General Dynamics - National Steel and Shipbuilding Company

CourtArmed Services Board of Contract Appeals
DecidedMarch 25, 2019
DocketASBCA No. 61524
StatusPublished

This text of General Dynamics - National Steel and Shipbuilding Company (General Dynamics - National Steel and Shipbuilding Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Dynamics - National Steel and Shipbuilding Company, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) General Dynamics - National Steel ) ASBCA No. 61524 and Shipbuilding Company ) ) Under Contract No. N00024- l 7-C-4426 )

APPEARANCE FOR THE APPELLANT: William M. Pannier. Esq. Pannier Law, PC Thousand Oaks, CA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Brian S. Smith, Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE PARTIES' MOTIONS FOR SUMMARY JUDGMENT

This appeal involves a contract for appellant General Dynamics - National Steel and Shipbuilding Company (NASSCO) to provide Drydocking Phased Maintenance Availability repairs and alterations onboard USS Makin Island (LHD 08). The contract was a fixed-price contract for NASSCO to accomplish defined work items. However, it also provided for growth work-work that the government might assign in addition to the defined work, which NASSCO committed to perform at a fixed-labor rate and material-burden percentage. The issue in this appeal is whether certain disputed clauses that required reservations of labor and material were for growth work.

NASSCO moves for summary judgment, arguing that the disputed clauses unambiguously were pre-priced reservations that capped the defined work, such that it is entitled to an equitable adjustment for any work in excess of the reservations' labor mandays and material costs. The government cross-moves for summary judgment, arguing that the disputed clauses unambiguously were reservations for growth work above and beyond the defined work, such that NASSCO must perform all of the defined work for the fixed price, even if it exceeds the reservations' labor mandays and material costs. We deny both motions because we find that the language of the disputed clauses is ambiguous-and therefore that it is necessary to resort to extrinsic evidence, which raises a genuine issue of material fact. STA TEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

1. On June 6, 2017, the United States Naval Sea Systems Command (government) awarded Contract No. N00024-l 7-C-4426 (4426 contract) to NASSCO (R4, tab 1 at 1338). The 4426 contract required NASSCO to:

[P]repare for and accomplish repair and alterations during the DryDocking Phased Maintenance Availability (DPMA) onboard USS MAKIN ISLAND (LHD 08) as specified in the statement of work provided herein and in accordance with standard items, work item specification package SSP TPPC-LHD8-SWRMC17-CNOl drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2. See Notes A and C.

(R4, tab 1 at 1339; app. supp. R4, tab 1 at 1-5)

2. The 4426 contract generally was a fixed-price contract (R4, tab 1 at 2-11, 14). However, NASSCO also committed in Notes A and C to provide reservations of labor and material at a fixed rate for "growth" work. Growth work was tasks that the government might assign in the future in addition to the defined work. (Id. at 1357-59)

3. The 4426 contract contained numerous Work Items (R4, tab 1 at 187-1568), which were individual sets of work requirements to accomplish a specific alteration or repair. Joint Fleet Maintenance Manual (JFMM), VII-4E-6, § Il(A), available at https://www.navsea.navy.mil/Portals/ 103/Documents/SSRAC/4E/FY20/ l 0%2026%20FY 20%20Apendex%204E%20JFMM%2001OCT2018.pdf?ver=2018 10-26-103 93 8-110. In particular, Work Items 311-21-001, 311-22-001, 311-23-002, 311-24-011, 311-25-001, and 311-26-003 (Work Items 21 through 26) addressed Ship Service Diesel Generators (SSDGs) Numbers 1 through 6, D level, respectively (R4, tab 1 at 1418-1568).

4. Paragraph 3 of each Work Item contained the requirements (R4, tab 1 at 1418-1568); see also JFMM, § VII(B )( 4 ). The first several subparagraphs of paragraph 3 (Defined Work Clauses) 1 required NASSCO to accomplish specifically enumerated tasks (defined work) (R4, tab 1 at 1418-1568). Then, paragraph 3 contained a subparagraph mandating a reservation of labor mandays and material costs (Reservation Clauses). In particular, subparagraphs 3.5 of Work Items 21, 23, and 26, and subparagraph 3 .4 of Work Item 22 (Disputed Reservation Clauses) stated,

1 The Defined Work Clauses were subparagraphs 3 .1 through 3 .3 of Work Items 22, 24, and 25; and subparagraphs 3.1 through 3.4 of Work Items 21, 23, and 26 (R4, tab 1 at 1418-1568).

2 "[p ]rovide 60 mandays of labor and 16,000 dollars of material to accomplish this Work Item, as designated by the SUPERVISOR." (Id. at 1419, 1431, 1451, 1558) Subparagraph 3.4 of Work Items 24 and 25 (Undisputed Reservation Clauses) stated, "[p]rovide 100 man days of labor and 50,000 dollars of material to accomplish additional work not already covered by this Work Item, as designated by the SUPERVISOR" (id. at 1463, 1510).

5. Other reservation clauses in other Work Items (Other Reservation Clauses) created a growth reservation of mandays and material to correct deficiencies identified during inspections and tests (R4, tab 1 at 469-70, 504-05, 942, 1175, 1218-19).

6. On September 11, 2017, NASSCO submitted a request for an equitable adjustment (REA), claiming that it was entitled to an equitable adjustment for any work on Work Items 21 through 23 and 26 (Disputed Work Items) requiring more than 60 labor mandays or $16,000 of materials (app. supp. R4, tab 3 at 71-126).

7. The government rejected NASSCO's REA on October 3, 2017 (R4, tab 3 at 1661).

8. On December 1, 2017, NASSCO filed a certified claim (R4, tab 2).

9. Based upon a deemed denial of that claim, this appeal followed.

DECISION

I. The Standard for Summary Judgment

We grant summary judgment if a moving party has shown that there are no genuine issues of material fact, and it is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). In deciding summary judgment motions, we do not resolve controversies, weigh evidence, or make credibility determinations. Anderson v. Liberty Lobby, Inc., 477 U.S. 242,255 (1986). Moreover, we draw all reasonable inferences in favor of the non-movant. Id. Summary judgment based upon an issue of contract interpretation may not be granted if there is an ambiguity requiring that we resort to extrinsic evidence over which there is a genuine dispute. Classic Site Solutions, Inc., ASBCA Nos. 58376, 58573, 14-1 BCA ,r 35,647 at 174,551.

II. Neither Party is Entitled to Summary Judgment Because the Language of the Disputed Reservation Clauses is Ambiguous and we Must Resort to Contested Extrinsic Evidence

Neither party is entitled to judgment as a matter of law because the language of the Disputed Reservation Clauses is ambiguous, and therefore we must resort to extrinsic evidence, which raises genuine issues of material fact. "[C]lear and

3 unambiguous [contract provisions] must be given their plain and ordinary meaning, and we may not resort to extrinsic evidence to interpret them." Coast Fed. Bank, FSB v. United States, 323 F.3d 1035, 1040 (Fed. Cir. 2003) (en bane) (citations and internal quotation marks omitted). ·'An ambiguity exists when a contract is susceptible to more than one reasonable interpretation." E.L. Hamm & Assoc., Inc. v. England, 379 F.3d 1334, 1341 (Fed. Cir. 2004). ·'To show an ambiguity it is not enough that the parties differ in their respective interpretations of a contract term.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
General Dynamics - National Steel and Shipbuilding Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-dynamics-national-steel-and-shipbuilding-company-asbca-2019.