Barlow Brothers Co. v. Gaffney

55 A. 582, 76 Conn. 107, 1903 Conn. LEXIS 75
CourtSupreme Court of Connecticut
DecidedJuly 24, 1903
StatusPublished
Cited by11 cases

This text of 55 A. 582 (Barlow Brothers Co. v. Gaffney) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barlow Brothers Co. v. Gaffney, 55 A. 582, 76 Conn. 107, 1903 Conn. LEXIS 75 (Colo. 1903).

Opinion

Torrance, C. J.

The bond in suit was made by John W. Gaffney and Company as principals and the other defendants as sureties, and was given for the release of a mechanic’s lien claimed by the plaintiff upon certain premises in Waterbury. The condition of the bond recited the facts upon which the lien was claimed, and ended with these words: “Now, therefore, if said John W. Gaffney & Company shall well and truly pay to the said Barlow Brothers Company all that money that may be justly and legally due it, with interest and costs, under said mechanic’s lien, this bond shall be void, otherwise good and valid.” The sum claimed by way of lien is $1,225, and the answer admits, in substance, that if the lien is a valid one, this sum, with interest, is due upon the bond.

The controlling facts relating to the validity of the lien are these: On the 3d of January, 1902, Gaffney and Company entered into a written contract with an ecclesiastical corporation of Waterbury, owning land there, to erect and complete a building on said land; and on the 6th day of the same month Gaffney and Company contracted with a corporation, called the Seeley and Upham Company, to do the plumbing on said building. Subsequently, in January, 1902, the Seeley and Upham Company sublet said plumbing contract to the plaintiff. The plaintiff completed said plumbing work on the 30th of August, 1902, but has been paid nothing thereon. Gaffney and Company claim to have paid the Seeley and Upham Company in full for said plumbing,on August 28tb, 1902. On the 27th of September, 1902, the plaintiff gave written notice to the ecclesiastical corporation, as required by law, of its intention to claim a lien upon said building and land for said plumbing, and three days later filed its certificate of lien as required by law. When said certificate was filed there was due to Gaffney and Company from said ecclesiastical corporation the sum of about $5,000.

On the sole ground that in doing this plumbing work the *109 plaintiff was a subcontractor of the Seeley and Upham Company, the trial court held that the plaintiff, under our law, was not entitled to a lien; and whether it erred or not in so holding is the main question in the case. The answer to this question depends upon the construction of our statutes relating to mechanics’ liens.

The statutes specially bearing upon this question are now to be found in §§ 4135 and 4137 of the General Statutes. Section 4135 provides, among other things, as follows: “ If any person shall have a claim . . . for materials furnished or services rendered in the construction ” of any building, “ and such claim shall be by virtue of an agreement with or by consent of the owner of the land upon which such building is erected . . . or of some person having authority from or rightfully acting for such owner in procuring such labor or materials, such building with the land on which it stands shall be subject to the payment of such claim. Such claim shall be a lien on such land ” and building. Section 4137 provides, among other things, as follows : “No person other than the original contractor for the construction ... of the building, or a subcontractor, whose contract with such original contractor is in writing, and has been assented to in writing by the other party to such original contract, shall be entitled to claim any such lien, unless he shall, after commencing, and not later than sixty days after ceasing, to furnish materials or render services for such construction, . . . give written notice to the owner of such building that he has furnished or commenced to furnish materials, or rendered or commenced to render services, and intends to claim a lien therefor on said building. ... No subcontractor, without a written contract complying with the provisions of this section, and no person who furnishes material or renders services by virtue of a contract with the original contractor or with any subcontractor, shall be required to obtain an agreement with, or the consent of, the owner of the land, as provided in § 4135, to enable him to claim a lien under this section.”

Legislation of the kind here in question appears to have begun in this State in 1836. It extended at first only to *110 buildings erected in cities, in favor of original contractor having claims exceeding $200. Public Acts of 1836, Chap. 76. In 1839 it was extended to any dwelling-house or other building, and to subcontractors having a claim of $50 or more and having an agreement in writing with the original contractor, assented to in writing by the proprietor of the building and land. Public Acts of 1839, Chap. 29. The legislation of this kind between 1836 and 1855 was embodied in Chap. 76 of the Public Acts of the latter year. That Act provided, among other things, that the claim of the mechanic need only exceed the sum of $25; and that any person having such a claim for materials furnished or services rendered in the erection of the building should have a lien; but it also provided that no person except the original contractor should have a lien, unless within sixty days from the time he began to furnish materials and render services he notified the owner of such fact and that he intended to claim a lien therefor. It also provided that the clause as to notice should not apply to the original contractor, “nor to any subcontractor whose contract with such original contractor is in writing, and has been assented to in writing by the other party to such original contract.”

The law as embodied in the Act of 1855 remained the law upon this subject, without any change which it is material to note, down to the Revision of 1875. In 1875 the important provision requiring the claim to be “ by virtue of an agreement with or by consent of the owner,” or his agent, was added by Chap. 15 of the Public Acts of that year. In 1879 it was provided that “no subcontractor, with or without a written contract, shall be required to obtain an agreement with, or the consent of such owner, to his procuring or furnishing such labor or materials, to enable such subcontractor to claim a lien.” Public Acts of 1879, Chap. 43. In the Revision of 1888 (§ 3020) the above provision appears in this form : “No subcontractor, with or without a written contract complying with the provisions of this section [as to being in writing and assented to in writing by the owner of the land], shall be required to obtain an agreement with, or the consent *111 of, the owner of the land, as provided in section 3018, to enable him to claim a lien under this section.” By Acts passed in 1899 and 1901 this provision was amended to read as follows: “ No subcontractor, with or without a written contract complying with the provisions of this section, and no person who furnishes material or renders services by virtue of a contract with the original contractor or with any subcontractor, shall be required to obtain an agreement with, or the consent of, the owner of the land, as provided in section 3018 of the General Statutes, to enable him to claim a lien under this section.” Public Acts of 1899, Chap. 121; id. 1901, Chap. 80. This is substantially the form in which this provision appears in § 4137 of the Revision of 1902, herein-before recited.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CASHMAN EQUIPMENT CO. VS. WEST EDNA ASSOC. C/W 65819/66452
2016 NV 69 (Nevada Supreme Court, 2016)
New England Savings Bank v. Meadow Lakes Realty Co.
706 A.2d 465 (Supreme Court of Connecticut, 1998)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
Ryan v. Board of Selectmen
228 A.2d 809 (Connecticut Superior Court, 1966)
Ryan v. Board of Selectmen
27 Conn. Supp. 31 (Pennsylvania Court of Common Pleas, 1966)
New Haven Orphan Asylum v. James A. Haggerty Co.
142 A. 847 (Supreme Court of Connecticut, 1928)
George Alling'S Sons Co. v. Cheshire Street Railway Co.
75 A. 143 (Supreme Court of Connecticut, 1910)
Pere Marquette Railroad v. Baertz
74 N.E. 51 (Indiana Court of Appeals, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
55 A. 582, 76 Conn. 107, 1903 Conn. LEXIS 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barlow-brothers-co-v-gaffney-conn-1903.