Rex Systems Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 15, 2016
DocketASBCA No. 59624
StatusPublished

This text of Rex Systems Inc. (Rex Systems Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rex Systems Inc., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Rex Systems Inc. ) ASBCA No. 59624 ) Under Contract No. SPRMM1-12-P-YH36 )

APPEARANCE FOR THE APPELLANT: Ms. Nicole L. Kornesczuk President

APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq. DCMA Chief Trial Attorney Kara M. Klaas, Esq. Trial Attorney Defense Contract Management Agency Chantilly, VA

OPINION BY ADMINISTRATIVE JUDGE PROUTY

In this appeal, we consider what compensation appellant, Rex Systems, Inc. (Rex), is entitled to for the government's termination of its contract for convenience. Although the contracting officer made an offer to settle Rex's termination costs, Rex alleges that the government imposed significant costs upon it through delay during the performance period and seeks payment of an amount greater than it would have been entitled to had the contract been completed in a timely manner. The parties also dispute Rex's entitlement to other components of its termination claim. For the most part, the government prevails, although Rex is entitled to some relief, as will be detailed below.

The parties waived a hearing and submitted the case upon the record pursuant to Board Rule 11. We granted Rex's request to have the declaration of its corporate officer Nicole Komesczuk (which had been previously submitted in tab 9 of its supplement to the Rule 4 file) stand in for its opening brief, rather than requiring it to submit a more formal brief. Ms. Komesczuk also filed a reply brief. The government filed an opening brief, but did not file a reply, stating that it believed that its opening brief addressed all the issues raised in the Kornesczuk affidavit.

FINDINGS OFF ACT

1. On 2 August 2012, the Defense Logistics Agency (DLA) awarded to Rex Contract No. SPRMM1-12-P-YH36 (the contract) in the amount of$42,096 for the production of certain semiconductor devices (R4, tab 1). These devices were electronic assemblies utilized to support the MK-49, a Department of Defense legacy system and provided electro-magnetic pulse protection (app. supp. R4, tab 9, ~ 5, tab 6 (provision of electro-magnetic pulse protection)). Rex had delivered the same assemblies for DLA in a previous contract (app. supp. R4, tab 9, ~ 10).

2. The contract required first article testing prior to the delivery of the eight devices (R4, tab 1 at G-2). It thus included the following schedule:

Submission of test procedures for first article and production lot items: 60 days after contract award.

Approval oftest procedures: 120 days after contract award.

Submittal of first article test sample and first article test report: 180 days after contract award.

Approval of first article: 270 days after contract award.

Shipment of production quantity and production lot test report: 360 days after contract award.

(Id.)

3. The contract also contained a number of standard Federal Acquisition Regulation (FAR) clauses, including FAR 52.213-4, TERMS AND CONDITIONS- SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL ITEMS (OCT 2010), paragraph (f) Terminations clause (R4, tab lat G-18); and FAR 52.209-3, FIRST ARTICLE APPROVAL-CONTRACTOR TESTING (SEP 1989) (id. at G-20-21 ).

4. Relevant here, the termination clause in FAR 52.213-4(f) provides, in part, that, upon notification of termination for the convenience of the government:

[T]he Contractor shall immediately stop all work ... and ... cause ... all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate ... have resulted from the termination.

(See R4, tab 1 at G-18)

2 5. Also relevant to this matter, are two portions of the First Article Testing clause, FAR 52.209-3, the first of which provides in part:

(b) The Contractor shall submit the first article test report within 180 calendar days from the date of this contract.... Within 90 calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor... ofthe conditional approval, approval, or disapproval of the first article ....

( f) If the Government does not act within the time specified in paragraph (b ) ... the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.

(R4, tab 1 at G-20)

6. The second material portion of the First Article Testing clause, FAR 52.209-3(g), relates to recoverable costs and warns that:

Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for ... termination settlements if the contract is terminated for the convenience of the Government.

(R4, tab 1 at G-20-21)

7. The contract also contained a standard Navy supplemental provision regarding pre-manufacturing test procedures (NAVSUPWSSIA05) further limiting the government's liability in a termination settlement for the contractor's acquisition of materials, which provided that:

Prior to approval of [first article test procedures], the acquisition of materials or components for ... the contract items (including first article samples) shall be at the sole risk of the contractor, and costs incurred on account thereof shall not be allocable to this contract...for the

3 purpose of termination settlement if this contract is terminated for convenience of the Government prior to approval of the [first article test procedure].

(R4, tab 1 at G-16)

8. In light of its having furnished the same items to the government in an earlier contract, on 14 August 2012, Rex requested that the government waive the contract's first article testing requirement (app. supp. R4, tab 1, tab 9, if 15). On 19 September 2012, the government denied this request (app. supp. R4, tab 1).

9. Before receiving the government's response to the first article test waiver request, on 30 August 2012, Rex contacted a parts supplier (USI Electronics) and ordered the production materials (the diodes) necessary to construct the first article and the other seven semiconductor devices required by the contract (supp. R4, tab 24 at G-195-96). Rex's pre-bid estimate noted that the diodes required a 24-week lead time (R4, tab 23 at G-170-71 ). Nevertheless, the materials were requested for delivery on 15 October 2012, and were received by Rex on 24 September 2012 (id. at G-195-97). The cost of these items was $8,979 (id.).

10. On 27 September 2012, Rex timely submitted its first article and production test procedures to the government for its approval (app. supp. R4, tab 2).

11. Without waiting for government approval of its test procedures, on 28 October 2012, Rex built the first article semiconductor device and conducted tests upon it (app. supp. R4, tab 5, see also tab 6 (photograph of completed semiconductor device)).

12. The government did not approve the proposed testing procedures within 120 days of contract award (or by 30 November 2012), as required by the contract. Rex contacted the government on 6 December 2012 and inquired about the status of the approval (app. supp. R4, tab 3 at 4).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melka Marine, Inc. v. United States
187 F.3d 1370 (Federal Circuit, 1999)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
P.J. Dick Inc. v. Principi
324 F.3d 1364 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Rex Systems Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rex-systems-inc-asbca-2016.