The Pike Company, Inc. v. Universal Concrete Products, Corp.

CourtDistrict Court, W.D. New York
DecidedMarch 10, 2021
Docket6:17-cv-06365
StatusUnknown

This text of The Pike Company, Inc. v. Universal Concrete Products, Corp. (The Pike Company, Inc. v. Universal Concrete Products, Corp.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Pike Company, Inc. v. Universal Concrete Products, Corp., (W.D.N.Y. 2021).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF NEW YORK ___________________________________

THE PIKE COMPANY, INC.,

Plaintiff, DECISION AND ORDER v. 6:17-CV-06365 EAW UNIVERSAL CONCRETE PRODUCTS, INC.,

Defendant.

___________________________________

MARIST COLLEGE,

Plaintiff-Intervenor, v. UNIVERSAL CONCRETE PRODUCTS, INC.,

Defendant. ___________________________________

INTRODUCTION This action involves disputes arising out of the construction of dormitory buildings on the campus of Plaintiff-Intervenor Marist College (“Marist”) in Poughkeepsie, New York. Plaintiff The Pike Company, Inc. (“Pike”), the general contractor for the construction project, claims in its amended complaint that defendant Universal Concrete Products Corp. (“UCP”), its subcontractor, materially breached the terms of the parties’ subcontract and caused the improper encumbrance of the project property with mechanic’s liens. (Dkt. 7). Pike seeks damages for breach of contract, unjust enrichment, and violations of the New York Lien Law, and a declaration that the lien filed by UCP was invalid. (Id.). UCP denies Pike’s allegations and asserts counterclaims for breach of

contract (both direct claims and as a third-party beneficiary), unjust enrichment/quantum meruit, misappropriation of trade secrets in violation of the Pennsylvania Trade Secrets Act, 12 Pa. Cons. Stat. Ann. § 5301 et seq. (“PUTSA”), and tortious interference with prospective business relationships. (Dkt. 29). Presently before the Court are competing summary judgment motions filed by the

parties. UCP seeks summary judgment on its first counterclaim “for the balance due of the Subcontract price,” it seeks summary judgment dismissing the amended complaint “in its entirety,” including dismissing the third, fourth, fifth and sixth causes of action “to the extent that such causes of action seek damages relating to any alleged delay,” and it seeks to strike as inadmissible Pike’s expert report prepared by Richard Merkhofer. (Dkt. 65).

Pike moves for partial summary judgment seeking dismissal of UCP’s fourth and fifth counterclaims. (Dkt. 68). For the reasons set forth below, UCP’s motion to strike Mr. Merkhofer’s expert report is denied, UCP’s motion for summary judgment is denied except as to Pike’s fifth cause of action seeking to declare UCP’s mechanic’s lien invalid, and Pike’s motion for

partial summary judgment in its favor on UCP’s fourth and fifth counterclaims is granted. BACKGROUND1 Pike entered into an agreement with Marist on May 1, 2015, to become the general contractor for a two-building residence hall complex located on the Marist College North Campus in Poughkeepsie, New York. (Dkt. 68-3 at ¶ 6; Dkt. 78 (no response)). The project

was designated as the first phase of a two phase dormitory project (“Phase I” and “Phase II,” respectively, and collectively the “Project”). (Id.). During the Project, the two buildings of Phase I were referred to as “Building A” and “Building B.” (Dkt. 68-3 at ¶ 7;

1 The facts set forth in this Background section are undisputed unless otherwise indicated. Notably, in response to Pike’s Statement of Undisputed Facts in support of its motion for partial summary judgment dismissing UCP’s fourth and fifth counterclaims (Dkt. 68-3 (“Pike’s Statement”)), UCP submitted a “counterstatement” of undisputed facts (Dkt. 78) wherein it contested some of the facts set forth in Pike’s Statement but failed to respond to a large number of the paragraphs in Pike’s Statement. This District’s Local Rule 56(a)(2) provides that the “papers opposing a motion for summary judgment shall include a response to each numbered paragraph in the moving party’s statement, in correspondingly numbered paragraphs and, if necessary, additional paragraphs containing a short and concise statement of additional material facts as to which it is contended there exists a genuine issue to be tried.” See also Fed. R. Civ. P. 56(e)(2) (when a party fails to properly support an assertion of fact or fails to address another party’s assertion of fact, the court may consider the fact undisputed for purposes of the motion). UCP failed to comply with this requirement. As a result, consistent with the Local Rule, and because the unanswered paragraphs in Pike’s Statement are supported by the record, Holtz v. Rockefeller & Co., 258 F.3d 62, 73-74 (2d Cir. 2001), the Court deems the facts therein admitted by UCP. See N.Y. State Teamsters Conference Pension & Ret. Fund v. Express Servs., Inc., 426 F.3d 640, 648-49 (2d Cir. 2005); Gubitosi v. Kapica, 154 F.3d 30, 31 n. 1 (2d Cir. 1998). In addition to Pike’s Statement and UCP’s response in connection with Pike’s partial summary judgment motion, the Court has also considered UCP’s Statement of Undisputed Facts submitted in support of its motion for summary judgment (“UCP’s Statement”) (Dkt. 65-1) and Pike’s response thereto and counterstatement (Dkt. 79), as well as all of the exhibits attached and referenced to the parties’ statements and responses. The Court notes that UCP’s Statement almost exclusively relies on an affidavit of UCP’s President, Donald Faust, Jr. (“Faust”) (Dkt. 65-6), as opposed to the deposition testimony elicited during discovery. Dkt. 78 (no response)). Phase II involved the construction of two buildings that were referred to as “Building C” and “Building D.” (Id.). The Project Architect for both Phase I and Phase II was Robert A.M. Stern Architects, LLP. (Dkt. 65-1 at ¶ 16; Dkt. 79 at ¶ 16).

The architectural design contemplated using pre-cast concrete wall panels with a natural stone veneer for the exterior walls, so that the new buildings would blend in with existing campus buildings. (Dkt. 65-1 at ¶ 17; Dkt. 79 at ¶ 17). Marist originally intended Kirchhoff-Consigli Construction Management (“Consigli’) to serve as the construction manager for Phase I and Phase II. (Dkt. 68-3 at

¶ 14; Dkt. 78 (no response)). Due to concerns with Consigli’s price and schedule, Marist decided to accept general contracting bids for Phase I instead. (Dkt. 68-3 at ¶ 15; Dkt. 78 (no response)). While Consigli was negotiating with Marist to be construction manager on the Project, Marist had begun preliminary work with UCP for Phase I’s precast concrete wall panels, including the production of shop drawings and mock-ups. (Dkt. 68-3 at ¶ 16;

Dkt. 78 (no response)). UCP specializes in precast concrete exterior wall cladding, and produces both architectural and structural precast panels. (Dkt. 68-3 at ¶ 8; Dkt. 78 (no response)). After deciding to solicit bids from general contractors for Phase I of the Project, Marist issued an invitation to bid specifying that a preconstruction agreement arrangement existed with UCP for the fabrication and installation of architectural precast panels and the

balance of the contract between UCP and Marist would be assigned to the successful bidder. (Dkt. 68-3 at ¶ 17; Dkt. 78 (no response)). Four general contractors bid the Project to serve as general contractor for Phase I, including Consigli and Pike. (Dkt. 68-3 at ¶ 18; Dkt. 78 (no response)). The bid process resulted in Marist selecting Pike to be the general contractor for Phase I. (Id.). Pike entered into a Master Subcontract Agreement with UCP on May 29, 2015 (“the

MSA”). (Dkt. 68-3 at ¶ 9; Dkt. 78 (no response); see Dkt. 69-2 (copy of the MSA)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riegel v. Medtronic, Inc.
451 F.3d 104 (Second Circuit, 2006)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
Riegel v. Medtronic, Inc.
552 U.S. 312 (Supreme Court, 2008)
Licci Ex Rel. Licci v. Lebanese Canadian Bank SAL
672 F.3d 155 (Second Circuit, 2012)
Laura Holtz v. Rockefeller & Co., Inc.
258 F.3d 62 (Second Circuit, 2001)
Premium Mortgage Corp. v. Equifax, Inc.
583 F.3d 103 (Second Circuit, 2009)
Ashland Management Inc. v. Janien
624 N.E.2d 1007 (New York Court of Appeals, 1993)
UMG Recordings, Inc. v. Lindor
531 F. Supp. 2d 453 (E.D. New York, 2007)
R.F.M.A.S., Inc. v. So
748 F. Supp. 2d 244 (S.D. New York, 2010)
EarthWeb, Inc. v. Schlack
71 F. Supp. 2d 299 (S.D. New York, 1999)
Capital Z Financial Services Fund II, L.P. v. Health Net, Inc.
43 A.D.3d 100 (Appellate Division of the Supreme Court of New York, 2007)
Krock v. Lipsay
97 F.3d 640 (Second Circuit, 1996)
Gubitosi v. Kapica
154 F.3d 30 (Second Circuit, 1998)
Washington v. Kellwood Co.
105 F. Supp. 3d 293 (S.D. New York, 2015)
M.B. v. CSX Transportation, Inc.
130 F. Supp. 3d 654 (N.D. New York, 2015)
Broker Genius, Inc. v. Zalta
280 F. Supp. 3d 495 (S.D. New York, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
The Pike Company, Inc. v. Universal Concrete Products, Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-pike-company-inc-v-universal-concrete-products-corp-nywd-2021.