Zafer Construction Company v. United States

CourtUnited States Court of Federal Claims
DecidedDecember 30, 2020
Docket19-673
StatusPublished

This text of Zafer Construction Company v. United States (Zafer Construction Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zafer Construction Company v. United States, (uscfc 2020).

Opinion

No. 19-673C (Filed: December 30, 2020)

**********************

ZAFER CONSTRUCTION COMPANY, Contracts; Contract Disputes Act, 41 U.S.C. Plaintiff, §§ 7101-7109 (2018); delay; disruption; v. changes; limitations period for making claims. THE UNITED STATES,

Defendant.

Sam Z. Gdanski, Teaneck, NJ, for plaintiff.

Robert R. Kiepura, Trial Counsel, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, DC, with whom were Ethan P. Davis, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Steven J. Gillingham, Assistant Director, for defendant. James D. Stephens, United States Army Corps of Engineers, Engineer Trial Attorney, of counsel.

OPINION

BRUGGINK, Judge.

This is an action brought by plaintiff, Zafer Construction Company (“Zafer”), a government contractor, pursuant to the Contract Disputes Act (“CDA”). 41 U.S.C. §§ 7101-7109 (2012). Pending is defendant’s motion to dismiss plaintiff’s complaint for failure to state a claim upon which relief can be granted. The motion is fully briefed. Oral argument is unnecessary. For the reasons explained below, we grant the government’s motion to dismiss because plaintiff did not present its claim to the contracting officer for decision within the limitations period of the CDA. BACKGROUND

On June 24, 2008, the United States, acting through the Army Corps of Engineers (“USCE”) entered into a contract with Zafer Construction Company for the Bagram Public Works Utilities Contract on the Bagram Air Base in Bagram, Afghanistan (“project”). 1 Under the project, Zafer was to design and build base-wide public work utilities including storm water collection systems, wastewater collection transmission systems, and water distribution and transmission systems for a contract price of $40,720,493.00.

Following completion of the project, Zafer submitted to the Contracting Officer (“CO”) a Request for Equitable Adjustment (“REA”) on September 10, 2013, and an amended REA on December 17, 2014, seeking additional payments in the total amount of $6,791,155.63. Four years later, on February 7, 2018, Zafer filed a certified claim with the CO. Complaint Ex. 4 at 1 (ECF No. 1-4 at 1). The CO’s final decision (“COFD”), submitted on May 9, 2018, denied the relief requested because the officer found that the claim was time-barred under 41 U.S.C. § 7103(a)(4)(A), which requires that claims must be submitted to the CO within six years of accrual.

Zafer filed its complaint here on May 7, 2019, basing its claim on the CDA. The government has filed a motion to dismiss under Rule 12(b)(6), alleging that Zafer failed to meet the presentment requirement of the CDA because it neglected to submit a certified claim within six years of claim accrual.

Zafer has extensive experience with other contracts in Bagram, Afghanistan. In its complaint, Zafer describes the unique difficulties of working on projects there. The timing of construction and the shipment of materials had to be perfect to avoid going over budget. The materials were often shipped from the United States, and once the materials entered Afghanistan, had to make their way through border and base security, a process could take weeks or months. Zafer alleges that it suffered damages in the current contract for similar delays, along with constructive changes attributable to the United States.

Zafer divides its claimed delays into four different periods, corresponding to its Critical Path Method (“CPM”) schedule updates or project milestone events. The four periods are as follows:

1 The contract number is W917ER-08-C-0027.

2 1. Period 1: September 24, 2009 Baseline Schedule through April 13, 2010 CPM schedule update. Zafer alleges that delays in this period added 10 days to the schedule. 2. Period 2: April 13, 2010 CPM schedule update through September 24, 2010 CPM Project status update. Zafer alleges that delays during this period added 178 days to the schedule; 3. Period 3: September 24, 2010 CPM Project status through June 29, 2011. Zafer alleges that delays in this period added 207 days to the schedule; and 4. Period 4: June 29, 2011 through July 3, 2012, actual Project completion. Zafer alleges that delays in period 4 added 224 days to the schedule.

Complaint at 4. 2

In total, the four periods embraced an additional 619 days of claimed delay to the project. Zafer contends that the government agreed in writing to time extensions totaling 378 days covering the period from October 23, 2010 to November 22, 2011. These time extensions were incorporated in the contract through three separate Contract Modifications: Modification B0006 (Bilateral) for 133 days, Modification B0014 (Bilateral) for 98 days, and Modification P0002 (Unilateral) for 147 days.

According to Zafer, the USCE issued the modifications to add time to the schedule while specifically reserving for a later date the parties’ negotiating positions concerning pricing of overhead and other delay costs. Zafer attached Modifications B0006 and B0014 as exhibits to its complaint. Although Zafer alleges that Modification B0006 states that “related impacts costs . . . will be negotiated at a later date,” Complaint at 6, the page with this statement is not included in the exhibit. Modification B0014 does include language stating that related impacts costs will be negotiated at a later date. Zafer states that Modification P0002 also included language that the parties would negotiate overhead costs at a later date, although that modification is not included as an exhibit.

Zafer alleges that there were further delays, for which Zafer is not responsible, and which were not covered by the contract modifications listed above. Many of these delays allegedly took place in period four and are blamed on the government’s failure to accept the turnover of the project at

2 Neither the complaint nor the attached materials explain what triggers the ends and the beginnings of these four periods.

3 completion or to outside causes including terrorism and protests, for which Zafer alleges the government is contractually responsible.

Zafer also alleges in its complaint that constructive changes arose as a result of the government’s direction that Zafer perform additional change order work which required Zafer to adhere to government demands which were not within the scope of the contract. In Zafer’s amended REA, these constructive changes have been listed under the following categories, among others: utility diggings, relocation of sewer main, repair of damages by others to completed works, additional works beyond contract scope, additional travel and extended service durations by supervisors, additional communication line, PVC Air distribution pipes, operation and maintenance of completed construction.

Zafer initially submitted an REA on September 10, 2013 3 and then an amended one on December 17, 2014. Zafer explains that the amended REA “combines the initial REA documents and all subsequent revisions, documents, backups, further clarifications/analysis prepared and submitted by Zafer.” Complaint Ex. 1 at 9 (December 2014 REA). 4 The September and December REA both included the following language, “This REA is submitted so that the parties can engage in immediate discussions and negotiations to mutually amicably resolve this request” to resolve the extended overhead costs for the delays and constructive changes. Complaint Ex. 1 at 9. 5 Both REAs contain the following certification, “I, Önder Tümer, certify this REA of $6.791.155,63 submitted in a Request for an Equitable Adjustment under Contract No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Zafer Construction Company v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zafer-construction-company-v-united-states-uscfc-2020.