S.C. §§ 7101–7109. CKY claimed that, in carrying out a task order under a fixed-price construction contract with the Corps, it incurred significant additional expenses from unexpected developments, contractually entitling it to com- pensation beyond the fixed price. CKY prevailed in recov- ering substantial additional compensation for particular expenses, while failing in its effort to recover compensation for other (assertedly even larger) expenses. CKY, Inc., ASBCA No. 60451, 20-1 BCA ¶ 37,575, pp. 182,449–57, 2020 WL 1896785 (Apr. 13, 2020) (Merits Decision). The Board then awarded EAJA fees and expenses to CKY, and in doing so, the Board stated that it was categorically lim- iting its substantial-justification inquiry to the govern- ment’s litigating position concerning the expenses for Case: 23-2067 Document: 29 Page: 3 Filed: 12/26/2024

IN RE: SECRETARY OF THE ARMY 3

which CKY was successful in obtaining recovery. Fees De- cision, at 186,013. The government here disputes that threshold narrowing of focus in the EAJA analysis. A In October 2012, the Corps awarded CKY a fixed-price task-order contract for CKY, in exchange for $932,349, to perform certain dewatering, culvert-installation, and other construction work in southern Louisiana. See Appx. 547– 50, 943; Merits Decision, at 182,449, 182,450–51 ¶¶ 2, 7– 9. 1 In November 2012, the government issued CKY a no- tice to proceed with the construction work and to complete it within 210 days. Appx. 65 ¶ 2, 90; Merits Decision, at 182,450–51 ¶¶ 3, 9. Heavy rainfall soon caused delays in scheduled work, and in January 2013, CKY identified wa- ter from the Mississippi River back-flowing into the con- struction site from two culverts that had not been disclosed in the task-order documents and drawings supplied by the government upon contracting. Appx. 67 ¶¶ 3–4, 92–94; Merits Decision, at 182,451 ¶¶ 10–11, 182,455. After discussions with CKY, the Corps agreed that the two culverts had not been disclosed at contracting, and in July 2013, it issued a Request for Proposal for CKY to spec- ify construction details for a prospective fix, which would “[p]rovide additional drainage pipes and swales to direct the flow” from the two undocumented culverts (and one al- ready documented culvert) into a new culvert and head- wall. Merits Decision, at 182,451–522 ¶¶ 11, 13–14. CKY did so, and on May 7, 2014, the Corps issued a notice to proceed with the change. Id. at 182,452 ¶ 14. The Corps authorized payments reflected in contract Modifications 1E

1 In selecting and summarizing facts to provide background for discussing the legal issues we resolve, we do not preclude any fuller or more precise factual recita- tions, if necessary, on remand. Case: 23-2067 Document: 29 Page: 4 Filed: 12/26/2024

4 IN RE: SECRETARY OF THE ARMY

(December 2013), 1L (July 2014), and 1M (December 2014). Appx. 2183–86, 2198–200; see Merits Decision, at 182,452 ¶¶ 15–17. Modification 1M, which referred back to 1E and 1L, included a “compensation in full” clause concerning the new construction ordered. Appx. 2199–200; Merits Deci- sion, at 182,452 ¶ 17. 2 CKY and the Corps also agreed to certain no-cost modifications that, because of high river- water levels and unusually severe weather, gave CKY more time to complete its contract work. Appx. 71–74, 2170–71, 2190–93. B In October 2014, CKY sought from the Corps a total of $828,126.70 in increased payments by submitting separate Requests for Equitable Adjustments pursuant to Federal Acquisition Regulations (FAR) 552.243-71, 48 C.F.R. § 552.243-71. See Appx. 75. For some of the requests, CKY invoked a FAR provision on “Differing Site Conditions,” FAR 52.236-2, 48 C.F.R. § 52.236-2 (1984), which provides for adjustments based on site conditions that are materi- ally different from those indicated in the contract and were reasonably unforeseeable. See Merits Decision, at 182,450 ¶ 1, 182,454. The contracting officer for the Corps itemized the requests and the separate amounts sought for each.

2 The provision states: It is further understood and agreed that this adjust- ment constitutes compensation in full on behalf of the contractor, its subcontractors and suppliers for all costs and markups directly or indirectly attributable to the changes ordered, for all delays, impacts and ex- tended overhead related thereto, and for performance of the change within the time frame stated. Appx. 2200, quoted in Merits Decision, at 185,452 ¶ 17. Case: 23-2067 Document: 29 Page: 5 Filed: 12/26/2024

IN RE: SECRETARY OF THE ARMY 5

Appx. 75. 3 She denied all the requests on April 7, 2014. See Appx. 75–76. Acting pursuant to the Contract Disputes Act, 41 U.S.C. §§ 7103(a)–(b), CKY submitted a certified claim to the Corps on June 17, 2015. Appx.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Pierce v. Underwood
487 U.S. 552 (Supreme Court, 1988)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Scarborough v. Principi
541 U.S. 401 (Supreme Court, 2004)
Gatimi v. Holder
606 F.3d 344 (Seventh Circuit, 2010)
SAYSANA v. Gillen
614 F.3d 1 (First Circuit, 2010)
Jacobs, Daniel S. v. Schiffer, Lois J.
204 F.3d 259 (D.C. Circuit, 2000)
Hong-Yee Chiu v. The United States
948 F.2d 711 (Federal Circuit, 1991)
Hanover Potato Products, Inc. v. Shalala
989 F.2d 123 (Third Circuit, 1993)
Patrick v. Dept. Of Veterans Affairs
668 F.3d 1325 (Federal Circuit, 2011)
United States v. Hurt
676 F.3d 649 (Eighth Circuit, 2012)
DGR Associates, Inc. v. United States
690 F.3d 1335 (Federal Circuit, 2012)
Stewart v. Astrue
561 F.3d 679 (Seventh Circuit, 2009)
United States v. 515 Granby, LLC
736 F.3d 309 (Fourth Circuit, 2013)
Highmark Inc. v. Allcare Health Management System, Inc.
134 S. Ct. 1744 (Supreme Court, 2014)
International Custom Products, Inc. v. United States
843 F.3d 1355 (Federal Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
In Re SECRETARY OF THE ARMY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-secretary-of-the-army-cafc-2024.