Radmacher Brothers Excavating Co., Inc.

CourtArmed Services Board of Contract Appeals
DecidedOctober 27, 2023
Docket63276, 63367
StatusPublished

This text of Radmacher Brothers Excavating Co., Inc. (Radmacher Brothers Excavating Co., Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Radmacher Brothers Excavating Co., Inc., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Radmacher Brothers Excavating Co., Inc. ) ASBCA Nos. 63276, 63367 ) Under Contract No. W912DQ-17-C-1095 )

APPEARANCE FOR THE APPELLANT: G. Steven Ruprecht, Esq. Brown & Ruprecht Attorneys at Law, PC Kansas City, MO

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Virginia Murray, Esq. Jacob T. Simpson, Esq. Engineer Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT ON THE GOVERNMENT’S MOTION FOR PARTIAL SUMMARY JUDGMENT

These appeals concern a contract between the United States Army Corps of Engineers (the government or the Corps) and Radmacher Brothers Excavating Co., Inc. (appellant or Radmacher). Contract No. W912DQ-17-C-1095 (the contract) was a contract to construct improvements to lower Turkey Creek in Wyandotte County, Kansas City, Kansas. Part of the contract required excavation operations to install underground piping under active railroad tracks. During performance of the contract, after receiving a request for information, the government informed appellant that it could not perform the boring, jacking, and pipe installation when trains were actively in use and also when stationary trains were present. This appeal resulted from the delays allegedly caused by the stationary trains. The government filed a motion for partial summary judgment, arguing that appellant referenced contract clauses not contained in the contract and did not meet the requirements for a differing site condition. For the reasons set forth below, we grant the government’s motion regarding the clauses not included in the contract and the type 1 differing site condition claim but deny the motion regarding the type 2 differing site conditions claim. STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

1. On August 4, 2017, the government issued Solicitation No. W912DQ-17-B-1018 (the solicitation) for the contract (R4, tab 9 at 8).

2. The solicitation included a requirement for boring and jacking (i.e. forcing the pipe through the embankment) under active railroad tracks to install 96-inch reinforced concrete pipe (R4, tab 9 at 754-99).

3. The solicitation’s performance work statement included

All tracks will remain in use at all times. Once jacking operations has commenced, it shall be continued uninterrupted around the clock until the conduit has been jacked under all live tracks except that no pipe movement will be allowed while a train is passing over any tracks designated as main tracks.

(R4, tab 9 at 760 ¶ H) The solicitation was silent concerning stationary trains.

4. The solicitation included directions that required extreme care when moving pipe under all tracks due to settlement issues. It stated, “If settlement occurs at any track, all jacking operations shall cease and Contractor shall notify COR immediately. No additional compensation will be made for the subsequent delays to the Contractor.” (R4, tab 9 at 760 ¶ I)

5. The solicitation also directed, “No equipment or materials can be operated or stored within fifteen (15) feet of the centerline of any railroad track that is subject to train traffic, without first receiving permission from the BNSF and UP railroad.” It also included further directions about excavations and shoring. (R4, tab 9 at 760 ¶ J)

6. On September 29, 2017, the government awarded the contract to appellant, in the amount of $26,577,770 (R4, tab 18 at 3).

7. The contract included Federal Acquisition Regulation (FAR) 52.243-4, CHANGES (JUN 2007) (R4, tab 18 at 55-56).

8. The contract included FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) (R4, tab 18 at 53).

9. Neither the contract nor the solicitation included General Services Administration Manual (GSAM) 552.243-71, a General Services Administration clause

2 concerning Equitable Adjustments referenced by appellant in its certified claim (R4, tabs 4, 9, 18, 46).

10. Neither the contract nor the solicitation included FAR 52.243-5, CHANGES AND CHANGED CONDITIONS (APR 1984) (R4, tabs 9, 18). FAR 43.205 directed using this clause “in solicitations and contracts for construction, when the contract amount is not expected to exceed the simplified acquisition threshold.” FAR 43.205(e). The simplified acquisition threshold was $250,000. FAR 2.101. This $26.5 million contract exceeded the simplified acquisition threshold.

11. On February 27, 2019, appellant submitted Request for Information Report (RFI) No. 0025 with the subject “Boring While a Train is Parked on the Tracks.” Appellant notified the government that it noticed “a string of railcars, with or without locomotives has remained parked for extended periods of time on the tracks that span the boring alignments between STA 5+69 and STA 8+01.” Appellant asked whether it would be prohibited from boring if the stationary trains remained when boring operations were ready to begin and if appellant would receive any time and monetary adjustments if a delay occurred. (R4, tab 25)

12. On March 29, 2019, the government answered appellant’s RFI No. 25, explaining that settlement can be a problem during jacking and that if a train was stopped on the track, “pipe jacking shall not be permitted unless the boring head has passed through the loading zone of the tracks.” It went on to recommend coordinating with the train companies to avoid having trains parked on the tracks above the borings. The government closed with the statement, “This response is derived from railroad guidance, which is required to be followed. Therefore, the Government does not anticipate a cost or schedule impact from this response.” (R4, tab 28 at 3)

13. On November 2, 2021, appellant submitted a request for equitable adjustment to the contracting officer, in the amount of $933,656.89, arguing that it was entitled to delay costs for the contract “under 48 CFR 552.243-71; ‘Changes Clause’ FAR 52.243-4; Changes and Changed Conditions Clause FAR 52.243-5; Differing Site Conditions Clause FAR 52.236-2, and any other provision of [the] Contract allowing entitlement to an equitable adjustment for additional time and costs incurred . . . (R4, tab 4 at 2-3).” The request was certified, allowing it to also be characterized as a certified claim (R4, tab 4 at 4).

14. On February 1, 2022, the contracting officer issued a contracting officer’s final decision letter, granting part of what appellant claimed and agreeing that the government owed a time extension of 13 days and monetary compensation in the amount of $351,751 (R4, tab 3 at 9). On February 7, 2022, the contracting officer amended the decision letter to add interest in the amount of $1,542.52 (R4, tab 2 at 10).

3 15. On May 4, 2022, appellant appealed to the Board. The Board docketed the appeal as ASBCA No. 63276.

16. On July 27, 2022, appellant notified the Board that it reduced the certified claim amount to $771,244.30 plus interest. The Board docketed this as a new appeal, ASBCA No. 63367. The parties requested this appeal be consolidated with ASBCA No. 63276, which the Board approved.

17. On June 26, 2023, the government filed a motion for partial summary judgment, asking the Board to grant it summary judgment. The government argued that appellant’s theory of differing site conditions did not properly apply to the situation and that appellant’s remaining arguments relied upon clauses not contained in the contract (gov’t mot. at 7-15). On July 26, 2023, appellant responded, appearing to concede to the government’s arguments regarding the two clauses not contained in the contract and type 1 differing site conditions but explaining why the Board should deny the government’s motion regarding type 2 differing site conditions (app. resp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Alabama v. North Carolina
560 U.S. 330 (Supreme Court, 2010)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Radmacher Brothers Excavating Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/radmacher-brothers-excavating-co-inc-asbca-2023.