D.L. Braughler Company, Inc. v. Togo D. West, Secretary of the Army

127 F.3d 1476, 42 Cont. Cas. Fed. 77,183, 1997 U.S. App. LEXIS 29370, 1997 WL 662672
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 27, 1997
Docket96-1277
StatusPublished
Cited by34 cases

This text of 127 F.3d 1476 (D.L. Braughler Company, Inc. v. Togo D. West, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.L. Braughler Company, Inc. v. Togo D. West, Secretary of the Army, 127 F.3d 1476, 42 Cont. Cas. Fed. 77,183, 1997 U.S. App. LEXIS 29370, 1997 WL 662672 (Fed. Cir. 1997).

Opinion

SCHALL, Circuit Judge.

D.L. Braughler Company, Inc. (“Braughler”) appeals from the November 28, 1995 decision of the Corps of Engineers Board of Contract Appeals (“Board”) dismissing as untimely Braughler’s appeal of a contracting officer’s final decision. D.L. Braughler Co., ENGBCA No. 6121, 96-1 BCA 28,110 (1995). We affirm.

BACKGROUND

On April 16,1982, Braughler and the United States Army Corps of Engineers (“Corps”) entered into a contract for remedial work at the R.D. Bailey Dam, Guyandot River, West Virginia. Braughler, 96-1 BCA at 140,310. In addition to its specific provisions, the contract contained various standard clauses from the Defense Acquisition Regulations (“DAR”). 1

*1478 During contract performance, a dispute arose, in which Braughler asserted that the Corps had unreasonably delayed approving its cofferdam shop drawings. Id. In response to Braughler’s request for an extension of the contract completion date, the Corps issued Modification P00013. Id. at 140,310-11. The modification extended the contract completion date by 180 days. Id. Braughler executed the modification but reserved the right to file a claim for compensable delay costs. Braughler, 96-1 BCA at 140,311.

On February 10, 1988, Braughler sent a letter to the Corps’ resident engineer for the project. The letter bore the subject title “Claim for Delay Caused by Untimely Approval of the Existing Stilling Basin Cofferdam.” Id. In the letter, Braughler stated that it was seeking $137,648.04 in compensable delay costs, as well as additional delay time. Id. Accompanying the letter were eighteen separate exhibits containing supporting data for the claim. In addition, Braughler informed the resident engineer that its books and records were available for review. In the final paragraph of the letter, Braughler stated that “Attached as Exhibit 19 is our Certification of our claim.” The certification read:

I, David L. Braughler, certify that the claim submitted by our letter dated 10 February 1988 and its attachments for the Delay Caused by Untimely Approval of the Existing Stilling Basin Cofferdam in the amount of $137,648.04 is made in good faith, that the supporting data are accurate and complete to the best of my knowledge and belief, and the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

The resident engineer was designated as the authorized representative of the contracting officer. In that capacity, he had authority to “take any or all actions in connection with contract administration which could be lawfully taken by [the contracting officer], except the execution of or agreement to any contract modification.”

On February 16 and August 19, 1989, Braughler contacted the resident engineer in order to inquire about the status of the claim. Eventually, on February 22, 1990, representatives of Braughler met with the resident engineer to discuss the claim. Braughler, 96-1 BCA at 140,311. The parties were unable to reach agreement, however, and by letter dated March 14, 1990, the resident engineer wrote Braughler concerning the claim. Id. In his letter, the resident engineer stated: “I find that your claim is not justifiable. The provisions for obtaining a Contracting Officer’s Decision are contained in General Provision 6, ‘Disputes’ of the contract.” Id.

By letter dated April 3, 1990, Braughler contacted the contracting officer concerning its claim. Id. The letter read:

This letter is written with regard to our claim for Untimely Approval of the Existing Stilling Basin Cofferdam, which was submitted by our letter of 10 February 1988. By letter dated 14 March 1990, [the resident engineer] denied the claim. We believe his decision is incorrect and • request that a final decision be issued on the claim. However, prior to issuance of a final decision, we would like to have the opportunity to meet with you and try to resolve the claim short of litigation. Please let us know if you are willing to meet with us and if so please set an acceptable date for the meeting.

Braughler did not provide a new claim certification with its April 3rd letter. Braughler, 96-1 BCA at 140,311. After further correspondence and a meeting between the parties, in a final decision dated November 16, 1990, the contracting officer denied Braughler’s claim. Id. at 140,311-12. The final decision opened with the following paragraph:

By letter dated February 10, 1988, you submitted a certified claim to the Resident Engineer in the amount of $137,648.04 for additional costs allegedly resulting from a delay caused by untimely approval of your cofferdam proposal (shop drawings). By *1479 letter dated March 14, 1990, the Resident Engineer responded by stating that the claim was not justified and referred you to the Contracting Officer for a Contracting Officer’s final decision. By letter dated April 3, 1990, you requested a Contracting Officer decision on your claim and a meeting with me prior to issuance of the decision.

Id. at 140,312 (citations omitted).

The contracting officer advised Braughler that it could appeal the final decision to the Board within ninety days or within twelve months could bring an action in the United States Claims Court, the predecessor of the Court of Federal Claims. Braughler did not pursue either of these avenues. Id.

On October 30, 1992, the Corps informed Braughler that it wanted to close out the contract because the time for appealing the final decision had expired. Braughler, 96-1 BCA at 140,312. By letter dated November 30, 1992, Braughler responded that its “submittal of February 10,1988 did not constitute a ‘claim’ under the Contract Disputes Act, and therefore the Contracting Officer’s final decision of November 28[sic], 1990 was not valid.” Braughler requested that the contracting officer issue a final decision, and it submitted a new claim certification dated December 7, 1992 with the letter. Braughler, 96-1 BCA at 140,312. The certification recited as follows:

I, David L. Braughler, certify that the claim submitted by our letter dated 10 February 1988 and its attachments for the Delay Caused by Untimely Approval of the Existing Stilling Basin Cofferdam in the amount of $137,648.04 is made in good faith, that the supporting data are accurate and complete to the best of my knowledge and belief, and the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

Id. No other materials were enclosed with the letter. Id.

The contracting officer did not issue a final decision. Id. Subsequently, on January 18, 1994, pursuant to section 605(c)(5) of the Contract Disputes Act (“CDA”), 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Boland, Inc.
Armed Services Board of Contract Appeals, 2025
A Best Services Inc.
Armed Services Board of Contract Appeals, 2024
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Goodsell v. United States
Federal Claims, 2017
KBAJ Enterprises, LLC t/d/b/a Home Again
Armed Services Board of Contract Appeals, 2016
KBAJ Enterprises, LLC t/b/d/a Home Again
Armed Services Board of Contract Appeals, 2016
Al-Juthoor Contracting Co. v. United States
129 Fed. Cl. 599 (Federal Claims, 2016)
Estes Express Lines v. United States
123 Fed. Cl. 538 (Federal Claims, 2015)
Woodies Holdings, L.L.C. v. United States
115 Fed. Cl. 204 (Federal Claims, 2014)
Northrop Grumman Computing Systems, Inc. v. United States
101 Fed. Cl. 362 (Federal Claims, 2011)
Newtech Research Systems LLC v. United States
99 Fed. Cl. 193 (Federal Claims, 2011)
Paradigm Learning, Inc. v. United States
93 Fed. Cl. 465 (Federal Claims, 2010)
OK's Cascade Co. v. United States
87 Fed. Cl. 739 (Federal Claims, 2009)
Lublin Corp. v. United States
84 Fed. Cl. 678 (Federal Claims, 2008)
Parker v. United States
77 Fed. Cl. 279 (Federal Claims, 2007)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
States Roofing Corp. v. United States
70 Fed. Cl. 299 (Federal Claims, 2006)
Lockheed Martin Corp. v. United States
70 Fed. Cl. 745 (Federal Claims, 2006)
Record Steel & Construction, Inc. v. United States
62 Fed. Cl. 508 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
127 F.3d 1476, 42 Cont. Cas. Fed. 77,183, 1997 U.S. App. LEXIS 29370, 1997 WL 662672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dl-braughler-company-inc-v-togo-d-west-secretary-of-the-army-cafc-1997.