Arlington Alliance, Ltd. v. United States

685 F.2d 1353, 30 Cont. Cas. Fed. 70,218, 231 Ct. Cl. 347, 1982 U.S. Ct. Cl. LEXIS 438
CourtUnited States Court of Claims
DecidedAugust 11, 1982
DocketNo. 122-81L
StatusPublished
Cited by19 cases

This text of 685 F.2d 1353 (Arlington Alliance, Ltd. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arlington Alliance, Ltd. v. United States, 685 F.2d 1353, 30 Cont. Cas. Fed. 70,218, 231 Ct. Cl. 347, 1982 U.S. Ct. Cl. LEXIS 438 (cc 1982).

Opinion

SKELTON, Senior Judge,

delivered the opinion of the court:

In this case the plaintiff, Arlington Alliance, Ltd., (Arlington or plaintiff) has filed suit against the United States (defendant or the government) under 28 U.S.C. §1491 for damages in excess of $50,000, together with interest and attorneys’ fees, for alleged breaches of three lease contracts, described below, by the General Services Administration (GSA). The government has filed a motion for summary judgment in which it contends that we lack jurisdiction of the case because the plaintiff has an adequate remedy under the contracts, but has failed to exhaust its administrative remedies under the disputes clause of the leases as required by law. The government denies that the GSA breached the contracts, which, if true, deprives us of jurisdiction under 28 U.S.C. 1491.

The government also says in the alternative that if the Contract Disputes Act, 41 U.S.C. 601 et seq. (the Act) applies to plaintiffs claims in Count I of its petition, we lack jurisdiction of the claims because the plaintiff failed to certify to the claims as required by 41 U.S.C. 605(c)(1) (quoted below) and otherwise failed to comply with the Act when it filed its claims with the contracting officer. It ^appears that the law and the facts are with the government and we decide the case in its favor.

The facts are generally as follows.

Arlington is a limited partnership which owns two highrise office buildings in Arlington, Virginia, known as the [349]*349James Polk Building and the Zachary Taylor Building. On or about January 15, 1970, the General Services Administration (GSA), as lessee, entered into a written lease of certain premises in the James Polk Building (Polk premises) with the James Polk Corporation, which lease was drafted and prepared by the government.

On or about February 17, 1970, GSA, as lessee, entered into a written lease of certain premises in the Taylor Building (Taylor Units 1 and 2) with the Zachary Taylor Corporation. By lease supplement on September 27, 1976, additional premises in the building (Taylor Unit 3) were leased to GSA. This lease was also drafted and prepared by the government.

The Polk and Taylor buildings were conveyed to Arlington on February 7, 1974, and Arlington thereby succeeded to all the rights and remedies of the lessors.

Each lease provides that rent adjustments are to be made periodically to provide for increases or decreases in general real estate taxes and specified operating costs, commencing on or by the following dates:

Leased Premises Rent Escalation Date

Taylor Unit 3 September 27, 1979

Polk Premises July 8, 1980

Taylor Units 1 And 2 September 20, 1980

Each lease contains a Tax Escalation clause providing a specified formula for the calculation of the escalated rent to be paid on account of increases in general real estate taxes and an Operating Cost Escalation clause providing that 90 days before the date for rent escalation, Arlington would provide the government with statements of Arlington’s past and projected operating costs (rent escalation proposal) for purposes of negotiating the rent escalation due under each lease, and that, after negotiation, the government would pay to Arlington the agreed amount of such negotiated escalated rent, if any, by the date provided for rent escalation, or, if the parties failed to reach an agreement, the government would provide the services in the leased premises for itself within 90 days thereafter.

[350]*350Pursuant to these provisions, Arlington provided the GSA contracting officer with rent escalation proposals and supporting data in writing as follows:

Leased Premises Rent Escalation Rent Escala-Proposal Sub- tion Date mission Date

Taylor Unit 3 June 27, 1979 September 27, 1979

Polk Premises April 7, 1980 July 8, 1980

Taylor Units 1 & 2 June 19, 1980 September 20, 1980

In 'such data, Arlington claimed that the amount of escaíated rent due under the Polk lease should be calculated on the basis of $119,747.22 for operating costs rent escalation ($4,095 per square foot per year) and $3,129.68 for general real estate taxes rent escalation ($.107 per square foot per year over 280,880 square feet).

Arlington claimed that the amount of escalated rent due under the Taylor lease should be calculated on the basis of $35,369.65 for operating costs rent escalation ($1,173 per square foot per year, for September 27, 1976, lease supplement only, over 34,074 square feet) and -$689.59 for general real estate taxes rent escalation (-$.023 per square foot per year, for September 26, 1976, lease supplement only) (the yearly rent escalation for the remainder of the Taylor lease would be $3.91 per square foot, comprised of $3,689 for operating costs and $.221 for taxes over 354,550 square feet).

Arlington did not certify that the claims were made in good faith, that the supporting data was accurate and complete to the best of its knowledge and belief, and that the amount requested accurately reflects the contract adjustment for which it believes the government is liable. Such a certification is required by 41 U.S.C. §605(c)(l) where the claim amounts to more than $50,000, which is the case here.1

[351]*351After the plaintiff had filed these rent escalation proposals and claims with the GSA (the last of which was filed June 19, 1980), the GSA discussed them with the plaintiff from time to time, but no agreement was reached regarding them. However, the plaintiff never asked for a decision by the contracting officer as required by 41 U.S.C. §605(a).2

On August 12, 1980, Arlington filed suit against the government in the Eastern District Court of Virginia (C.A. No. 80-0773-A) in which it sought damages by alleging that the GSA had breached the Polk and Taylor leases by failing to adjust and escalate the rents which it claimed were due under the leases. That case was dismissed without prejudice on Arlington’s motion so that it could file suit on its claims in this court. At the time that suit was filed, Arlington advised the GSA that it was "washing its hands of the administrative process” and that it desired a judicial determination of its claims.

On February 19,1981, Arlington wrote letters to the GSA that it had terminated the leases as of August 14, 1980, by serving the complaint in the district court case on the government, and that thereafter the GSA occupied the leased premises as a tenant at will and by reason thereof was required to pay the fair rental value of the premises which it alleged was at least $16 per square foot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hansen Bancorp, Inc. v. United States
67 Fed. Cl. 411 (Federal Claims, 2005)
United Sales, Inc. v. United States
40 Cont. Cas. Fed. 76,842 (Federal Claims, 1995)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)
Aleman Food Services, Inc. v. United States
37 Cont. Cas. Fed. 76,199 (Court of Claims, 1991)
Shirley Construction Corp. v. United States
37 Cont. Cas. Fed. 76,155 (Court of Claims, 1991)
City of El Centro v. United States
35 Cont. Cas. Fed. 75,724 (Court of Claims, 1989)
Frawley v. United States
34 Cont. Cas. Fed. 75,503 (Court of Claims, 1988)
Aeron Marine Shipping Co. v. United States
10 Cl. Ct. 236 (Court of Claims, 1986)
Prefab Products, Inc. v. United States
33 Cont. Cas. Fed. 74,378 (Court of Claims, 1986)
Richard L. Thoen v. The United States
765 F.2d 1110 (Federal Circuit, 1985)
Rider v. United States
32 Cont. Cas. Fed. 73,473 (Court of Claims, 1985)
Gunn-Williams v. United States
32 Cont. Cas. Fed. 73,106 (Court of Claims, 1984)
T.J.D. Services, Inc. v. United States
32 Cont. Cas. Fed. 72,871 (Court of Claims, 1984)
Conoc Construction Corp. v. United States
31 Cont. Cas. Fed. 71,371 (Court of Claims, 1983)
LePeck Construction Corp. v. United States
31 Cont. Cas. Fed. 71,174 (Court of Claims, 1983)
Warchol Construction Co. v. United States
30 Cont. Cas. Fed. 71,088 (Court of Claims, 1983)
Metric Construction Co. v. United States
30 Cont. Cas. Fed. 70,793 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
685 F.2d 1353, 30 Cont. Cas. Fed. 70,218, 231 Ct. Cl. 347, 1982 U.S. Ct. Cl. LEXIS 438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arlington-alliance-ltd-v-united-states-cc-1982.