Optex Systems, Inc.

CourtArmed Services Board of Contract Appeals
DecidedNovember 6, 2014
DocketASBCA No. 58220
StatusPublished

This text of Optex Systems, Inc. (Optex Systems, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Optex Systems, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Optex Systems, Inc. ) ASBCA No. 58220 ) Under Contract No. W52H09-06-D-0229 )

APPEARANCES FOR THE APPELLANT: Albert B. Krachman, Esq. Harrison R. Kang, Esq. Blank Rome LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ Cameron Edlefsen, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN ON THE GOVERNMENT'S AFFIRMATIVE DEFENSES

Optex Systems, Inc. (Optex) appeals from a Contracting Officer's (CO's) final decision denying its claim for increased costs incurred in producing precision optical sighting instruments, known as M2A2 Aiming Circles, used by the U.S. military to aim howitzers. The government has asserted as affirmative defenses that appellant's claim is barred by release and by accord and satisfaction. The parties have submitted the issues of release and accord and satisfaction for decision on the written record pursuant to Board Rule 11. The Board has jurisdiction under the Contract Disputes Act, 41 U.S.C. §§ 7101-7109. We find that appellant's claim is not barred by release or by accord and satisfaction.

FINDINGS OF FACT

1. On 23 January 2006, the Rock Island Arsenal, Rock Island, Illinois, (government) issued a solicitation for offers for award of a five-year Indefinite Delivery/Indefinite Quantity, firm-fixed-price contract for the production and delivery of the Aiming Circles (R4, tab 16). The solicitation reserved the right to make multiple awards. (R4, tab 15 at 2)

2. On 7 July 2006, the government awarded Contract No. W52H09-06-D-0229 (hereinafter the contract) to Optex (R4, tab 1). Delivery Order (DO) No. 0001, for 310 Aiming Circles in the total amount of $1,283,260.20, was also issued to Optex on 7 July 2006 (R4, tab 39). Costs to prepare for and undergo First Article Test (FAT) were included in the unit prices (id.).

3. The government also awarded a contract and a first delivery order for Aiming Circles to Radian Corp., a small business later acquired by DRS Technologies, Inc. (amended compl. and answer~ 34).

4. The contract required Optex to manufacture the Aiming Circles in accordance with specifications contained in Technical Data Package (TDP) No. 11785090 (R4, tab 15 at 11-12). Prior to the award to Optex and Radian, the Army was the sole manufacturer of Aiming Circles (Appellant's Rule 11 Cross Motion for Judgment on the Release Issue and Memorandum in Support, ex. B, decl. of Danny Schoening (Schoening decl.) ~ 13). The majority of drawings in the TDP are dated from 1955-1960, and some from even earlier (gov't br., ex. 4, decl. of Anthony Corcella ~ 10).

5. On 29 June 2007, the parties executed bilateral Modification No. P00002 to the contract (R4, tab 221 ). This modification incorporated four Engineering Change Proposals (ECPs) making changes to the TDP (id. at 2). All other terms and conditions remained unchanged (id.)

6. The first ECP, No. H06A2077 (ECP #1), updated the TDP to make the Aiming Circle easier to produce, using alternate materials for castings, new set screws, and different sealing compounds (Joint Stipulation of Material Facts (J. Stip.) ~ 6.a). ECP # 1 also corrected drawing callouts and added distribution statements (id.; R4, tab 65 at 2-3).

7. The second ECP, No. H06A2093 (ECP #2), updated the TDP to add alternate materials, add or correct missing or incorrect dimensions and tolerances, correct callouts, update finishes, add distribution statements, update cancelled standards, and add a new "QAP" (J. Stip. ~ 7.a). ECP #2 stated: "Numerous issues with the TDP were found during preparations for initial production. These issues have been addressed in this ECP so that the M2A2 Aiming Circle TDP will be correct, up to date, and producible." (Id.; R4, tab 110 at 3)

8. The third ECP, No. H07A2004 (ECP #3), made more changes to the TDP "to address issues found during initial production planning" (R4, tab 156 at 1-2, 5).

9. The fourth ECP, Appellant's Request for Deviation No. H07A7006 (ECP #4), changed the brass alloy specified for a set screw at appellant's request (J. Stip. ~ 9.a).

2 10. Appellant's Request for Equitable Adjustment (REA) dated 7 October 2010 calculated that these 4 ECPs encompassed 119 changes to the TDP (R4, tab 590 at 1). Subsequent ECPs brought the claimed total changes to the TDP to 254 (id.).

11. Beginning at the post-award orientation conference in September 2006, Optex requested that the government modify the limitation on progress payments to allow Optex to be reimbursed for the purchase of long lead items (R4, tab 43 at 4). The contract as awarded contained a special clause H-3, 52.232-4506, PROGRESS PAYMENT LIMITATION (MAR 1988), which provided:

Prior to first article approval, only costs incurred for the first article are allowable for progress payments; however, such payments shall not exceed 10 percent ( 10 %) of the initial award value of the contract.

(R4, tab 15 at 22) The contract also contained the standard progress payments clause, Federal Acquisition Regulation (FAR) 52.232-16 (APR 2003) (id. at 27-30).

12. On 29 May 2007, following the approval ofECPs ##1-4, Optex submitted a list of parts that it considered to be long lead items and requested funding in the amount of $736,402 to cover the cost of ordering the parts (R4, tab 194 ). On 18 June 2007, the government responded that the submission was being reviewed, and requested that Optex add part numbers to its listing (R4, tab 208). Also on 18 June, Optex responded that it would provide a more detailed list, and inquired whether it would be possible to remove special clause H-3 (R4, tab 219 at 1). By letter dated 28 June 2007, the CO declined to remove the clause, stating that the government "does not want to risk an amount greater than the 10% of the contract value ... because there is no evidence of progress of completed parts and/or parts that have been tested" (id. at 4).

13. On 2 July 2007, the contract specialist reminded Optex that the government was still awaiting the more detailed list of long lead items, and explained that although the government was unwilling to remove the H-3 clause, it was still willing to consider funding for long lead items (R4, tab 224).

14. By letter dated 10 July 2007, Optex provided the detailed list oflong lead items and expressed its hope that the government would modify the contract to allow for the procurement of production material (R4, tab 228). On 31 July the government responded, requesting the delivery schedule for the listed items (R4, tab 23 7).

15. Following some clarifying communications, on 20 October 2007 Optex submitted a revised long lead item proposal detailing the parts, costs, and on-order dates needed to meet the contract's production delivery requirements (R4, tab 304). Funding was requested in a total amount of $490,799.89 (id.). The contract specialist

3 obtained internal government concurrence that the listed items met the definition of long lead items (R4, tabs 317, 319). She also obtained the concurrence of the administrative contracting officer to allow progress payments for those items (R4, tab 324). For reasons that do not appear in the record, however, the contract was not modified to allow for long lead item funding.

16. FAT commenced on 4 May 2009 (R4, tabs 510, 511).

17. On 5 May 2009 Optex resumed its request for funding of long lead items (R4, tab 512). In the interim, Optex had purchased parts needed for production at its own risk in order to expedite production after first article approval (id.). The total of Optex's at-risk expenditure was $1,352,563.60 (id.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
R.P. Richards Construction Co. v. United States
51 Fed. Cl. 116 (Federal Claims, 2001)
Information Systems & Networks Corp. v. United States
68 Fed. Cl. 336 (Federal Claims, 2005)
Peter Kiewit Sons' Co. v. United States
109 Ct. Cl. 390 (Court of Claims, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
Optex Systems, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/optex-systems-inc-asbca-2014.