New Haven Orphan Asylum v. James A. Haggerty Co.

142 A. 847, 108 Conn. 232, 1928 Conn. LEXIS 195
CourtSupreme Court of Connecticut
DecidedJuly 18, 1928
StatusPublished
Cited by21 cases

This text of 142 A. 847 (New Haven Orphan Asylum v. James A. Haggerty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Haven Orphan Asylum v. James A. Haggerty Co., 142 A. 847, 108 Conn. 232, 1928 Conn. LEXIS 195 (Colo. 1928).

Opinion

Haines, J.

The finding discloses that the plaintiff, owning land and buildings in the town of Hamden, made a contract with the Haggerty Company in October, 1923, for the construction of certain buildings and improvements thereon, and a second contract in February, 1924, for certain other work on the same property.

The work was fully performed by the Haggerty Company. The defendants Richard W. Desmond, The DeForest & Hotchkiss Company, The F. L. McDermott Iron Works, Inc., Hardwood Floors, Inc., The Connecticut Sash & Door Company, The Drazen Lumber Company, Horace E. Clark, Cairns & Funkie, Inc., and The Connecticut Adamant Plaster Company were subcontractors engaged by the Haggerty Company, and each rendered services and furnished materials pursuant to the plaintiff’s contracts with the Haggerty Company; but none of these subcontracts were in writing, nor were any of them assented to in writing by the plaintiff.

Upon the completion of the work a substantial balance of the contract price was due from the plaintiff, but the latter refused to pay because of conflicting claims by subcontractors and general creditors of the Plaggerty Company, and brought this action in the *235 nature of interpleader to determine the rights of all parties. The plaintiff waived certain claims it had first made against the Haggerty Company and for counsel fees and disbursements and agreed that the net sum due and in its hands was $20,768.70. The defendant John A. Condon was a general creditor of the Haggerty Company and served process of garnishment on this fund in the hands of the plaintiff and the same course was taken by two of the above-named subcontractors, The Adamant Plaster Company and Hardwood Floors, Inc.

At the opening of the hearing, defaults were entered against certain defendants, some by agreement and some for nonappearance, and disclaimers were filed by certain others. All the remaining parties consenting thereto in writing, the court entered an interlocutory judgment that the above-named sum be paid into court and held by the clerk subject to the final judgment of the court, and that the plaintiff and its property be freed of all claims theretofore made by the parties. It does not appear of record that a formal judgment of interpleader was entered, but the claims of the parties were made by answer and cross-complaint and were fully heard.

The fund being insufficient to pay all claimants in full, the main question presented to the court was that of priorities. The trial court adopted the views of the garnisheeing creditors, that the rights of the subcontractors dated from the time they gave notice of intention to claim their liens, and gave judgment for payment in full to the following claimants: To Cairns & Funkie, Inc., whose notice was given September 16th, 1925, $3,616; to John A. Condon, who served garnishee process October 3d, 1925, $1,698.61; to Richard W. Desmond, whose notice was given October 16th, 1925, $3,234.64; to DeForest & Hotchkiss Company, whose *236 notice was given October 23d, 1925, $751.89; to F. L. McDermott, Inc., whose notice was given October 23d, 1925, $2,841.53; to Adamant Plaster Company, which served garnishee process October 23d, 1925, $7,365.83; dividing the balance of the fund pro rata between five subcontractors whose notices were given subsequent to October 23d, 1925, the date of the Plaster Company’s garnishment, viz.: Hardwood Floors, Inc., Connecticut Sash & Door Company, Drazen Lumber Company, John E. Bassett Company and Horace E. Clark. From this judgment the last-named subcontractors, with the exception of the Bassett Company, took separate appeals, but on identical grounds.

The appellants are contending for priority over the garnisheeing creditors and equality with the other subcontractor lienors, on the ground that their right to the fund dates from the time their service began. This precise question has not heretofore been presented to this court. Where it has been passed upon in other jurisdictions there is a sharp conflict of opinion, not only or solely because of differing statutory provisions, but of differing views of the spirit and purpose of mechanics’ lien laws in general. •

That portion of our own law in which we are to seek the solution of the present question is contained in General Statutes, Rev. 1918, §§5217 to 5220, inclusive. * *237 One of the purposes of this legislation is to give to building creditors certain peculiar and different rights *238 from those enjoyed by general creditors. Chapin v. Persse & Brooks Paper Works, 30 Conn. 461, 474; National Fireproofing Co. v. Huntington, 81 Conn. 632, 634, 71 Atl. 911.

“The design of the statute was to give to one who, by furnishing services or materials, under a contract with the owner of land, has added to its value by constructing a building upon it, ... a substantial security for *239 his proper remuneration. ... To carry out this intent, it is necessary to give the statute such a construction, if its terms are doubtful, as may serve to make mechanics’ liens of some value.” Balch v. Chaffee, 73 Conn. 318, 320, 47 Atl. 327. “The mischief to be prevented was loss to those furnishing services or materials in the construction of a building, if unable to collect what might be due them on such account from the owner of the real estate.” National Fireproofing Co. v. Huntington, 81 Conn. 632, 634, 71 Atl. 911. In determining the legislative intent we may not wholly rely upon the literal meaning of particular provisions, but must proceed upon the assumption that the law was intended to be read as a whole with each provision in harmony with every other. Hartford Builders Finish Co. v. Anderson, 99 Conn. 343, 352, 122 Atl. 76.

“The mechanic’s lien law is a creature of statute, and this statute is to be construed so as to reasonably and fairly carry out its remedial intent. It is not to be construed with unreasonable strictness.” Parsons v. Keeney, 98 Conn. 745, 748, 120 Atl. 505; Cronan v. Corbett, 78 Conn. 475, 478, 62 Atl. 662; Brabazon v. Allen, 41 Conn. 361, 362.

A mechanic’s lien law was first enacted in this State in 1836. It only secured the original contractors having claims of over $200 and applied only to buildings in cities. Public Acts of 1836, Chap. 76. Three years later, by amendment, subcontractors were given the lien if their claims were $50 or more and if they had an agreement in writing with the contractor assented to in writing by the owner of the property. Public Acts of 1839, Chap. 29.

In the succeeding sixteen years, by amendments, it was provided the mechanic’s claim need only exceed $25; that any person having such a claim for services or materials should have a lien, but all save the main *240

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New England Savings Bank v. Meadow Lakes Realty Co.
706 A.2d 465 (Supreme Court of Connecticut, 1998)
Thompson & Peck, Inc. v. Division Drywall, Inc.
696 A.2d 326 (Supreme Court of Connecticut, 1997)
Waterbury Landfill Associates v. the Eastern Co., No. 0122318 (Mar. 4, 1996)
1996 Conn. Super. Ct. 1729 (Connecticut Superior Court, 1996)
First Constitution Bank v. Harbor Village Ltd. Partnership
646 A.2d 812 (Supreme Court of Connecticut, 1994)
American Home Builder's v. Blonder, No. Cv88-0040857 (Jun. 14, 1991)
1991 Conn. Super. Ct. 5624 (Connecticut Superior Court, 1991)
Nickel Mine Brook Associates v. Sakal
585 A.2d 1210 (Supreme Court of Connecticut, 1991)
Pero Building Co. v. Smith
504 A.2d 524 (Connecticut Appellate Court, 1986)
Reardon v. DeGregorio (In Re Reardon)
10 B.R. 697 (D. Connecticut, 1981)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
Camputaro v. Stuart Hardwood Corp.
429 A.2d 796 (Supreme Court of Connecticut, 1980)
Stone v. Rosenfield
104 A.2d 545 (Supreme Court of Connecticut, 1954)
Hamilton Nat. Bank v. Long
226 S.W.2d 293 (Tennessee Supreme Court, 1949)
Concettina Garofalo v. Permacrete Corporation
15 Conn. Super. Ct. 358 (Connecticut Superior Court, 1948)
Garofalo v. Permacrete Corp.
15 Conn. Supp. 358 (Pennsylvania Court of Common Pleas, 1948)
Pierce, Butler & Pierce Manufacturing Corp. v. Enders
174 A. 169 (Supreme Court of Connecticut, 1934)
Thames Lumber Co. v. Cruise
164 A. 652 (Supreme Court of Connecticut, 1933)
Burque v. Naugatuck Lumber Co.
155 A. 414 (Supreme Court of Connecticut, 1931)
Kelly v. Dewey
149 A. 840 (Supreme Court of Connecticut, 1930)
J. L. Purcell, Inc. v. Libbey
149 A. 225 (Supreme Court of Connecticut, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
142 A. 847, 108 Conn. 232, 1928 Conn. LEXIS 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-haven-orphan-asylum-v-james-a-haggerty-co-conn-1928.