Islands Mechanical Contractor, Inc.

CourtArmed Services Board of Contract Appeals
DecidedApril 13, 2017
DocketASBCA No. 59655
StatusPublished

This text of Islands Mechanical Contractor, Inc. (Islands Mechanical Contractor, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Islands Mechanical Contractor, Inc., (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Islands Mechanical Contractor, Inc. ) ASBCA No. 59655 ) Under Contract No. N69272-06-C-0012 )

APPEARANCE FOR THE APPELLANT: . James E. Krause, Esq. Jacksonville, FL

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Matthew S. Hawkins, Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SWEET

This is an appeal of a contracting officer's deemed denial of a claim by Islands Mechanical Contractor, Inc. (IMC). The government has moved to dismiss. We grant the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 1

1. In 2006, the Department of the Navy awarded IMC Contract No. N69272-06-C-0012 (contract 0012), a firm-fixed-price contract to provide wastewater treatment system repairs at Naval Station Guantanamo Bay, Cuba (2nd amended compl. ilil 1, 18, 34).

2. IMC began performance in 2006 (2nd amended compI. ii 34 ).

3. IMC alleges that it encountered differing and unforeseen site conditions (2nd amended compl. ilil 19, 35). In particular, IMC alleges that the Naval Facilities Engineering Command (NAVF AC) provided defective plans and specifications, which did not contain correct information on existing electrical supply systems, water lines, and sewer lines (id. ii 28).

4. IMC alleges that it submitted requests for information (RFis) to NAVF AC seeking guidance regarding how to proceed. IMC alleges that NAVF AC did not respond to all of the RFis (2nd· amended compl. ilil 19, 35, 40). Nor has NA VFAC issued a suspension or stop work order (id. ilil 22, 40). Therefore, on 3 April 2009,

1 For purposes of this motion only, we accept the allegations in the second amended complaint as true. IMC placed all of its equipment on stand-by status. IMC alleges that contract 0012 remains in stand-by status. (Id. ilil 38, 43)

5. IMC alleges that the failure to respond to the RFis caused delay and damages (2nd amended compl. ifil 25, 29, 41). In particular, IMC alleges that the uncertainty of not knowing when NA VF AC was going to respond to the RFis forced IMC to maintain equipment on stand-by status (id. if 30). IMC also alleges that, as a result of the delay, the warranties or guaranties on the installed equipment have expired (id. if 45). Further, IMC alleges that some of the installed equipment will need to be replaced, and additional work beyond the scope of work will be required to complete the project (id. ilil 45, 51 ).

6. IMC alleges that NAVF AC provided IMC with a draft modification on 21 September 2009. IMC alleges that the draft modification would have resolved the outstanding RFis. However, IMC refused to sign the draft modification because it contained language waiving IMC's right to seek additional compensation for the damages it incurred. (2nd amended comp I. if 44)

7. In response to the draft modification, IMC submitted a proposal to complete contract 0012 for $373, 121.72. NAVFAC has not accepted that proposal. (2nd amended comp I. if 154)

8. On 11 July 2014, IMC submitted a request for equitable adjustment (REA) (R4, tab 18).

9. On 29 July 2014, IMC resubmitted the REA as a certified claim. In the claim, IMC sought $2, 151,801.86 in direct labor and equipment costs, $2,308,966.96 in indirect overhead costs, and "$373,121. 78 pursuant to its proposal...for the completion of the Contract and to NAVFAC's Draft Modification dated July 31, 2013, once it receives direction from NA VF AC on the outstanding RFI[ s]." (R4, tab 19 at G-662-63)

10. After a deemed denial, IMC filed an appeal and complaint with the Board (compl.).

11. We stayed proceedings, and IMC certified a revised claim with the contracting officer on 30 June 2015. The revised claim sought $1,736,599.39 in direct labor and equipment costs, $1,182,427.45 in indirect overhead costs, and "$373,121.78 pursuant to its proposal...for the completion of the Contract and to NAVFAC's Draft Modification dated July 31, 2013, once it receives direction from NA VF AC on the outstanding RFI[s]." (R4, tab 25 at G-716-18)

12. On 17 May 2016, IMC filed an amended complaint with the Board, and certified a second revised claim to the contracting officer. The second revised claim- which is the operative claim-sought $1,494,996.09 in stand-by equipment costs,

2 $479,382.79 in home office overhead costs, and "$373,121.78 pursuant to its proposal...for the completion of the Contract and to NA VFAC's Draft Modification elated July 31, 2013, once IMC receives direction from NAVF AC on the outstanding RFI[s]." The second revised claim also sought "an extension of time." The second revised claim did not request that NA VF AC accept equipment without warranties or guaranties or pay replacement costs; provide direction to IMC; or modify the contract for IMC to perform additional work. (R4, tab 28 at G-767-68)

13. On 25 July 2016, IMC filed a second amended complaint-which is the operative complaint. The second amended complaint seeks $1,494,996.09 in stand-by equipment costs, $479,382.79 in home office overhead costs, and $373,121.78 "pursuant to its proposal for the completion of the Contract." (2°d amended comp I. ilil 26, 62, 153-54) (citation omitted). In the "Relief Requested" section, the second amended complaint requests that we:

A. Determine that the NAVF AC Contracting Officer's refusal to notify the Contractor of the date by which the decision will be made is a deemed denial;

B. Determine that IMC's claim is valid pursuant to the Contract Disputes Act;

C. Find that NA VF AC is responsible for damages incurred by IMC for the factual and legal reasons outlined above;

D. Direct NA VF AC to make payment to IMC of the total of the sum certain amounts under the CLAIMS Section above, including standby or idle equipment, and office overhead in the amount of $1,974,378.88 during the period from April 3, 2009 through December 31, 2013;

E. Direct NA VF AC to accept equipment that has remained exposed to the elements, installed by IMC pursuant to the plans but left unfinished due to the non- actions of NA VF AC, without warranties or guaranties, or to pay any costs to replace such equipment and the labor cost to remove the nonfunctioning equipment and install new equipment;

F. Direct NA VF AC to provide direction to IMC to allow completion of the Contract;

3 G. Direct NA VF AC to modify the Contract for IMC to perform the additional work outlined in the proposal from IMC dated February 15, 2013 in the amount of $373,121.78;

H. Direct NA VF AC to add to the Contract as many days as necessary to bring the Contract current plus the days needed to complete the original scope of work plus the days necessary to complete the additional work outlined in the Proposal from IMC in the amount of $373, 121.78[.]

(Id. at 34-35) (Citation omitted)

14. The government has moved to dismiss, arguing that we do not possess jurisdiction because IMC seeks specific performance and injunctive relief, and failed to certify a claim seeking a sum certain as a matter of right.

DECISION

We do not possess jurisdiction over the appeal because IMC failed to certify a claim for a sum certain as a matter of right. 2 Under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, we only possess jurisdiction over an appeal if a contractor submits a cognizable claim to the contracting officer. Rejlectone, Inc. v. Dalton, 60 F.3d

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Ferguson
60 F.3d 1 (First Circuit, 1995)
Essex Electro Engineers, Inc. v. The United States
960 F.2d 1576 (Federal Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Islands Mechanical Contractor, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/islands-mechanical-contractor-inc-asbca-2017.