Alderman Building Company, Inc.

CourtArmed Services Board of Contract Appeals
DecidedDecember 9, 2014
DocketASBCA No. 58082
StatusPublished

This text of Alderman Building Company, Inc. (Alderman Building Company, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alderman Building Company, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Alderman Building Company, Inc. ) ASBCA No. 58082 ) Under Contract No. N40085-09-D-5321 )

APPEARANCE FOR THE APPELLANT: Marilyn H. David, Esq. Biloxi, MS

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Genifer M. Tarkowski, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE YOUNGER ON APPELLANT'S MOTION FOR PARTIAL SUMMARY JUDGMENT REGARDING (1) UNABSORBED OVERHEAD UNDER ALTERNATIVE TO EICHLEA Y FORMULA AND (2) STANDBY LABOR COSTS AND RESPONDENT'S CROSS-MOTION FOR SUMMARY JUDGMENT

In this sponsored appeal regarding a contract for the renovation and interior repair of a building, the contractor, Alderman Building Company, Inc. (Alderman), has moved for partial summary judgment regarding pre-performance unabsorbed overhead under an alternative method to the Eichleay formula, and regarding standby labor costs. In response to the motion, the Navy has opposed and cross-moved for summary judgment, generally contending that the facts do not bring the case within a recognized exception to the Eichleay formula. We grant Alderman's motion in part and deny the Navy's cross-motion.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS

1. By date of27 March 2009, the Navy awarded a Task Order for supplies or services under Contract No. N40085-09-D-5321 to Alderman for renovations of the interior, repairs to building systems, and incidental related work, on a building at Camp Lejeune, North Carolina (R4, tab 1 at 1, 3 of 6). The Task Order provided that "[t]he entire work ... shall be completed by 3/22/2010" (id. at 3 of 6).

2. The contract contained various standard clauses, including Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002); FAR 52.242-14, SUSPENSION OF WORK (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 5.6 at 11 of31). 3. By date of 8 April 2009, Alderman entered into a subcontract with Big John's Electric Co., Inc. (Big John's), for labor, equipment, materials, and supplies for specified portions of the interior repairs to the building (R4, tab 5.12 at 1). The subcontract provided that "time is of the essence," and that Big John's was to "begin work within seven (7) days after notification" by Alderman (id. at 2).

4. Contract performance was characterized by repeated government-caused delays in starting work. Alderman and Big John's were delayed because new facilities for the existing tenants in the building were not available (R4, tab 6 at 1). There were multiple delays to the project start date, as memorialized in the following exchanges:

Date Document Start Date Record Citation 13 January 2009 Solicitation 10 calendar days R4, tab 5.6 at 1 of31 after contract award. 10 March 2009 Solicitation "Work may not R4, tab 1 at 10 Amendment begin ... until 01 No. 0003 June 2009." 27 May 2009 Email, OICC to "Lets nlan on R4, tab 5.13 Alderman Project starting" in mid- Manager July 2009 "time oeriod."* 19 June 2009 Email, OICC to Afraid construction R4, tab 5.14 Alderman Project may be pushed Manager back to August 2009. 1July2009 Email, OICC to "Lets set the new R4, tab 5.15 Alderman Project start date at Manager 15 October" 2009. * 7 July 2009 CO Suspension Suspension "until R4, tab 5.16 Letter to Alderman further notice." 9 July 2009 Email, Alderman Project start date R4,tab5.17 Project Manager to "susnended until Subcontractors October" 2009. * 30 September 2009 Email, Alderman "[N]ew start date R4,tab5.18 Project Manager to for the project is Subcontractors 12/15/09." 18 November 2009 Email, OICC to "We are still on for R4, tab 5.20 Alderman Project 15 December at this Manager noint."* 8 December 2009 Email, OICC to "[N]o earlier than R4, tab 5.21 Alderman Project the 1st of February Manager [2010] for Starting." 2 8 December 2009 Email, Alderman "Project will not be R4, tab 5.22 Project Manager to starting now until Subcontractors February 1st [201 O], at the earliest."* 2 February 2010 Email, OICC to Some tenants not R4, tab 5.28 Alderman Project moving out "until Manager sometime, probably after the 9th"; others will vacate on 8th.

*Underscoring in original.

5. In his 7 July 2009 letter to Alderman, the contracting officer had advised that, pursuant to the Suspension of Work clause (see statement 2), "you are hereby directed to suspend all work under the referenced contract," with an exception not relevant here, "until further notice." The contracting officer's cited reason was "Government delays in vacating the premises." (R4, tab 5.16 at 2)

6. Alderman eventually began contract performance on 19 February 2010 (Expert Report of Roger K. Seals (Seals rpt.) at 2). Big John's ultimately began performance of its subcontract on the same date (R4, tab 5.38 at 2, tab 5.50 at 2) and completed work on 28 October 2010 (Seals rpt., tab 40, 1st Affidavit of Michael Dougherty (Dougherty aff.) ifif 4, 5).

7. By letter to the contracting officer dated 18 August 2011, Alderman submitted a claim for $20,518 on behalf of Big John's for government delay in starting work (R4, tab 5).

8. By date of 19 January 2012, the contracting officer denied the claim in its entirety (R4, tab 6). Alderman thereafter brought this timely appeal.

9. Alderman's lengthy complaint is in 15 counts. Styling the counts as Alderman does, we summarize those alleging entitlement to Eichleay recovery and standby as follows:

(a) Count I: Ordered and Constructive Suspensions of Work. In general, Alderman alleges that the Navy "delayed the start of Big John's work, by delaying the Notice to Proceed and by successively revising the date the job site would be available and work could start" (compl. if 27). Alderman then makes particular allegations regarding the delays in the start date, and alleges that the delays were unreasonable, that they were due to the Navy's convenience, and alleges entitlement to extended and unabsorbed home office overhead costs on behalf of Big John's (id. ifif 28-46).

3 (c) Count III: Eichleay Claim and Prerequisites. In general, Alderman alleges that it meets the requirements for application of the Eichleay formula, "[e]ven with use of an alternate method of computation" (id. if 79).

Alderman also alleges entitlement to recovery of unabsorbed overhead using a methodology other than the Eichleay formula, including the Changes clause (id. if 125) and quantum meruit (id. iii! 131-35).

10. The Navy cites three email exchanges that are said to show that it did not require Alderman to resume work immediately and at full speed (Respondent's Cross Motion for Summary Judgment and Response in Opposition to Appellant's Motion for Partial Summary Judgment Regarding (1) Unabsorbed Overhead Under Alternative to Eichleay Formula and (2) Standby Labor Costs (gov't opp'n) at 9-10, 13). We find that none are conclusive. The first cited exchange is dated 1 February 2010 between Alderman, Big John's, and the Navy. It was, by its terms, technical in nature, initiated by the subcontractor's expression of "a few concerns with a partial tum over of the building" regarding "several circuits." (R4, tab 4.5) The second cited exchange is between the OICC and Alderman on 28 January and 2 February 2010 regarding "New Developments." It relates to arrangements to have "temp. power going before the start date," to avoid consuming time on such arrangements when work ultimately began. (R4, tab 4.6) The third cited exchange is between the OICC and Alderman on 1-2 February 2010 regarding the cost of doing inside work while the building was partially occupied, as well as tracking "contractual impacts ... due to the government delays [for] a revised cost proposal" (R4, tab 5.27).

11. Alderman has tendered an expert report from Roger K.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
P.J. Dick Inc. v. Principi
324 F.3d 1364 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Alderman Building Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/alderman-building-company-inc-asbca-2014.