OPINION
HARKINS, Judge:
Everett Plywood Corporation (plaintiff) has applied for attorney fees and expenses under the Equal Access to Justice Act (EAJA)1 as the prevailing party in a breach of contract action involving a timber cutting contract. The contract, awarded by the Forest Service of the Department of Agriculture, was to clearcut and purchase timber from four designated logging units in the Mt. Baker National Forest, Snohomish County, Washington (the ARM timber sale). The contract was canceled, effective November 9, 1973, by the Secretary of Agriculture for environmental reasons.
Plaintiff’s petition (now complaint) was filed in the United States Court of Claims on June 12,1975, and a 6-day trial was held in February 1978. The trial judge’s opinion, filed December 28, 1979, recommended that defendant was not liable for breach of contract on the ground that, under the doctrine of frustration of contract purpose, the Secretary’s November 9, 1973, cancellation was lawful in the exercise of responsibility for the care and preservation of the environment in Mt. Baker National Forest. In an opinion dated May 20, 1981,2 the Court of Claims held that defendant’s unilateral termination of contract was a breach that entitled plaintiff to recover compensable costs and breach damages by the formula set out in 36 C.F.R. § 223.9(a)(5) (1980), entered judgment for plaintiff on entitlement, and remanded the case to the trial division to calculate damages, without interest.
On October 1, 1981, the effective date of the EAJA, this case was pending in the trial division of the Court of Claims; and on October 1, 1982, it was transferred to the United States Claims Court pursuant to section 403(d) of the Federal Courts Improvement Act of 1982.3 On May 16, 1983, after a prolonged period of negotiation, pursuant to the stipulation of the parties, the United States Claims Court entered judgment for plaintiff in the sum of $370,000. The stipulation for entry of judgment reserved the position of the parties on the question of a claim under the EAJA.4 Plaintiff’s application for attorney fees and expenses was timely filed on June 15, 1983.
Defendant argues that the Claims Court lacks jurisdiction to award attorney fees, expenses and costs authorized by the EAJA because it is “not a court of the United States” established under Article III of the Constitution. Defendant’s contention has been considered, and rejected, by [708]*708the Federal Circuit with respect to cases that were pending in the Court of Claims on October 1,1981, the effective date of the EAJA, and transferred undecided to the Claims Court on October 1, 1982, pursuant to section 403(d) of the Federal Courts Improvement Act of 1982.5 Section 403(d) is not a transfer provision that requires an independent basis for decision. It provides that “Any matter pending before a commissioner of the United States Court of Claims on the effective date.... shall be determined by the United States Claims Court.” This language requires this court to enter a final judgment on plaintiff’s application for attorney fees which was ordered on August 31, 1982, to be filed.
Defendant urges that Ellis is not applicable to the facts of this case because the “matter” before the trial judge on October 1, 1982, was not a “cause of action” for attorney fees and expenses, but was the merits of the case in chief, the issue of damages. Defendant asserts that the cause of action for attorney fees did not accrue until entry of the money judgment on May 16, 1983, and, consequently, the attorney fees issue is not being determined pursuant to section 403(d). Defendant misses the point. The Federal Circuit opined in Ellis that nothing in the Improvement Act or in its legislative history suggests that a prevailing plaintiff would be divested of the opportunity to pursue an award of fees and costs because of the transfer provisions contained in the Act.6 Plaintiff’s eligibility to pursue attorney fees necessarily was part of the “matter” pending before the Court of Claims commissioner on September 30, 1982, and undecided by the Court of Claims on that date.
The EAJA provides in 28 U.S.C. § 2412(d)(1)(A) that attorney fees and other expenses may be awarded to the prevailing party in a civil action brought by or against the United States “in any court having jurisdiction of that action.” With respect to matters begun on or after October 1, 1982, the Claims Court clearly is vested with jurisdiction under 28 U.S.C. § 1491 over timber cutting contracts. This jurisdiction would include the power to award attorney fees and expenses on plaintiff’s application in this case.7
A prevailing party, other than the United States, in civil actions not sounding in tort brought by or against the United States, may be awarded attorney fees and expenses in the absence of a finding by the court that “the position of the United States was substantially justified or that special circumstances make an award unjust.”8 One purpose of the EAJA is “to diminish the deterrent effect of seeking review of, or defending against, governmental action.”
The Act specifies that an application for fees and expenses is to be submitted within 30 days of final judgment, with an itemized statement that shows actual time expended and rates used in computations. The definition of fees and expenses requires that expenses of expert witnesses be “reasonable” and that attorney fees be “reasonable”. The amount of fees are to be based upon “prevailing market rates” for the kind and quality of the services furnished. Attorney fees “shall not be awarded in excess of $75 per hour unless the court determines that an increase in the cost of living or a special factor, such as the limited availability of qualified attorneys for the proceedings involved, justifies a higher fee.”9
The content of the authority conferred by the EAJA to award attorney fees and expenses has been considered in a number of cases. The EAJA authorizes pay[709]*709ment of attorney fees and related expenses incurred before the effective date, October I, 1981, as well as those incurred after that date.10 The United States bears the burden of proving its position was substantially justified.11 The test for determining whether the Government’s position was substantially justified is one of reasonableness. Where the Government can show that its position had a reasonable basis both in law and in fact, no EAJA award can be made.12 In determining whether the position of the United States was substantially justified in a particular case, the position taken by the Government before the court is the subject of inquiry, not the position taken during the administrative action.13
A primary purpose of the EAJA is to eliminate legal expense as a barrier to challenges of unreasonable governmental action. Accordingly, attorney fees and expenses may be assessed against the Government for a separate phase or portion of the litigation in which the Government’s position lacks substantial justification, even though the Government may have adopted wholly reasonable positions in other parts of the case.14
This case on the question of substantial justification for defendant’s position falls into three distinct phases or periods: (1) I, the trial period, June 12,1975, to December 28, 1979; (2) II, the appeal period, December 28, 1979, to July 10, 1981 (plaintiff’s motion for clarification and/or amendment of opinion denied); and III, the damages period, July 10,1981, to June 15, 1983. Defendant has not shown that its litigating position during the trial period (I) and the damages period (III) was substantially justified.
Prior to the Secretary’s unilateral cancellation of the ARM sale, effective November 9, 1973, the Forest Service, in its administration of the ARM sale contract, had taken the position that such action would breach the contract and expose the Government to a claim of damages. The Deputy Chief of the Forest Service on June 6, 1972, had advised the Regional Forester that the Office of General Counsel and, informally, the Comptroller General, had confirmed that the ARM sale contract could not legally be modified in the circumstances. In the event that the contract was canceled upon completion of logging in unit No. 2, the Deputy Chief stated, such action would be a breach that would expose the Government to a claim for damages, to be processed through the Comptroller General or the United States Court of Claims. The letter further advised that, in order to expedite settlement of the claim, the Regional Forester should seek agreement as to the amount of the claim which will result from the breach. On September 13, 1972, the Deputy Chief advised the Regional Forester environmental damage could necessitate a suspension if a contract modification could not be negotiated. He noted that the ARM sale contract did not authorize suspension on environmental grounds, that the plaintiff had not breached any provisions of the contract, and that they were, in effect, suspending operations without cause.
Notwithstanding the Agriculture Department’s recognition that the Secretary’s cancellation had no support in the contract, plaintiff was forced to litigate its claim. During the trial period, defendant’s counsel refused to concede liability, but at the same time declined to present a defense. No effort was made to negotiate a settlement of the claim until the damages period.
[710]*710In pretrial preparation both parties identified disputed questions of fact on liability issues to be tried. Defendant maintained that cancellation of the contract on environmental grounds was justified and any damage recovery by plaintiff was precluded. Defendant’s counsel, however, agreed with plaintiff that all liability matters could be disposed of on the basis of documentary evidence. The question of the need to prepare and present evidence on liability issues was not resolved until the first day of trial, on February 7, 1978.15 Plaintiff at that time withdrew any challenge to factual support for the Forest Service’s conclusion that the timber sale cancellation was motivated by environmental concerns. Plaintiff accepted the proposition that the Forest Service motivation to unilaterally cancel the contract was unstable soil conditions caused by road construction and logging. Defendant agreed that the ARM sale contract did not provide for cancellation on environmental grounds.16
Nonetheless, defendant throughout the trial continued to refuse to concede liability.17 [711]*711Defendant made no effort to meet or rebut plaintiff’s evidence. Testimony was concerned with factual matters relative to damages only. Defendant called no witnesses and presented no evidence on liability issues; defendant called one witness, whose testimony was limited to Forest Service appraisal procedures. Defendant’s posttrial briefing did not address the question of liability to plaintiff; it was concerned solely with matters related to damages. In short from the inception of plaintiff’s case in the Court of Claims to the December 28, 1979, opinion of the trial judge, defendant presented no defense. The litigating posture of the United States was merely to put plaintiff to its proof. No effort was made to meet or rebut plaintiff’s case.
On the basis of the record in pretrial, at trial, and in posttrial briefing, defendant’s litigating posture during the trial period was unreasonable. Substantial justification for the defendant’s actions during the trial period has not been shown.
In the light of defendant’s refusal to concede liability while presenting no defense, and from independent consideration of the record, the trial judge sua sponte invoked the doctrine of frustration of purpose. Defendant was found not to have breached the contract because the contractual obligation had become incapable of being performed without rendering performance radically different and worthless to the Government. This argument had not been presented by either party. When the Appellate Division reviewed plaintiff’s exceptions to the findings and conclusion of the trial judge, defendant supported application of the doctrine of frustration of contract purpose. In addition, defendant advanced a new argument that had not been presented to the trial judge. This argument was that cancellation of the contract to protect the environment was in the nature of a sovereign act, akin to the operation of a public dam for the public good. The Court of Claims rejected both the frustration of purpose and sovereign act arguments.
Defendant’s litigating posture during the appeal period was reasonable. Accordingly, defendant’s position was substantially justified, and plaintiff is not entitled to recover under the EAJA during this period.
In its May 20, 1981, decision, the Court of Claims determined that plaintiff was entitled to recover compensable costs and breach damages by the formula in 36 C.F.R. § 223.9(a)(5) (1980). This formula for computation of claims on cancellation for environmental reasons had been promulgated in 1977, and utilized thereafter with respect to Forest Service contracts when applicable. Notwithstanding administrative experience with the policy and procedures involved in application of this formula, negotiations for a settlement of plaintiff’s damages were extended for an unreasonable period.
After the July 10, 1981, denial of plaintiff’s motion for clarification and/or amendment of the May 20, 1981, decision, counsel were directed, on July 13, 1981, to confer and to report (on or before August 14,1981) the status of their efforts to stipulate or otherwise agree upon the amounts to be recovered by plaintiff. After a series of time extensions, plaintiff’s statement on damages for its claims was presented to defendant on December 10, 1981.
On March 11, 1982, defendant reported that a-final report on plaintiff’s submission was expected from the Forest Service within 30 days. The Forest Service report was submitted to plaintiff on April 29, 1982.
On June 8, 1982, counsel were ordered to file a report by June 18,1982, on the status of consideration of the computation of the amount to be recovered by plaintiff. Plaintiff submitted a report on June 18, 1982. [712]*712Defendant did not respond, and on June 28, 1982, defendant was ordered to file a statement on or before July 16,1982, that either “accepts or rejects with reasons therefor” the items in plaintiffs statement. Defendant filed a number of motions for enlargement of time, the last of which was denied on July 27, 1982. Defendant filed its response to the June 28, 1982, order on August 6, 1982. By orders dated August 31, 1982, September 23, 1982, and December 3, 1982, counsel were encouraged to negotiate.18
On February 11,1983, plaintiff submitted an offer in compromise. On April 8, 1983, counsel were directed to file a status report; on April 26, 1983, defendant advised that the offer in compromise had been accepted; and, pursuant to stipulation, judgment for plaintiff was entered on May 16, 1983, for $370,000.
During the damages period, negotiations between counsel were unreasonably protracted, with most of the delay the responsibility of defendant. Defendant’s litigating posture during this period was not substantially justified.
Attorney fees authorized to be compensated by the EAJA are to be “reasonable.” The Act does not define the term “reasonable,” but the amount awarded is to be based upon “prevailing market rates for the kind and quality of services furnished” and attorney fees may not exceed $75 per hour unless the .court determines that a higher rate is justified. In its consideration of awards for attorney fees, the Court of Claims endorsed a fee standard that derived generally from the factors set forth in the American Bar Association Code of Professional Responsibility, DR 2-106(B).19 These factors, with minor variations, have been applied with respect to attorney fees authorized in other statutes.20
The weight to be given to the respective factors varies with the requirements of the particular case. Of primary importance, however, is a consideration of the number of hours reasonably expended, [713]*713and the hourly rate that is reasonable and customary in the community for the type of work involved.21 In the consideration of plaintiff’s application in this case, particular emphasis is given to the rates the parties agreed upon, and to the circumstance that under the prevailing rate structure in the local community, comparable services were compensated at the rates charged by plaintiff. The rates set forth in plaintiff’s application are commensurate with rates charged in the area of Seattle, Washington by lawyers with comparable or equivalent skills, training and experience.
Plaintiff’s application asks for payment of $95,018 for attorney fees for a total of 1,316.3 hours of work during the period June 1975 through June 1983. This represents, overall, an average hourly rate of $72.19.
It is not permissible to compute charges over the entire period so as to arrive at the average rate that is below the $75 per hour maximum. The EAJA does not authorize compensation at an hourly rate in excess of the rate that actually was charged for particular hours. To average the rate over the entire period, as reflected in plaintiff’s application, would result in a compensation for some hours at a rate higher than the rate actually paid for those hours. During the period covered by the application, 8.1 hours were billed at $140 per hour. This and other charges over the $75 per hour maximum are not allowable and must be adjusted.
Adjustments have been made to permit reimbursement at the rate billed when the rate was $75 per hour or less. Hours billed at rates in excess of $75 per hour were reduced to that amount.
The EAJA provides that the $75 per hour maximum may be exceeded when the court determines that an increase in the cost of living or a special factor, such as the limited availability of qualified attorneys for the proceedings involved, justifies a higher fee. The record in this case does not provide a basis for a determination on either basis. Plaintiff asserts that its principal attorney is “one of about 10 lawyers in the United States with extensive experience in litigating over Forest Service and other public timber sale contracts.” Counsel’s specialization and ability are not questioned. Timber sale contracts, however, have been a part of Forest Service routines for many years, and no shortage of qualified attorneys for such proceedings has been shown, or is apparent.
Plaintiff’s application sets forth amounts invoiced to Everett Plywood Corporation for legal services in connection with this case, for each year, in the period June 1975 through June 10, 1983. Support for these billings is provided by an itemized summary, by daily entry, of the legal services provided on that date. These calendar entries are supported by time slips that set forth the date, the services rendered, and the attorney doing the work. The invoices are further supported in the application by a summary, by year, of the total fees billed, segregated by hours and hourly rates of each lawyer rendering services.
Invoices billed to plaintiff for legal services in connection with this case total $95,-018, and are summarized as follows:
INVOICES
1975 $ 3,975.00
1976 4,835.00
1977 9,395.00
1978 25,360.00
1979 10,785.00
1980 28,270.00
1981 4,705.00
1982 3,650.00
1983 (to 6/10/83) 4.043.00
? 95,018.00
During the course of this litigation, the hourly rates for the principal attorney varied from $60 to $140, and hourly rates for associates ranged from $50 to $115. Different hourly rates were used in each year, dependent upon the particular work involved. Generally, over the course of the litigation period, there was a gradual increase in hourly rates. During period No. I [714]*714(the trial period), rates for the principal attorney and the associate varied from $50 to $85; during period no. II (the appeal period), the rates varied from $65 to $100, and during the period No. Ill (the damages period), the rates varied from $65 to $140. Rates charged during the course of this litigation were as follows:
HOURLY RATES PRINCIPAL ATTORNEY ASSOCIATES
1976 ?60;$80 $50;$55;$60
1976 $65;$75;$80 $50;$55
1977 $65;$75 $55;$65
1978 $75 $55;$60;$65
1979 $75;$85 $65;$75
1980 $85;$95 $65;$70;$75
1981 $85;$100 $70;$75;$85
1982 $100;$125 $65;$75
1983 $125;$140 $95;$115
The following table sets forth the applicable rates, the hours provided, the total charge at the hourly rate and the total entitlement after adjustment to reduce the rate to the $75 maximum for those hours subject to the maximum.
Period No. I - Trial Period
Rate Total Adjusted to $75 max.
$50 1.3 $ 65.00
$55 234.0 12.870.00
$60 42.2 2.532.00
$65 238.3 15,489.50
$75 251.3 18,847.80
$80 59.2 4.736.00 $ 4,440.00
$85 1.4 119.00 105.00
Total 827.7 $ 54,659.30 $ 54,349.30
Period No. II - Appeal Period
Rate Total Adjusted to $75 max.
$65 125.9 $ 8,183.50
$70 20.3 1.421.00
$75 15.8 1.185.00
$85 220.3 18,725.50 $ 16,522.50
$95 1.0 95.00 75.00
$100 _ÍU55 955.00 716.25
Total 392.85 $ 30,565.00 $ 28,103.25
Period No. Ill - Damages Period
Rate Total Adjusted to $75 max.
$65 0.3 $ .19.50
$70 Í.8 126.00
$75 15.8 1.192.50
$85 6.6 561.00 $ 495.00
$95 20.9 1.985.50 1.567.50
$100 10.05 1.005.00 753.75
$115 0.5 57.50 37.50
$125 31.7 3.962.50 2.377.50
$140 8.1 1.134.00 607.50
Total 95.75 $ 10,043.50 $ 7,176.75
For attorney fees, plaintiff is entitled to an award of the adjusted totals for periods I and III.
Plaintiff’s application contains an analysis of charges paid for consultants and engineering work. These charges were paid to plaintiff’s consultants, Mason, Bruce & Gir-ard, Inc., in connection with the ARM timber sale during 1974 to 1982. The services included a field evaluation of ARM timber, related engineering services, and written reports and testimony.
Defendant argues that plaintiff is not entitled to these expenses because they were waived in paragraph 4 of the stipulation for entry of judgment.
Charges for consultants and engineering work are summarized as follows:
Consultants and Engineering Work
1974 $ 2,710.51
1977 924.90
1978 1,139.52
1981 1,393.67
1982 1,232.50 $ 7,401.00
Payments made by plaintiff during 1974 in connection with the ARM timber sale are not eligible costs under the EAJA. They were incurred prior to the institution of this case on June 12, 1975. The remainder of the expenses clearly were waived by the terms of paragraph 4 of the stipulation, which plaintiff signed in May 1983. The stipulated amount of $370,000 was for full satisfaction of all claims, including “all claims for costs, expenses, and damages of any kind.”
Plaintiff cites a letter dated February 11, 1983, to support its contention that there never was any discussion or agreement to forego a claim for costs and expenses. Paragraph 4 of the stipulation is clear; no ambiguity exists. There is no reason to go behind its terms in an attempt to divine the parties’ intentions at an earlier stage of the negotiations. Similarly, plaintiff’s claim for costs and related expenses in the amount of $3,284.42 has been satisfied and is not compensable under the EAJA.
The total amount of attorney fees and expenses for which plaintiff seeks reim[715]*715bursement, and the amounts to be awarded are as follows:
SUMMARY
Requested Allowed
Attorney Fees $ 95,018.00 $ 61,526.05 *
Consultants & Eng. Work 7,401.10 ----
Costs & Related Expenses 3,284.42 ----
$105,703.52 $ 61,526.05
* For Period Nos. I and III
CONCLUSION
For the reasons set forth in this opinion, plaintiff is the prevailing party in this case and is entitled to an award pursuant to the Equal Access to Justice Act, 28 U.S.C. § 2412(d), of $61,526.05 for attorney fees incurred during the trial period and the damages period of this case. Judgment will be entered in that amount.