CASHMAN EQUIPMENT CO. VS. WEST EDNA ASSOC. C/W 65819/66452

2016 NV 69
CourtNevada Supreme Court
DecidedSeptember 29, 2016
Docket61715
StatusPublished

This text of 2016 NV 69 (CASHMAN EQUIPMENT CO. VS. WEST EDNA ASSOC. C/W 65819/66452) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CASHMAN EQUIPMENT CO. VS. WEST EDNA ASSOC. C/W 65819/66452, 2016 NV 69 (Neb. 2016).

Opinion

132 Nev., Advance Opinion IA IN THE SUPREME COURT OF THE STATE OF NEVADA

CASHMAN EQUIPMENT COMPANY, A No. 61715 NEVADA CORPORATION, Appellant, vs. ILE WEST EDNA ASSOCIATES, LTD., D/B/A MOJAVE ELECTRIC, A NEVADA SEP 2 9 2016 CORPORATION; WESTERN SURETY TRACIE K. LINDEMANu__ CLE Tie UP,REME COMPANY, A SURETY; AND THE BY CHIEF DEI4TY CLERK WHITING TURNER CONTRACTING COMPANY, A MARYLAND CORPORATION, Respondents. CASHMAN EQUIPMENT COMPANY, No. 65819 NEVADA CORPORATION, Appellant, vs. WEST EDNA ASSOCIATES, LTD., D/B/A MOJAVE ELECTRIC, A NEVADA CORPORATION; WESTERN SURETY COMPANY, A SURETY; THE WHITING TURNER CONTRACTING COMPANY, A MARYLAND CORPORATION; QH LAS VEGAS LLC, A FOREIGN LIMITED LIABILITY COMPANY; PQ LAS VEGAS, LLC, A FOREIGN LIMITED LIABILITY COMPANY; LWTIC SUCCESSOR LLC, AN UNKNOWN LIMITED LIABILITY COMPANY; AND FC/LW VEGAS, A FOREIGN LIMITED LIABILITY COMPANY, Respondents. CASHMAN EQUIPMENT COMPANY, A No. 66452 NEVADA CORPORATION, Appellant, vs. WEST EDNA ASSOCIATES, LTD., D/B/A MOJAVE ELECTRIC, A NEVADA CORPORATION; WESTERN SURETY COMPANY, A SURETY; THE WHITING TURNER CONTRACTING COMPANY, A

: r. 24411 Cp. rtettei c7.-3oCIS MARYLAND CORPORATION; QH LAS VEGAS LLC, A FOREIGN LIMITED LIABILITY COMPANY; PQ LAS VEGAS, LLC, A FOREIGN LIMITED LIABILITY COMPANY; LWTIC SUCCESSOR LLC, AN UNKNOWN LIMITED LIABILITY COMPANY; AND FC/LW VEGAS, A FOREIGN LIMITED LIABILITY COMPANY, Respondents.

Consolidated appeals from a district court injunction, final judgment, and post-judgment attorney fees and costs order in a construction contract dispute. Eighth Judicial District Court, Clark County; Rob Bare, Judge. Reversed and remanded with instructions.

Howard & Howard Attorneys PLLC and Jennifer R. Lloyd, Brian J. Pezzillo, and Marisa L. Maskas, Las Vegas, for Appellant.

Holley, Driggs, Walch, Fine, Wray, Puzey & Thompson and Brian W. Boschee and William N. Miller, Las Vegas, for Respondents.

BEFORE THE COURT EN BANC.'

OPINION By the Court, CHERRY, J.: In this matter, we consider whether an unconditional release from a bottom-tiered contractor (Cashman) to a higher-tiered contractor

"The Honorable Nancy M. Saitta, Justice, having retired, this matter was decided by a six-justice court.

SUPREME COURT OF NEVADA 2 (0) 1947A (Mojave) is enforceable when the higher-tiered contractor properly paid the middle-tiered contractor (Cam) but the middle-tiered contractor failed to pay the bottom-tiered contractor. We conclude that NRS 108.2457(5)(e) precludes enforcement of the release when the check given in exchange for the release is not honored by the payor's bank. Although the check that Mojave gave to Cam for payment to Cashman cleared the bank, the check that Cam gave to Cashman did not clear the bank. Therefore, the unconditional release that Cashman gave to Cam and Mojave is void. We also consider whether equitable fault analysis may be used to reduce an award in a mechanic's lien case. Based on this court's decision in Lamb v. Goldfield Lucky Boy Mining Co., 37 Nev. 9, 16, 138 P. 902, 904 (1914) (holding that "equity jurisprudence" "ha[s] no place" in determining the rights of a mechanic's lienholder), we conclude that it may not. Therefore, we reverse the decision of the district court and remand this case to the district court to recalculate Mojave's liability to Cashman with instructions that the unconditional release is void. Following recalculation, the parties may move the district court for attorney fees and costs as Nevada law permits. FACTS This case stems from the new Las Vegas City Hall construction project. Respondent Mojave was chosen to be the electrical subcontractor for the project. Mojave contracted with Western Surety to provide a payment bond and, later, a mechanic's release bond for this project. Mojave accepted a bid from appellant Cashman to provide specialty materials for the emergency standby power for the building. The general contractor, respondent Whiting Turner, required that Mojave

SUPREME COURT OF NEVADA

(0) 1947A involve disadvantaged business entities (DBE) in the project. Therefore, instead of contracting directly with Cashman for the services and materials, Mojave contracted with Cam and Cam contracted with Cashman. Mojave also paid Cam for the labor and supplies that Cashman provided. In exchange for an unconditional release from Cashman to Cam and Mojave, Cashman received payment via a check from Cam, but Cam stopped payment on the check. Cam gave Cashman a second check for payment, but the check was returned for insufficient funds. Cashman made additional attempts to secure payment from Cam to no avail. Upon realizing that payment was not forthcoming, Cashman filed a mechanic's lien for $755,893.89, ceased working on the project, and then filed suit. Cashman and Mojave later learned that Angelo Carvalho, Cam's owner, absconded with the funds from Mojave, which should have been forwarded to Cashman. The parties proceeded to a bench trial, and the district court awarded Cashman $197,051.87 for foreclosure of security interest and $86,600 for unjust enrichment, to be paid once Cashman enters the codes for the electrical systems to communicate with each other. Following trial, the district court denied both parties' motions for fees and costs. Cashman's appeal followed. On appeal, Cashman argues that the district court erred (1) when it declined to enforce Cashman's mechanic's lien and upheld the unconditional waiver despite lack of payment; (2) when it denied Cashman's claim for recovery through the payment bond because the court applied the defense of impossibility despite Mojave's failure to prove that its performance was impossible, or that Cam's failure to pay was not an unforeseen contingency; (3) in reducing Cashman's award based on

4 equitable fault and by requiring completed performance to receive the award; (4) when it issued a preliminary injunction for Cashman to input codes for the electrical system, even though the district court found that Cashman was likely to prevail on the merits; and (5) when it denied Cashman's motions for attorney fees and costs, even though Cashman prevailed at tria1. 2 DISCUSSION

Whether the district court erred in denying recovery to Cashman on its mechanic's lien claim by enforcing an unconditional waiver In its findings of fact and conclusions of law following the bench trial, the district court enforced the unconditional waiver and release that Cashman executed, determining that Mojave's payment to Cam constituted payment to Cashman and made Cashman's waiver enforceable. Cashman argues that the district court erred when it enforced the waiver and release of the mechanic's lien because the plain language of NRS 108.2457(5)(e) states that when a payment fails, the waiver and release are void. We review a lower court's interpretation of a contract de novo when the facts in a case are not disputed. Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 124 Nev. 1102, 1115, 197 P.3d 1032, 1041 (2008).

2In their answering brief, but without cross-appealing, the respondents seek affirmative relief on multiple claims. NRAP 3(a)(1) dictates that "an appeal permitted by law from a district court may be taken only by filing a notice of appeal with the district court clerk within the time allowed by Rule 4." (Emphasis added.) This court has clarified that cross-appeals are not exempt from NRAP 3(a)(1). See Mahaffey v. Investor's Nat'l Sec. Co., 102 Nev.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bisch v. Las Vegas Metropolitan Police Department
302 P.3d 1108 (Nevada Supreme Court, 2013)
Nebaco, Inc. v. Riverview Realty Co.
482 P.2d 305 (Nevada Supreme Court, 1971)
Elliott v. Mallory Electric Corp.
571 P.2d 397 (Nevada Supreme Court, 1977)
Personhood Nevada v. Bristol
245 P.3d 572 (Nevada Supreme Court, 2010)
Mahaffey v. INVESTOR'S NATIONAL SECURITY CO.
725 P.2d 1218 (Nevada Supreme Court, 1986)
Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.
197 P.3d 1032 (Nevada Supreme Court, 2008)
Barlow Brothers Co. v. Gaffney
55 A. 582 (Supreme Court of Connecticut, 1903)
Ringling Bros.-Barnum & Bailey Combined Shows, Inc. v. Hart
390 So. 2d 367 (District Court of Appeal of Florida, 1980)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
Lamb v. Goldfield Lucky Boy Mining Co.
138 P. 902 (Nevada Supreme Court, 1914)
I. Cox Construction Co. v. CH2 Investments, LLC
296 P.3d 1202 (Nevada Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2016 NV 69, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cashman-equipment-co-vs-west-edna-assoc-cw-6581966452-nev-2016.