David Boland, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 6, 2025
Docket60498
StatusPublished

This text of David Boland, Inc. (David Boland, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Boland, Inc., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) David Boland, Inc. ) ASBCA No. 60498 ) Under Contract No. W912P8-10-C-0079 )

APPEARANCES FOR THE APPELLANT: Denis L. Durkin, Esq. Michael S. Vitale, Esq. Baker & Hostetler LLP Orlando, FL Carys A. Arvidson, Esq. Daniel Lund III, Esq. Phelps Dunbar, LLP New Orleans, LA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney William G. Meiners, Esq. Trial Attorney U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN

This appeal arises from a U.S. Army Corps of Engineers (USACE) contract awarded to David Boland, Inc. (Boland) involving the replacement and construction of floodwalls as part of a hurricane protection project in New Orleans, Louisiana. Boland has brought this appeal on behalf of its primary subcontractor, Target Construction, Inc. (Target). Boland alleges that it and Target encountered materially different subsurface conditions from what was represented in the contract documents, including a void present under the area where a temporary retaining structure (TRS) was to be constructed, which resulted in the TRS flooding, and timber piles that made pile driving conditions more difficult. Boland contends this constitutes a Type 1 differing site condition. In the alternative, Boland asserts that the contract’s specifications were defective. USACE counters that Boland has failed to demonstrate the existence of a differing site condition, that the contract’s specifications were not defective, and that the flooding was caused by Boland and Target’s failure to properly install the TRS. The Board conducted a two-day hearing in New Orleans, Louisiana. Only entitlement is before us. We deny the appeal. FINDINGS OF FACT

The Contract

1. On March 5, 2010, USACE issued Solicitation No. W912P8-10-B-0054 (R4, tab 10 1 at GOV00087; tab 75 at GOV001674). This solicitation sought firms interested in performing work pursuant to USACE’s Lake Pontchartrain and Vicinity (LPV) Hurricane Protection Project (R4, tab 75 at GOV001670-71). The work specified in the solicitation involved the replacement and construction of floodwalls along Haynes Boulevard in New Orleans, Louisiana (id. at GOV001676).

2. On May 13, 2010, USACE awarded Contract No. W912P8-10-C-0079 at a total price of $19,472,000 (R4, tab 5).

3. Relevant to this appeal, the contract’s scope required Boland to design and install a temporary restraining structure (TRS) to facilitate the construction of a sluice gate structure across the existing St. Charles pump station culvert. The sluice gate structure “ties into adjacent floodwalls to create a continuous line of flood protection along the south shore of Lake Pontchartrain.” (R4, tab 283 at 1)

4. A TRS, or cofferdam, is a structure that a contractor typically builds when an excavation is necessary to construct a footing or foundation, whether for a building or a wall. It also serves to protect workers from water infiltration and from soil loads collapsing. Its purpose is to keep the excavation area dry, usually with assistance from pumps. (Tr. 1/28; 2/16)

5. The TRS was needed to facilitate construction of a floodwall tie-in at the St. Charles Street box culvert and was subjected to water surges from Lake Pontchartrain (R4, tab 282 at 1).

6. Boland’s bid to perform work for contract line-item number 10, Modifications to St. Charles Pump Station Culvert, was a lump sum price of $1,161,000 (R4, tab 39 at GOV000956).

The TRS Specifications

7. As part of its work of furnishing, designing, and installing the TRS, Boland was required to fill the space between the existing base slab and the sheet pile used for the

1 Tabs 1-240 refer to a Rule 4 file that USCAE also submitted for ASBCA Nos. 59313 and 60294, appeals filed by Boland involving the same contract. Tabs 251-284 are in the Rule 4 file that was submitted for Appeal No. 60498 2 TRS with a concrete plug as shown on Section A of Drawing S-37 (R4, tab 75 at GOV002074; tab 240 at 138).

8. Section 01 53 00.02 12 of the contract’s specifications was entitled “Temporary Restraining Structures.” The specifications described the scope of the TRS work as follows:

This work shall consist of designing, furnishing, installing, maintaining and subsequently removing all temporary retaining structures required to complete this project. The Contractor shall be solely responsible for the design, layout, construction, maintenance and subsequent removal and disposal of all elements of the temporary retaining structures.

(R4, tab 75 at GOV002074)

9. Section 1.4 of the contract’s TRS specifications required Boland to submit shop drawings of the TRS layout bearing the stamp and signature of the registered professional engineer who designed the TRS (id. at GOV002074-75).

10. Section 1.5.1 of the TRS specifications provided that the contractor was to use and rely on the following in developing the shop drawings: “soil borings, design shear strength profile(s) and unit weight data presented in the plans and/or in the figure(s) attached at the end of this section for its design” (id. at GOV002075).

11. Section 1.5.3.4 of the TRS specifications, entitled “Designs and Modifications,” further required that:

All designs and any subsequent modifications to the design presented above shall be performed, certified and stamped by a Registered Professional Engineer and submitted to the Contracting Officer for review and approval. The Registered Professional Engineer shall be present at the Contractor Quality Control preparatory and initial inspections. The Contractor shall, as a part of the Quality Control, furnish a signed statement by the design Professional Engineer stating that the installation is in conformance with the approved design.

(id. at GOV002076)

3 12. Section 1.5.2 of the TRS specifications required the TRS to be capable of maintaining an elevation of +6 feet of water from Lake Pontchartrain and a minimum tip elevation of the sheet piling of -45 feet (id. at GOV002075).

13. Section 3.1.2 of the TRS specifications, “Driving,” contained the following language:

The Contractor is advised that buried stumps or similar debris may be encountered periodically on the sheet pile wall alignment and appropriate consideration should be given to hard driving conditions should they occur.

(id. at GOV002078)

The TRS Contract Drawings

14. Contract drawings S-33 through S-41 are labeled as drawings applicable to the “St. Charles Pump Station” work (R4, tab 240 at 134-142).

15. Contract drawing S-37, entitled “St. Charles Pump Station Temporary Restraining Structure,” includes a depiction of a TRS design plan as well as a depiction of the existing culvert, the culvert foundation, and timber piles supporting the foundation, the location of TRS sheet piles. (id. at 138).

16. Drawing S-37 set forth the construction of an east and west TRS separated by an existing box culvert (id.).

17. Drawing S-37 included the notation “SHEET PILE SIZE PZ27” and further indicated that the tip elevation of the sheet piles (i.e., the depth to which the sheet piles were to be driven) was -45 feet (id.).

18. Drawing S-37 included the following notation:

GENERAL SHAPE OF COFFERDAM IS FOR ILLUSTRATION PURPOSES ONLY. THE CUT-OFF ELEVATION AND TIP ELEVATIONS SHOWN ON THE DRAWING ARE MINIMUM REQUIRED. MEMBER SIZE[S] ARE GIVEN FOR BIDDING PURPOSES ONLY. CONTRACTOR SHALL PROVIDE AN EXCAVATION / COFFERDAM / DEWATERING

4 PLAN DESIGNED AND STAMPED BY A REGISTERED ENGINEER.

(Id.)

19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Pacific Alaska Contractors, Inc. v. The United States
436 F.2d 461 (Court of Claims, 1971)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
David Boland, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-boland-inc-asbca-2025.