LePeck Construction Corp. v. United States

31 Cont. Cas. Fed. 71,174, 2 Cl. Ct. 470, 1983 U.S. Claims LEXIS 1749
CourtUnited States Court of Claims
DecidedMay 11, 1983
DocketNo. 433-82C
StatusPublished

This text of 31 Cont. Cas. Fed. 71,174 (LePeck Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LePeck Construction Corp. v. United States, 31 Cont. Cas. Fed. 71,174, 2 Cl. Ct. 470, 1983 U.S. Claims LEXIS 1749 (cc 1983).

Opinion

OPINION

WOOD, Judge:

In this action, filed August 30, 1982, plaintiff sues to recover $1,439,159.00, representing increased costs alleged to be due and owing in consequence of governmental delays during the performance of a 1977 contract (Contract No. GS-02B-17,187, hereinafter Contract 17,187) between plaintiff and defendant.

Defendant has moved for summary judgment dismissing the complaint, asserting that the action is (a) barred by plaintiff’s failure to file suit within twelve months following its receipt of a written decision from the contracting officer on the “delay” claim herein and the statute of limitations contained in section 10(a)(3) of the Contract Disputes Act of 1978, Pub.L. 95-563, 92 Stat. 2388, 41 U.S.C. § 609(a)(3) (Supp. V 1981)1, and (b) that plaintiff is precluded from obtaining judicial review of the contracting officer’s decision denying that claim by its failure to exhaust administrative remedies.

Plaintiff’s “objections and responses” to defendant’s motion do not dispute the facts (hereinafter stated) on which that motion rests. Nor does plaintiff directly challenge the government’s argument that prosecution of this action — at least as a separate one — is barred by limitations. Plaintiff’s position appears to be, rather, that “all of the counts and claims” here presented, even “if technically time barred as a ‘separate’ action, can and should be treated as an amended or supplemental pleading to * * ” the complaint in LePeck Construction Co. v. United States, Docket No. 325-80C.2 Plaintiff has accordingly filed herein what it terms a “cross-motion to amend” the complaint in Docket No. 325-80C.

Sections 10(a)(1) and (3) of the 1978 act, supra, 41 U.S.C. §§ 609(a)(1) and (3), provide in pertinent part as follows3:

(a)(1) * * * in lieu of appealing the decision of the contracting officer under section 605 of this title to an agency board, a contractor may bring an action [472]*472on the claim in the United States Court of Claims, notwithstanding any contract provision, regulation, or rule of law to the contrary.4
* * * * * *
(3) Any action under paragraph (1) * * shall be filed within twelve months from the date of the receipt by the contractor of the decision of the contracting officer concerning the claim * * *.

As of 1977, “General Provisions (Standard Form 23-A)” for fixed price government construction contracts included a “Disputes” clause providing in substance that a contracting officer’s decision on any question within the scope of the said clause “shall be final and conclusive unless, within 30 days from the date of receipt of [a copy of such decision] the Contractor * * * ” appeals in writing to the head of the agency involved or his duly authorized representative. 41 C.F.R. § 1-7.602-6 (1977). That standard clause was included in Contract 17,187. Pursuant to Section 7 of the 1978 act, 92 Stat. 2385, 41 U.S.C. § 606 (Supp. V 1981), however, plaintiff was entitled, upon electing to proceed with its delay claim under the 1978 act, to a longer (90-day) period within which to appeal in writing to the head of the agency involved.5

II

In pertinent substance, Contract 17,187, executed September 8, 1977, provided that plaintiff would perform certain “New Construction-Masonry Work” for the government (acting through the General Services Administration) at the Federal Correctional Institution for Adults (FCI), Otisville, New York, for a contract price of $3,734,000.00.6 Plaintiff thereafter entered into a subcontract with Bafill Construction Corporation for the performance of portions of the masonry work, and into a subcontract with Williamsburg Steel Products Company for the performance of certain hollow metal (and other) work, required of plaintiff pursuant to the terms of Contract 17,187.

During performance of Contract 17,187, two separate “claims” arose. According to the complaint in Docket No. 433-82C, the claims asserted herein, called “the ‘delay’ (and ‘coordination’) claims,” allegedly arose between September 29,1977, and March 29, 1978; elsewhere, however, plaintiff asserts that the “delay” claims arose December 14, 1977, upon defendant’s suspension of all field work, “and continued through November 30,1979.” The claims asserted in Docket No. 325-80C, called the “grout” claim, and based on allegedly defective government specifications, assertedly arose between April 1, 1978, and May 31, 1979.

On May 25, 1979, plaintiff submitted to the contracting officer, pursuant to section 6 of the 1978 act, a written, duly certified, “grout” claim. The contracting officer denied that claim in writing on March 7,1980, and on June 25, 1980, plaintiff filed a “direct access” action on its “grout” claim,7 pursuant to section 10(a)(1) of the 1978 act.8 That action was docketed as No. 325-80C, and assigned to Judge Wiese.

On January 21, 1981, plaintiff submitted to the contracting officer its written, duly [473]*473certified, “delay” claim.9 The contracting officer issued a written decision denying that claim in its entirety June 12, 1981. Plaintiff received a copy of that decision June 16,1981. Plaintiff did not appeal that decision to “an agency board of contract appeals” pursuant to section 7 of the 1978 act within ninety days thereafter, and it did not file suit in the Court of Claims, pursuant to section 10(a)(1) of the 1978 act, within twelve months thereafter.10 These inac-tions have given rise to, and form the basis for, defendant’s present motion.

Ill

The government says, first, that to the extent plaintiff purports to sue under the “direct access” provisions of sections 10(a)(1) and (3) of the 1978 act, such an action, to be timely, must be brought within the “twelve month limit established by the Act * * * ” and, if not commenced within that “definite limitation period,” is beyond the jurisdiction of this court. Gregory Lumber Co. v. United States, 229 Ct.Cl.(Docket No. 134-81C, Order, filed January 8, 1982). This action was not commenced within the twelve-month period following plaintiff’s receipt of the contracting officer’s written decision on the “delay” claim asserted herein.

Defendant adds that to the extent plaintiff’s claim of right to relief in Docket No. 433-82C may rest upon any other jurisdictional basis, that claim is nonetheless barred. In this connection, defendant asserts that since plaintiff took no appeal whatever from the contracting officer’s de-cisión denying the “delay” claim advanced in Docket No. 433-82C, it is thereby precluded from pressing that claim by a failure to exhaust administrative remedies.11

Plaintiff cannot, and does not, deny that this suit was not commenced within the “definite limitation period” prescribed by section 10(a)(3). Nor does plaintiff attempt to controvert in any way the factual components of defendant’s failure to exhaust argument.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The United States v. The Northern Paiute Nation
393 F.2d 786 (Court of Claims, 1968)
Zidell Explorations, Inc. v. The United States
427 F.2d 735 (Court of Claims, 1970)
Essex Electro Engineers, Inc. v. The United States
702 F.2d 998 (Federal Circuit, 1983)
Blau v. Lamb
191 F. Supp. 906 (S.D. New York, 1961)
Monroe Garment Co. v. United States
488 F.2d 989 (Court of Claims, 1973)
Troup Bros.
618 F.2d 123 (Court of Claims, 1979)
Monroe M. Tapper & Associates v. United States
611 F.2d 354 (Court of Claims, 1979)
Arlington Alliance, Ltd. v. United States
685 F.2d 1353 (Court of Claims, 1982)
Mitchell v. RKO Rhode Island Corp.
148 F. Supp. 245 (D. Massachusetts, 1956)
Alessi v. Raybestos-Manhattan, Inc.
448 U.S. 911 (Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,174, 2 Cl. Ct. 470, 1983 U.S. Claims LEXIS 1749, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lepeck-construction-corp-v-united-states-cc-1983.