Kenny Construction Company v. District of Columbia

262 F.2d 926, 105 U.S. App. D.C. 8, 1959 U.S. App. LEXIS 5038
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 22, 1959
Docket14429
StatusPublished
Cited by15 cases

This text of 262 F.2d 926 (Kenny Construction Company v. District of Columbia) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kenny Construction Company v. District of Columbia, 262 F.2d 926, 105 U.S. App. D.C. 8, 1959 U.S. App. LEXIS 5038 (D.C. Cir. 1959).

Opinions

WILBUR K. MILLER, Circuit Judge.

September 30, 1954, Kenny Construction Company contracted with the District of Columbia to do certain street and sewer construction at an estimated price of $2,343,974. Partial payments were to be made monthly to Kenny as the work progressed, with 10% retained until “completion and acceptance of the work.” Such retention of 10% was provided for by statute,1 in obedience to which it was required.

As also required by the contract, appellant furnished to the District (1) a Performance and Payment Bond in the penal sum of $2,343,974, guaranteeing to “save harmless and indemnify the District from any and all claims, delays, suits, costs, charges, damages, counsel fees, judgments, and decrees to which said District may be subjected at any time on account of any injuries to persons or damage to property or premises that occur as a result of any act or omission of the principal [Kenny Construction Company] in connection with the prosecution of the work, and pay the same,” and (2) evidence that in addition to the liability for injuries to persons, it carried for itself total liability insurance of $500,000 for damages from injury to or destruction of property, and a like amount of liability insurance for any such damages with respect to operations performed by its subcontractors.

The work went forward despite litigation brought by Greenway, Inc., to enjoin its continuance because of anticipated danger to its nearby apartment buildings.2 On August 13, 1956, officials of the District inspected the work and found it complete and satisfactory “with the exception of restoration of private property,”' — a reference to the allegedly endangered apartment houses.

On August 30, 1956, when the District of Columbia took possession of the project, the balance due on the contract was $291,131.31, exclusive of claims for extra work not here in issue. Payment of this agreed balance was refused by the District on the ground that the apartment buildings had not been restored, whereupon Kenny appealed to the District Contract Appeals Board. That Board held that, as there was no contractual authority for the retention of more than 10% of the partial payments,3 the sum of $46,810.18 (the amount by which the retained sum of $291,131.31 exceeded 10% of the partial payments allowed) should be paid to Kenny forthwith, but without interest as no authorization existed for payment of interest on withheld partial payments. The Board also held that the contract had not been fully performed in that the apartment houses [928]*928had not been restored, and that the sum of $244,321.13 could therefore properly be withheld, although Kenny had furnished a performance bond and liability insurance in that respect as required by the contract.

A motion for reconsideration having been denied by the District Contract Appeals Board, Kenny filed this suit against the District of Columbia and its Commissioners 4 asking the United States District Court for the District of Columbia to declare, inter alia-,

“That the sum of $244,321.13, representing the retained percentages, is being wrongfully withheld from plaintiff herein, and is forthwith due and payable to it by defendant District of Columbia, together with interest thereon at six percent per annum from August 30, 1956, to date of payment;
“That interest on the sum of $46,-810.18 is due and payable to plaintiff herein by said District at six per cent per annum from August 30, 1956, to date of actual disbursement of said sum to plaintiff herein as directed in said Decision [of the Contract Appeals Board].”

The District Court granted the District’s motion to dismiss the complaint, and Kenny appeals.

Section 15 of the contract is said by the District to bar this action. It follows:

“Except as otherwise specifically provided in this contract, all disputes concerning questions arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within thirty (30) days to the'Contract Appeals Board, whose decision shall be final and conclusive upon the parties thereto * * *. In the meantime the contractor shall diligently proceed with the work as directed.”

Such a provision, argues the District, has been held to make the administrative decision final unless it was founded on fraud, alleged and proved, and fraud was not charged or shown here. It cites in support United States v. Wunderlich, 1951, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113, which is the latest utterance of the Supreme Court on the subject, and which does indeed so hold. Subsequent to that decision, however, and for the purpose of overcoming its effect,5 (and before the execution of the contract under consideration here), Congress enacted on May 11, 1954, legislation which included material which is now §§ 321 and 322 of Title 41 U.S.C.A., which are as follows:

§ 321. “No provision of any contract entered into by the United States, relating to the finality or conclusiveness of any decision of the head of any department or agency or his duly authorized representative or board in a dispute involving a question arising under such contract, shall be pleaded in any suit now filed or to be filed as limiting judicial review of any such decision to cases where fraud by such official or his said representative or board is alleged: Provided, however, That any such decision shall be final and conclusive unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence.”
§ 322. “No Government contract shall contain a provision making final on a question of law the deei[929]*929sion of any administrative official, representative, or board.”

The District of Columbia urges that this legislation, which has to do with contracts of the United States Government, has no application here since the District is an entity apart from the federal government. The appellee overlooks the fact that in citing the Wunderlich case and another somewhat similar,6 both of which dealt with contracts of the United States Government and not those of the District of Columbia, it was relying not on factual identity but only on the principle announced therein. That principle having been changed by legislation, the cases are no longer authority on the point.

Moreover, and dispositive of the point, the Wunderlich case dealt only with decisions on questions of fact. The United States Government contract there involved provided [342 U.S. 98, 72 S.Ct. 155]: “* * * [A] 11 disputes concerning questions of fact * * * shall be decided by the contracting officer,” and that the decision of the department head upon appeal shall be final. The Court was careful to emphasize that it was dealing with questions of fact. The District of Columbia contract with which we are here concerned broadened that provision to include all questions; its terms are: “* * * [A] 11 disputes concerning questions * * * shall be de-cidéd by the contracting officer,” etc. The Wunderlich decision is therefore not authority for the District’s position.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

District of Columbia v. C.J. Langenfelder & Son, Inc.
558 A.2d 1155 (District of Columbia Court of Appeals, 1989)
Jonal Corporation v. District of Columbia
533 F.2d 1192 (D.C. Circuit, 1976)
District of Columbia v. Heman Ward, Inc.
261 A.2d 836 (District of Columbia Court of Appeals, 1970)
M. Berger Co. v. United States
199 F. Supp. 22 (W.D. Pennsylvania, 1961)
Kayfield Construction Corp. v. United States
278 F.2d 217 (Second Circuit, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
262 F.2d 926, 105 U.S. App. D.C. 8, 1959 U.S. App. LEXIS 5038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kenny-construction-company-v-district-of-columbia-cadc-1959.