North Wind Construction Services, LLC

CourtArmed Services Board of Contract Appeals
DecidedFebruary 13, 2024
Docket63548, 63549, 63641, 63642, 63733, 63750, 63751, 63759, 63760, 63761, 63762
StatusPublished

This text of North Wind Construction Services, LLC (North Wind Construction Services, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Wind Construction Services, LLC, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) North Wind Construction Services, LLC ) ASBCA Nos. 63548, 63549, 63641 ) 63642, 63733, 63750 ) 63751, 63759, 63760 ) 63761, 63762 ) Under Contract No. W91237-21-C-0003 )

APPEARANCES FOR THE APPELLANT: Dana W. Lang, Esq. Womble Bond Dickson (US) LLP Charleston, SC

Joshua A. Mullen, Esq. Joshua R. Funderburke, Esq. Womble Bond Dickinson (US) LLP Nashville, TN

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Matt D. Coakley, Esq. Joshua J. McCarroll, Esq. Jack D. Myers, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Huntington

OPINION BY ADMINISTRATIVE JUDGE MELNICK GRANTING THE GOVERNMENT’S MOTION TO DISMISS ASBCA NOS. 63548 AND 63549 AS MOOT

On July 15, 2021, the Army Corps of Engineers (government) awarded North Wind Construction Services, LLC (NWCS), the contract identified above for the design and construction of a seepage barrier at the Portsmouth, Ohio levee (ASBCA Nos. 63548, 63549 compl. ¶¶ 5, 16). 1 NWCS proposed a secant wall for the barrier (compl. ¶ 15). After NWCS began construction, the government claimed its work did not meet contract specifications because there was no bonded interface between piles and NWCS was required to employ joint cleaning procedures between bonded joints (compl. ¶ 20). NWCS believes that the contract specifications only required barriers

1 This complaint, one of several from these consolidated appeals, is cited throughout unless otherwise indicated. containing panel joints to have a bonded interface. It maintains that a secant wall is not composed of panels. (Compl. ¶¶ 21-26) Additionally, NWCS expected that permeability and strength would be tested from cores taken out of the solid mass of the piles, while the government directed the use of cores taken from the intersections of the primary and secondary piles (compl. ¶¶ 34-38).

On October 20, 2022, NWCS submitted non-monetary claims to the contracting officer for contract interpretation (compl. ¶ 45). On March 1, 2023, NWCS filed two notices of appeal from the contracting officer’s decision that were docketed as ASBCA Nos. 63548 and 63549 and consolidated. The combined complaint seeks a declaration that NWCS’ technical proposal, including its selection of a secant wall, was part of the contract. It also asks the Board to declare that use of a secant wall was not a deviation from the specifications and therefore did not require a variance, specifications applicable to a panel type wall were inapplicable to verifying the properties of a secant wall, and both permeability and strength could be measured through the solid portions of the piles. (Compl. ¶¶ 56, 63)

On July 21, 2023, after NWCS appealed its contract interpretation claims, the government terminated the contract for default (gov’t mot. at 3; app. resp. at 3). NWCS appealed the default, which is docketed as ASBCA No. 63733 and consolidated with these appeals. Among the allegations NWCS advances in that appeal are that the government imposed the improper contract requirements that NWCS raised in the declaratory relief appeals (ASBCA No. 63733 compl. ¶¶ 49-77). Also consolidated here are NWCS’ appeals from claims for the costs arising from a secant wall demonstration section, a haul road, and for associated government delays (ASBCA Nos. 63641, 63642, 63750, 63751, 63759, 63760, 63761, 63762).

Because the contract has now been terminated for default, the government asks us to dismiss as moot the two original appeals seeking declarations of the contract’s terms (ASBCA Nos. 63548 and 63549).

It has long been recognized that this Board’s Contract Disputes Act (CDA) jurisdiction includes granting declaratory relief when appropriate. See 41 U.S.C. §§ 7101-09; Alliant Techsystems, Inc. v. United States, 178 F.3d 1260, 1269-70 (Fed. Cir. 1999). Actions seeking only a declaration of a contract’s terms are potentially proper when additional contract performance remains to be accomplished, the costs of which might be affected by the ruling. As NWCS concedes, “a nonmonetary appeal should survive if a favorable ruling . . . results in the avoidance of costs rather than a recovery of money” (app. resp. at 7 (citing J&J Maint., Inc., ASBCA No. 63013, 23-1 BCA ¶ 38,353)). Given that this contract has now been terminated, and there are no future performance costs that could be avoided, there is no purpose for these actions. For this reason, we have historically dismissed as moot appeals seeking a declaration of the terms of fully performed or terminated contracts. See Windamir

2 Dev., Inc., ASBCA No. 63461, 24-1 BCA ¶ 38,484 at 187,045; Shirley Constr. Corp., ASBCA No. 35868, 89-2 BCA ¶ 21,590 at 108,720; Poysky Bros., ASBCA No. 33935, 87-3 BCA ¶ 20,180 at 102,146. The law also disfavors affording declaratory relief such as what NWCS seeks in these two appeals when standard legal remedies are available to adequately protect its interests. See Securiforce Int’l Am., LLC v. United States, 879 F.3d 1354, 1360-62 (Fed. Cir. 2018); Alliant, 178 F.3d at 1271-72.

NWCS’ citation to Tactical Network Corp., ASBCA No. 62963, 21-1 BCA ¶ 37,942, does not alter our conclusion. There, after a pro se appellant appealed to us the government’s interpretation of its contract, the government terminated the contract for default. The appellant then filed a “motion to join” in the existing appeal seeking the Board to convert the termination for default to a termination for convenience. The Board treated the motion to join as a new notice of appeal challenging the default. It consolidated the appeals and declined the government’s request to dismiss the declaratory action as moot, saying the issues it presented were relevant to the default. Instead of overturning our prior precedent dismissing appeals seeking declarations of the terms of terminated contracts, which it could not do, we view Tactical Network as limited to its circumstances, giving administrative leeway to a pro se appellant so that it could fully join the issues it sought to present. See GLJ, Inc., ASBCA No. 62964, 22-1 BCA ¶ 38,121 at 185,184. NWCS is represented by counsel and does not require the kind of accommodation afforded to the pro se appellant in Tactical Network.

NWCS suggests that retention of these two appeals on our docket is also required by M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323 (Fed. Cir. 2010), to enable our review of the contract in its appeal of the termination for default, ASBCA No. 63733. Maropakis says that “a contactor seeking an adjustment of contract terms must meet the jurisdictional requirements and procedural prerequisites of the CDA, whether asserting the claim against the government as an affirmative claim or as a defense to a government action.” 609 F.3d at 1331. Here, the default termination is a government claim that it bears the burden of proving justified. See Securiforce, 879 F.3d at 1363; Incircle Mgmt., Inc., ASBCA No. 62684, 23-1 BCA ¶ 38,442 at 186,841. Challenges NWCS may make to the government’s reading of the defaulted contract would not seek an adjustment to its terms. Cf. ASFA Int’l Constr. Indus. and Trade, Inc., ASBCA No. 57880, 14-1 BCA ¶ 35,736 at 174,910-911 (holding Maropakis inapplicable to an assertion that contract rights were waived).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
North Wind Construction Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-wind-construction-services-llc-asbca-2024.