Alderman Building Company, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMay 21, 2020
DocketASBCA No. 58082
StatusPublished

This text of Alderman Building Company, Inc. (Alderman Building Company, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alderman Building Company, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Alderman Building Company, Inc. ) ASBCA No. 58082 ) Under Contract No. N40085-09-D-5321 )

APPEARANCE FOR THE APPELLANT: Marilyn H. David, Esq. D’Iberville, MS

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Genifer M. Tarkowski, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE YOUNGER

In this sponsored appeal regarding a contract for the renovation and interior repair of a building, Alderman Building Co., Inc. (Alderman), seeks unabsorbed home office overhead on behalf of its electrical subcontractor relating to performance delays. The issues are heavily fact-intensive, and we have previously denied motions for summary judgment filed by both parties. After disposition of their summary judgment motions, the parties elected to submit the appeal on the record pursuant to our Rule 11 and supplemented the record with additional documents. Both entitlement and quantum are before us for decision. We sustain the appeal in part.

FINDINGS OF FACTS

A. Contract and Subcontract

1. By date of March 27, 2009, the Navy awarded a Task Order for supplies or services under Contract No. N40085-09-D-5321 to Alderman for renovations of the interior, repairs to building systems, and incidental related work, on building M403 at Marine Corps Base Camp Lejeune, North Carolina (R4, tab 1 at 1-7). The Task Order provided that “[t]he entire work . . . shall be completed by 3/22/2010” (id. at 7).

2. The contract contained various standard clauses, including Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002); FAR 52.242-14, SUSPENSION OF WORK (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 5.6 at 958). 3. By date of April 8, 2009, Alderman entered into a subcontract with Big John’s Electric Co., Inc. (Big John’s), for labor, equipment, materials, and supplies for specified portions of the interior repairs to the building (R4, tab 5.12 at 995). Big John’s was an electrical subcontractor that performed approximately 90 percent of its work on Federal projects (ex. A-1, tab 40 ¶¶ 2-27). The subcontract provided that “time is of the essence,” and that Big John’s was to “begin work within 7 days after notification” by Alderman (R4, tab 5.12 at 996).

B. Delays

4. Approximately two months after award, by email dated May 27, 2009, the Navy directed Alderman to “[c]ontinue to get all of your submittals approved and ready to start construction and we will move the [contract completion date]” accordingly when we have a nailed down work start date” (R4, tab 5.13). We find that the Navy expected the work to be initiated with full force by all parties.

5. While the solicitation provided that the contract start date would be 10 days after award (R4, tab 5.6 at 948), we find that contract performance was characterized by repeated government-caused delays that aggregated to 263 days and pushed the start work date into February 2010. The delays were chiefly caused by the unavailability of new facilities for the existing tenants in building M403 (R4, tab 6 at 1107). The multiple delays to the start date were memorialized as follows:

Date Document Start Date Record Citation January 13, 2009 Solicitation 10 calendar days R4, tab 5.6 at 948 after award. March 10, 2009 Solicitation “Work may not R4, tab 1 at 21 Amendment begin . . . until No. 0003 01 June 2009.” May 27, 2009 Email, Navy “Lets plan on R4, tab 5.13 project engineer starting” in mid- to Alderman July 2009 “time Project Manager period.”* June 19, 2009 Email, Navy Afraid construction R4, tab 5.14 project engineer may be pushed to Alderman back to August Project Manager 2009.

2 July 1, 2009 Email, Navy “Lets set the new R4, tab 5.15 project engineer start date at 15 to Alderman October” 2009.* Project Manager July 7, 2009 CO Suspension Suspension “until R4, tab 5.16 Letter to further notice.” Alderman July 9, 2009 Email, Alderman Project start date R4, tab 5.17 Project Manager “suspended until to Subcontractors October” 2009.*

September 30, 2009 Email, Alderman “[N]ew start date R4, tab 5.18 Project Manager for the project is to Subcontractors 12/15/09.” November 18, 2009 Email, Navy “We are still on for R4, tab 5.20 project engineer 15 December to Alderman [2009] at this Project Manager point.”*

December 8, 2009 Email, Navy “[N]o earlier than R4, tab 5.21 project engineer the 1st of February to Alderman [2010] for Project Manager Starting.”

December 8, 2009 Email, Alderman “Project will not be R4, tab 5.22 Project Manager starting now until to Subcontractors February 1st [2010], at the earliest.”* February 2, 2010 Email, Navy Some tenants not R4, tab 5.28 project engineer moving out “until to Alderman sometime, probably Project Manager after the 9th”; others will vacate on the 8th.

*Underscoring in original.

6. In his July 7, 2009 letter to Alderman, the contracting officer had advised that, pursuant to the Suspension of Work clause (see finding 2), “you are hereby

3 directed to suspend all work under the referenced contract,” with an exception not relevant here, “until further notice.” The contracting officer’s cited reason was “Government delays in vacating the premises.” (R4, tab 5.16 at 1004) The contracting officer’s notice did not contain any explicit direction to Alderman to place its work force on standby during the suspension period.

7. After the delays set forth in finding 5, above, Alderman began contract performance on February 19, 2010 (ex. A-1 at 2). Big John’s began performance of its subcontract on the same date and completed work on October 28, 2010 (ex. A-1, tab 40 ¶¶ 4-5).

8. In a three-part email string dated March 17, 2010, the Navy project engineer agreed to submit Alderman’s requested 270-day time extension in the contract completion date to the contracting officer (R4, tab 4.11).

C. Claims Sponsorship Agreement

9. By date of August 18, 2011, Alderman and Big John’s executed a Claims Sponsorship Agreement (R4, tab 5.57). In the introductory paragraph of that agreement at issue here, the two parties provided:

WHEREFORE, pursuant to the terms of the Subcontract, and this Agreement, Contractor and Subcontractor agree that the Owner is the ultimate responsible party to pay for the Subcontractor’s and Contractors’ claims, and further agree that it is the intent of this Agreement to reserve and preserve to Subcontractor the right to have its claims prosecuted in Contractor’s name against the Owner, in accordance with this Agreement.

(R4, tab 5.57 at 1101) Consistent with that stated intent, the agreement provided in paragraph 1 that “Contractor will pay any Subcontractor’s sums due Subcontractor with respect to its claims promptly upon payment to Contractor by the Owner” (id.). It also provided in paragraph 2(a) that “[t]he claims of Subcontractor will be included in a claim to be presented by Contractor and Subcontractor in the name of Contractor against the Owner before the Contracting Officer . . .” (id.).

10. We find no evidence in the record that Big John’s released Alderman from liability to Big John’s for any costs of performing its subcontract.

4 11. By date of February 20, 2012, Alderman’s president executed a final release under the prime contract providing that, in consideration of a specified sum, Alderman:

[D]oes, and by the receipt of said sum shall, for itself, its successors and assigns, remise, release and forever discharge the Government, its officers, agents, and employees, of and from all liabilities, obligations and claims whatsoever in law and in equity under or arising out of said contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Alderman Building Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/alderman-building-company-inc-asbca-2020.