CPS Mechanical Contractors, Inc. v. United States

59 Fed. Cl. 760, 2004 U.S. Claims LEXIS 50, 2004 WL 542631
CourtUnited States Court of Federal Claims
DecidedMarch 18, 2004
DocketNo. 02-477C
StatusPublished
Cited by12 cases

This text of 59 Fed. Cl. 760 (CPS Mechanical Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CPS Mechanical Contractors, Inc. v. United States, 59 Fed. Cl. 760, 2004 U.S. Claims LEXIS 50, 2004 WL 542631 (uscfc 2004).

Opinion

OPINION

MARGOLIS, Senior Judge.

This action is before the Court on defendant’s motion to dismiss pursuant to R. Ct. Fed. Cl. 12(b)(1). Plaintiff filed a complaint, pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-609 (2003) (“CDA”), seeking an equitable adjustment for alleged additional work it performed under a construction contract with defendant. Defendant filed a motion to dismiss the complaint for lack of subject matter jurisdiction, claiming that plaintiff has not satisfied the CDA’s jurisdictional requirements. After careful consideration of both parties’ briefs, this Court GRANTS defendant’s motion to dismiss.

Facts

In August 1996, the United States, acting through the United States Army (“Army” or “defendant”), entered into a contract with CPS Mechanical Contractors, Inc. (“CPS” or “plaintiff’) for the renovation of sewer system components at Fort Jackson in South Carolina. According to the contract’s statement of work provision, plaintiffs work included “installing 991 l.f. of 10" pvc gravity sewer, 1149 l.f. of 8" gravity sewer, 11 manholes, tieing [sic] to existing sewer system and installing 7 chemical injection units.” Pl.’s Compl. at 1-2. A dispute arose when the Army directed CPS to install 988 l.f. of 6" laterals. While CPS performed this work during the contract period, it nonetheless protested that the work was beyond that set out in the statement of work. CPS sent a series of letters to the Contracting Officer (“CO”) expressing its view that the 6" lateral installation work was beyond the scope of work under the contract and thus constituted additional work, which entitled CPS to an equitable adjustment under the contract. In its first letter, dated January 3, 2000, CPS informed the CO that there was a discrepancy between the contract drawings and the contract’s statement of work. CPS stated that the drawings included the installation of the 6" laterals while the contract’s statement of work did not. The letter asked the CO to resolve the discrepancy. In a letter dated January 5, 2000, the CO informed CPS that in her opinion there was no discrepancy between the statement of work and the drawings. According to the CO, the statement of work is merely a general statement that provides an overall description of the work to be done, and therefore, the drawings must also be used to determine the work required by the contract. Thus, while certain work may not be included in a contract’s statement of work, if it is included in the drawings, it is a part of the contract, and the contractor is responsible for completing such work. Further, the CO found that even if a discrepancy existed, FAR 52.236-21, which states, in relevant part “Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both,” resolved the discrepancy. Pl.’s Opp’n at App. 2-3; 48 C.F.R. § 52.236-21(a) (2003).

CPS sent another letter, dated January 6, 2000, to the CO explaining its disagreement with the CO’s opinion. CPS noted that, in interpreting the contract provisions, the CO failed to consider another sentence from FAR 52.236.21 which stated, “In differences between the drawings and specifications the specifications shall govern.” Pl.’s Opp’n at App. 4. As evidence that the Army interpreted FAR 52.236.21 in the same manner as CPS, CPS noted that the Army had previously deleted a manhole that was shown on the drawings, but that was not included in the statement of work, in order for the drawings [762]*762and the statement of work to agree with each other.

On January 24, 2000, the CO responded to CPS’s second letter. First the CO explained that the FAR sentence that CPS referenced did not apply to this situation because it only applies where there is an inconsistency between the statement of work and the drawings, and in this case no such inconsistency existed. Citing to a board of contracts appeals case, the CO stated, “[T]he omission in a specification of an item sét forth in a drawing is not an inconsistency.” Id. at App. 5 (citing Hickman Mechanical, Inc., ASBCA No. 46492, 94-2 BCA 1126,914, 1994 WL 171594). Second, the CO explained that even if a discrepancy existed, CPS did not have a valid claim because a bidder has a “duty to notify the contracting officer, prior to bid submissions, of all patent and known discrepancies,” and because CPS failed to so notify the CO, it could not now complain of the discrepancy. Id.

Thereafter, CPS sent the CO a letter, dated February 7, 2000, expressly asking whether the CO was “denying any liability for the installation of the 6" pipe[.]” Id. at 7. In the letter, CPS asked for a response with an explanation. The CO responded on February 9, 2000, and again stated that according to FAR 52.236-21, no discrepancy existed between the statement of work and the drawings. In a response letter, dated February 18, 2000, CPS again expressed its disagreement with the CO’s interpretation of the work called for by the contract and further reserved its right to file a claim for all work associated with the installation of the 6" laterals.

Thereafter, on May 15, 2002, CPS filed a complaint in this Court seeking an equitable adjustment, in the amount of $51,989.67 plus interest, for the alleged additional work it performed in installing the 6" laterals. In response, the Army filed a motion to dismiss for lack of subject matter jurisdiction, arguing that CPS failed to satisfy the requirements of the CDA. Specifically, defendant contends that CPS failed to submit to the CO a written demand seeking payment, as a matter of right, for the installation of the 6" laterals, and further that the CO has not issued a final decision on the issue.

Discussion

In this ease, plaintiff invokes the CDA, which gives this Court jurisdiction over actions for claims brought within twelve months of a contracting officer’s final decision. 41 U.S.C. § 609(a)(1),(3). Therefore, for this Court to have jurisdiction, plaintiff must show two things: first, that it submitted a claim to the CO, 41 U.S.C. § 605(a); James M. Ellett Constr. Co., Inc. v. United States, 93 F.3d 1537, 1541-42 (Fed.Cir.1996), and second, that the CO rendered a final decision on the claim. Bath Iron Works Corp. v. United States, 20 F.3d 1567, 1578-79 (Fed.Cir.1994); Clearwater Constructors, Inc. v. United States, 56 Fed.Cl. 303, 311 (2003).

CDA Requirements for “Valid” Claim

Because the CDA leaves the term “claim” undefined, the Court must look to the FAR, the CDA’s implementing regulations, to determine what is necessary for a contractor’s submission to be deemed a claim.1 Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed.Cir.1995). The FAR defines a “claim” as:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tanana Chiefs Conference v. Azar
District of Columbia, 2022
M. Nicolas Enterprises, Llc.
Federal Claims, 2021
Estes Express Lines v. United States
123 Fed. Cl. 538 (Federal Claims, 2015)
K-Con Building Systems, Inc. v. United States
114 Fed. Cl. 722 (Federal Claims, 2014)
L.A. Ruiz Associates, Inc. v. United States
94 Fed. Cl. 768 (Federal Claims, 2010)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
Engineered Demolition, Inc. v. United States
70 Fed. Cl. 580 (Federal Claims, 2006)
Modeer v. United States
68 Fed. Cl. 131 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
59 Fed. Cl. 760, 2004 U.S. Claims LEXIS 50, 2004 WL 542631, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cps-mechanical-contractors-inc-v-united-states-uscfc-2004.