J.P. Donovan Construction, Inc. v. Mabus

469 F. App'x 903
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 27, 2012
Docket2011-1162
StatusUnpublished
Cited by2 cases

This text of 469 F. App'x 903 (J.P. Donovan Construction, Inc. v. Mabus) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.P. Donovan Construction, Inc. v. Mabus, 469 F. App'x 903 (Fed. Cir. 2012).

Opinion

RADER, Chief Judge.

The Armed Services Board of Contract Appeals dismissed the claim of J.P. Donovan Construction, Inc. (“Donovan”) for lack of jurisdiction. J.P. Donovan Constr., Inc., ASBCA No. 55335, 10-2 BCA ¶ 34,-509, 2010 WL 2899029 (July 16, 2010). The Board held that Donovan did not submit a valid claim under the Contract Disputes Act of 1978 (“CDA”), 41 U.S.C. §§ 601-13 (1998), in view of the Federal Acquisition Regulation (“FAR”). In the absence of any reversible error, this court affirms.

I.

On September 18, 2002, Donovan entered into Contract No. N62467-02-C-2747 (“Contract”) with the United States Navy Department (“Navy”) to repair runways at the Naval Air Station, Key West, Florida. [JA 2, 21, 33.] The Contract contained the FAR disputes clause, which *905 defined “claim” as “a written demand or ... assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain.... ” 48 C.F.R. § 52.233-1 (2002). [JA 2.] The Contract also contained a Defense Federal Acquisition Regulations (“DFARS”) clause regarding requests for equitable adjustment. 48 C.F.R. § 252.243-7002 (1998).

In October 2002, Donovan subcontracted with Costello Industries, Inc. (“Costello”). [JA 2, 21.] Work began on November 13, 2002 and was completed on May 9, 2003. On August 9, 2004, on behalf of Costello, Donovan submitted a letter (“August Letter”) to the contracting officer requesting an equitable adjustment (“REA # 2”). In part, the August letter stated: “Of the $559,764.00 that Costello is claiming, Donovan is herein stating that Donovan has or will have approximately $55,000.00 of additional direct and administrative costs that should be added to this Costello requested amount.” J.A. 124. The contracting officer rejected this request for exceeding the simplified acquisition threshold; for missing the certification requirement of title 10, section 2410(a); and for insufficient “disclosure of all relevant facts.” J.A. 126.

On January 14, 2005, Costello submitted to Donovan another REA for $559,764.00 and asked Donovan to certify and submit the claim to the Navy. [JA 2.] On March 7, 2005, Donovan submitted Costello’s REA and a CDA certification to the contracting officer. [JA 2.] Donovan’s March 7, 2005 letter (“March Letter”) was titled “Submit-tal of Claim for Equitable Adjustment ...” and stated, in relevant part:

Of the $559,764.00 that Costello is claiming, Donovan is herein stating that Donovan has or will have approximately $65,000.00 of additional direct and administrative costs that should be added to this Costello requested amount. These Donovan costs are for previous expenditures for Donovan’s consultants whilst the Claim was entitled REA# 2 as well as for previous costs expended by Donovan for necessary outside legal efforts.

J.A. 3, 42. On November 1, 2005, the contracting officer issued a final decision denying Donovan’s claim of $624,764 which included Costello’s claim of $559,764 and Donovan’s claim of S65,000. [JA 3, 43.]

On January 27, 2006, Donovan filed a notice of appeal of the contracting officer’s final decision with the Board which stated, “[t]he amount of the claim is $624,764.00.” [JA 4, 123.] In March 2006, Donovan filed a complaint before the Board seeking money damages for Costello. The complaint was amended in 2009 to include the following prayer for relief: “Money damages for overhead costs [Donovan] incurred arising from or related to [Costello’s] claim under its subcontract with [Donovan].” J.A. 4, 7, 25. The parties engaged in an extensive discovery period. On January 28, 2010, the Navy submitted a motion to dismiss for lack of jurisdiction or in the alternative motion to stay proceedings, alleging that Donovan’s certification was qualified and not made in good faith. [JA 135-56.]

On March 23, 2010, the Board sent the parties a letter asking sua sponte whether the language in Donovan’s March Letter (“Donovan has or will have approximately $65,000 of additional direct and administrative costs that should be added to this Costello requested amount” of $559,764.00) “result[s] in a claim which does not state a ‘sum certain,’ thus negating the Board’s jurisdiction of the appeal.” J.A. 39-40. The parties briefed this issue and the Navy submitted a motion to dismiss for failure to state a sum certain. [JA 59.] The Board granted the Navy’s motion. Specifically, the Board determined that it lacked jurisdiction because Costello’s claim for $559,764.00 and Donovan’s “add-ons” *906 were not separate claims and that the entire claim was not in a sum certain due to the qualifying language as to Donovan’s claim. [JA 1-6.] The Board did not make a determination concerning the Navy’s motion to dismiss for lack of jurisdiction due to Donovan’s alleged bad faith. Donovan appealed the Board’s decision, and this court possesses jurisdiction under 28 U.S.C. § 1295(a)(10).

II.

The statute sets this court’s standard of review:

(1) the decision of the agency board on a question of law is not final or conclusive; but (2) the decision of the agency board on a question of fact is final and conclusive and may not be set aside unless the decision is — (A) fraudulent, arbitrary, or capricious; (B) so grossly erroneous as to necessarily imply bad faith; or (C) not supported by substantial evidence.

41 U.S.C. § 7107(b). The Board’s dismissal for lack of jurisdiction is a question of law. Transamerica Ins. Corp. v. United States, 973 F.2d 1572, 1576 (Fed.Cir.1992). This court reviews the Board’s legal determinations without deference. England v. Sherman R. Smoot Corp., 388 F.3d 844, 848 (Fed.Cir.2004).

The “jurisdictional prerequisites to any appeal” under the CDA are that “the contractor must submit a proper claim ... [and] ... the contractor must have received the contracting officer’s final decision on that claim.” M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1328 (Fed.Cir.2010) (citing James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1541-42 (Fed.Cir.1996)). “Each claim by a contractor against the government shall be in writing and shall be submitted to the contracting officer for a decision,” 41 U.S.C. § 7103

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
469 F. App'x 903, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jp-donovan-construction-inc-v-mabus-cafc-2012.