CDM Constructors, Inc.

CourtArmed Services Board of Contract Appeals
DecidedAugust 20, 2018
DocketASBCA No. 61074
StatusPublished

This text of CDM Constructors, Inc. (CDM Constructors, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CDM Constructors, Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) CDM Constructors, Inc. ) ASBCA No. 61074 ) Under Contract No. W912HN-15-C-OO 15 )

APPEARANCES FOR THE APPELLANT: John T. Flynn, Esq. Joseph J. Minock, Esq. Weinberg, Wheeler, Hudgins, Gunn & Dial, LLC Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Laura J. Arnett, Esq. Engineer Trial Attorney U.S. Army Engineer District, Savannah

. OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

CDM Constructors, Inc. (CDM) appeals a contracting officer's (CO's) final decision denying its claim for $3,157,098.58 in increased costs of performing a contract for the construction of dissolved oxygen injection systems at two locations on the Savannah River. CDM claims that the increased costs were the result of a suspension of work from August 14, 2015 to October 14, 2015, pursuant to a bid protest ultimately decided in the government's favor. The government moves for summary judgment on the grounds that ( 1) CDM cannot establish that the delay was unreasonable, which is a requirement for recovery under the Suspension of Work clause, and (2) in any event, CDM's claimed damages were not caused by the suspension. CDM opposes on the ground that there are genuine issues of law and fact regarding both the reasonableness of the suspension and the proximate cause of CDM's damages. We grant the motion for the reasons discussed below.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

Contract No. W912HN-15-C-0015 (the contract) was awarded to CDM on July 31, 2015, by the U.S. Army Corps of Engineers, Savannah District (Corps). The contract, totaling $99,675,591, called for the construction of the Savannah Harbor

r Expansion Project Dissolved Oxygen Injection System (DO project). (Gov't SMF ,r 45) 1 On August 14, 2015, the Corps notified CDM that a protest had been filed with the Government Accountability Office (GAO). The notice further advised CDM as follows:

Please be advised that in accordance with 31 U.S.C. § 3553(d), 4 C.F.R. § 21.6, and FAR 33.104(c), performance of the contract is suspended, pending resolution of the protest. Do not begin performance until authorized to do so by the Contracting Officer.

(R4, tab 9 at 3) On October 8, 2015, the GAO denied the protest. On October 14, 2015, the Corps lifted the suspension, and on October 21, 2015, at the pre-construction meeting, the Corps issued the notice to proceed (NTP) (gov't SMF ,r,r 69, 71, 74). On December 21, 2015, CDM notified the Corps that the protest delay had caused its contemplated marine construction subcontractor, Cape Romain, to withdraw (R4, tab 17). As a result, CDM stated, it had resumed discussions with · other marine contractors who offered both higher pricing and more extended schedules than Cape Romain had proposed (and on which CDM had based its proposal) (id.). The certified claim eventually submitted by CDM to the Corps on June 27, 2016, claimed increased costs in the amount of $3,157,098.58, allegedly caused by the protest suspension described above (R4, tab 18). CDM's claim was denied by the Corps on December 2, 2016, and CDM thereafter timely filed an appeal to the Board which was docketed on February 27, 2017.

The contract contained both the Federal Acquisition Regulation (FAR) 52.242-14, SUSPENSION OF WORK (APR 1984); and FAR 52.233-3, PROTEST AFTER A WARD (AUG 1996) clauses. The Suspension of Work clause provided, in relevant part:

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted

1 All references herein to statements of material fact are to undisputed facts unless otherwise noted. f 2

I ( 1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified by this contract ( or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.

(R4, tab 8 at 148-49)

The Protest after Award clause provided, in relevant part:

(a) Upon receipt ofa notice of protest (as defined in FAR 33.101) or a determination that a protest is likely (see FAR 33.102(d)), the Contracting Officer may, by written order to the Contractor, direct the Contractor to stop performance of the work called for by this contract. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order;the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Upon receipt of the final decision in the protest, the Contracting Officer shall either--

( 1) Cancel the stop-work order; or

(2) Terminate the work covered by the order as provided in the Default, or the Termination for Convenience of the Government, clause of this contract,

(b) If a stop-work order issued under this clause is cancelled either before or after a final decision in the protest, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule or contract price, or both, and the contract shall be modified, in writing, accordingly, if--

( 1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract ....

(R4, tab 8 at 137-38)

I On October 6, 2014, CDM entered into a teaming agreement with Ballard Marine Construction for marine construction services on the DO project (gov't SMF ,r 5). The teaming agreement set forth the parties' agreement to "exert their respective best efforts to produce and timely submit the jointly prepared Response to the RFP which is intended to cause the selection of CDM Smithl2l as the prime contractor and Ballard as an exclusive marine construction sub-contractor to perform the Project for the Owner" (id. ,r 6).

CDM stated in its proposal that Ballard "will provide support of the in-water portion of the dissolved oxygen injection systems and associated ancillary work of the project" which could include, but was not limited to, "installing conveyance piping and associated items, installing Speece cones and diffusers, and conducting associated activities underwater (e.g. welding)" (R4, tab 4 at 585). Mr. Robert Gilbert, CDM's south regional operations manager, testified that this scope of work was only a portion of the entire marine construction scope of work on the DO project (app. resp., ex. 1 (Gilbert Deposition) at 12-13). Ballard was featured prominently in CDM's proposal for the DO project in both CDM' s small business subcontracting plan, which noted that Ballard was both a small business and a woman-owned small business that would be performing "a significant portion of the effort," and CDM's past performance submission, which included a total of five projects, two of which were Ballard projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hornsby v. United States
77 U.S. 224 (Supreme Court, 1870)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
CDM Constructors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cdm-constructors-inc-asbca-2018.