United States v. Lakeshore Terminal and Pipeline Co.

639 F. Supp. 958, 1986 U.S. Dist. LEXIS 24277
CourtDistrict Court, E.D. Michigan
DecidedJune 12, 1986
DocketCiv. A. 78-10135 BC
StatusPublished
Cited by12 cases

This text of 639 F. Supp. 958 (United States v. Lakeshore Terminal and Pipeline Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Lakeshore Terminal and Pipeline Co., 639 F. Supp. 958, 1986 U.S. Dist. LEXIS 24277 (E.D. Mich. 1986).

Opinion

MEMORANDUM OPINION AND ORDER

JAMES HARVEY, District Judge.

This case is now before the Court on defendant’s motion for an award of attorney fees under the Equal Access to Justice Act, 28 U.S.C. § 2412(d). The defendant seeks an award of attorney fees in the amount of $260,298.00.

In 1979, the United States filed this declaratory judgment action seeking a ruling that it was entitled to purchase the Harris-ville petroleum storage and terminalling facilities owned by the defendant Lakeshore. The Harrisville facility is located in northern Michigan and services Wurtsmith Air Force Base. In an opinion dated December 21, 1982, this Court adopted a magistrate’s recommendation which granted summary judgment in favor of the defendant. The United States appealed that ruling to the Court of Appeals for the Sixth Circuit but eventually dismissed the appeal when it decided that it no longer sought ownership of the Harrisville facilities. The defendant now seeks an award of attorney fees.

Factual Background

In 1956, Congress sought to increase national security by facilitating the construction of petroleum storage and terminalling facilities in rural areas that were less vulnerable to attack. 1 Accordingly, Congress authorized the Secretary of Defense to contract for the storage and handling of petroleum. See 10 U.S.C. § 2388.

Recognizing the commercial impracticality of locating petroleum storage facilities in rural areas, the United States provided the incentives necessary to induce private construction of such facilities by entering into long term contracts. These contracts called for heavily front loaded payments which allowed contractors to recapture their construction costs quickly. Part and parcel to this program was a Congressional intent that the United States be allowed to purchase these petroleum storage facilities after they had been constructed. Congress also intended that the government be allowed at least a partial credit against the purchase price for the front loaded payments. 2

*960 In April 1961, the United States entered into a contract with American Fuel Company, the defendant’s predecessor in interest. That contract required American Fuel to provide petroleum storage and terminalling facilities to service Wurthsmith Air Force Base. Under the contract, the government had an option to renew the three-year contract for 15 successive three-year periods, upon the same terms and conditions. Section XIII of the contract also gave the government the option to purchase the completed petroleum facilities. Section XIII provides:

At any time during the period of this contract or any renewal thereof, Government shall [sic] the option to purchase the petroleum storage and terminalling facilities furnished under this contract, including underlying land, and any Contractor furnished pipeline, on the following terms and conditions.

The contract then set forth two alternate purchase price formulas. The section relevant to this case provided:

If purchase is made subsequent to “Acceptance Date” of the facility as such term is defined in Section IV and prior to the expiration date of this contract, the purchase price will be the total actual incurred costs of completing the facility less that amount of revenue received under this contract which is reasonably allocable to amortization of facility costs.

During the first three years of the life of this contract, the United States paid American Fuel $1,412,000.00. In the following five years, the United States paid American Fuel an additional $1,929,400.00. These payments were intended to reimburse American Fuel’s construction costs and cover operating expenses.

In 1967, Lakeshore purchased the Harris-ville facilities from American Fuel Company. Because American Fuel did not own the land on which the Harrisville facility was located, Lakeshore also purchased the land but from another party. Lakeshore paid $95,000.00 for both the petroleum storage facilities and the land and assumed all of the contractual rights and responsibilities of American Fuel Company.

In 1977, the United States notified Lake-shore that it intended to exercise its option to purchase the Harrisville facilities. Believing that it had fully compensated American Fuel and Lakeshore for the construction costs of this facility, the United States felt that it was entitled to have the facility transferred to it for zero dollars. Lake-shore responded, through its parent company — the Detroit and Mackinac Railway Company, that it disagreed with the government’s assessment. Lakeshore notified the government that it valued the property at $6,000,000.00, that it would allow the United States a set off of only 1% of gross receipts, and that it would demand a 10-year operating contract to transfer ownership of the facility.

Following unsuccessful appeals to the contracting officer and the Armed Services Board of Contract Appeals, Lakeshore continued to refuse to convey the Harrisville Facility to the United States. The United States then filed suit in this Court requesting a declaratory judgment that it is entitled to title of the Harrisville facility.

In an opinion dated December 1982, this Court adopted a magistrate’s recommendation that summary judgment be granted in favor of Lakeshore. The basis for this ruling was a finding that the purchase price formula was so poorly drafted that the Court could not reasonably determine what percentage of the revenues that the United States paid American Fuel and Lakeshore were intended to be a credit against the purchase price. Specifically, the Court found that the phrase “reasonably allocable to amortization of facility costs” was ambiguous to the extent that it rendered the entire purchase option null and void. The Court also found that the contract was unenforceable because while the option gave the government the right to purchase both the storage facilities and the land on which they are located, the contract failed to specify how the land was to be valued. While the purchase price formula covered the facility, it did not cov *961 er the land. The summary judgment which the Court granted Lakeshore was granted on these two very narrow issues. Other issues in this case were not sufficient to support a motion for summary judgment for the reason that genuine issues of material fact remained to be decided. The Court found, for example, that the contract did adequately define the basis for valuing the Harrisville facility from which the credits were to be deducted. Nevertheless, because it was unclear what portion of the revenues paid by the United States were to be credited against that purchase price, summary judgment was appropriate.

Applicable Law

The availability of attorney fees under the Equal Access to Justice Act is provided for in 28 U.S.C. § 2412(d)(1)(A) which states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
639 F. Supp. 958, 1986 U.S. Dist. LEXIS 24277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-lakeshore-terminal-and-pipeline-co-mied-1986.