Hartford Builders Finish Co. v. Anderson

122 A. 76, 99 Conn. 343, 1923 Conn. LEXIS 100
CourtSupreme Court of Connecticut
DecidedJuly 27, 1923
StatusPublished
Cited by8 cases

This text of 122 A. 76 (Hartford Builders Finish Co. v. Anderson) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Builders Finish Co. v. Anderson, 122 A. 76, 99 Conn. 343, 1923 Conn. LEXIS 100 (Colo. 1923).

Opinion

Keeleb, J.

From the finding of facts it appears that the plaintiff and all of the defendants (except Anderson and Larson) furnished materials and rendered services in the construction of a dwelling-house for Anderson and Larson upon a lot of land in West Hartford owned by them, and that the plaintiff and all of the other defendants filed mechanics’ liens against the real property; and that the commencement of each hen was the date of the beginning of rendering services or furnishing materials. Each of the lienors'was an original contractor with the owners, and there were no other general contractors. The property was sold by judg *345 ment of the court for $5,150, and a net sum of $4,855.26 remained for distribution among the lienors after payment of costs and expenses of sale. The aggregate amount due to all the lienors was $6,471.84. The court in its judgment ordered the sum remaining for distribution to be paid and apportioned pro rata among the lienors, and overruled the claim of the appellant that they should be paid in the order of precedence and priority of their incumbrances according to the dates of commencement of the various liens, from which judgment the appellant appealed, assigning the application of the rule of division adopted by the court as error.

Very little in the way of uniform doctrine can be derived from the construction which has been placed upon statutes of the different States relating to mechanics’ liens, by reason of the diversity of the terms employed. Some of them settle the question involved in the instant case by express provisions as to priority, others have more general provisions. These latter may be said to fall into two classes: in one, all liens attach from the commencement of the building; in the other, liens attach from the commencement of work or of furnishing materials. As to the former class it has been generally held that lienors prorate their claims and that among them there is no priority. In considering statutes falling in the second class, the construction has ordinarily been that priority exists, and that, as among themselves, lienors are preferred in the order of time at which they severally commenced to render services or furnish materials. The Connecticut statute is included in the second class above defined. The diligence of counsel and investigation by the court has failed to find more than two cases, Choteau, Merle & Sandford v. Thompson & Campbell, 2 Ohio St. 114, and Crowell v. Gilmore, *346 18 Cal. 370, in which, under a statute falling in the second class, it has been held that the principle of a pro rata division applies and not that of priority. It is also doubtful whether the California statute comes clearly within the second class.

In Kendall v. Pickard, 67 N. H. 470, 32 Atl. 763, the court — construing the statute of New Hampshire, P. S. Ch. 141, § 16, which provides that a contractor’s lien “shall continue for ninety days after the services are performed, or the materials or supplies are furnished, unless payment therefor is previously made, and shall take precedence of all prior [sic] claims except liens on account of taxes,” — says: “It is difficult to express in fewer or more explicit words . . . that liens of the kind in question have precedence in the order of their accrual, and, if they accrue simultaneously, in the order of the attachments made to secure them.”

The statute of New York relating to mechanic’s liens (N. Y. Consol. Laws, 1st.Ed., Vol. 3, Chap. 38, Art. 2, § 3, p. 3140), provided the contractors should have a lien on the property improved or to be improved and upon the improvement, from the time of filing a notice of such lien. The Act has been construed to give priority to lienors according to the dates of filing their respective liens. Hall v. Thomas, 110 N. Y. Supp. 979; Western Sash, D. & L. Co. v. Gaul Const. Co., 126 N. Y. Supp. 1110; Vogel & Binder Co. v. Montgomery, 133 N. Y. App. Div. 836, 118 N. Y. Supp. 10; Kelley Lumber Co. v. Otselic Valley R. Co., 136 N. Y. App. Div. 146, 120 N. Y. Supp. 415.

Passing to a review of our own statutes concerning mechanics’ liens, and decisions applicable to the question under consideration, we find that the first statute upon the subject was' enacted in 1836, Public Acts of 1836, Chap. 76; and § 1 subjects a building *347 and the land whereon it is placed, in any incorporated city, to a lien in favor of a contractor whose claim for services performed or materials furnished in the erection or repair of such building shall exceed $200, and provides that the sum due “shall be a lien on such land and building, and shall take precedence of any other lien or incumbrance, which originated subsequent to the commencement of such building or repairs, and such premises shall be liable to be foreclosed by such contractor or contractors, in the same manner as if held by mortgage.”

In 1838 the statute was amended to include buildings located anywhere in the State, and in 1839 a right of lien was extended to subcontractors. In 1855 (Public Acts of 1855, Chap. 76) there was added to § 1 of the law of 1836 above cited, the words: “subject to apportionment as provided in the fifth section of this Act.” This fifth section is substantially what we now have in General Statutes, § 5220, relating to liens of subcontractors.

Various changes were made from time to time in the provision of the lien law, but none affecting the question now under consideration "until the Revision of 1875, when the words of § 1 of the Act of 1836 were changed by striking out the word “lien,” so that the section as revised, reads: “and shall take precedence of any other incumbrance originating after the commencement” etc. No substantial change in this section was made in subsequent Revisions, and it now appears in General Statutes, § 5217. Both of these sections are printed in the foot-note.

*348 As we have stated, appellant claims precedence and priority for the various liens according to the time in which each accrued. The appellees claim an apportionment of the available fund pro rata in accordance with the amounts of their several claims, and in support of this contention advance the following reasons: First, that the rule of equity is equality, and that in default of an express provision in unmis *349 takable terms giving priority, this rule should have effect in construing the statute considered. This is the ground of decision adopted by the court, as appears from its memorandum, wherein it is said: “This statute says nothing as to priorities or pro rating, but we think the spirit and intent of the statute, the mischief which it was designed to remedy, and the application of equitable principles, all require that the statute be construed as giving an interest to each lienor in proportion to his claims.” This ground is also adopted in the two cases favorable to the contention of the appellees before referred to, Choteau, Merle & Sandford v. Thompson & Campbell, 2 Ohio St. 114, and Crowell v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Constitution Bank v. Harbor Village Ltd. Partnership
646 A.2d 812 (Supreme Court of Connecticut, 1994)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
Camputaro v. Stuart Hardwood Corp.
429 A.2d 796 (Supreme Court of Connecticut, 1980)
Bassett v. City Bank & Trust Co.
161 A. 852 (Supreme Court of Connecticut, 1932)
Kelly v. Dewey
149 A. 840 (Supreme Court of Connecticut, 1930)
New Haven Orphan Asylum v. James A. Haggerty Co.
142 A. 847 (Supreme Court of Connecticut, 1928)
City of Waterbury v. MacKen
124 A. 5 (Supreme Court of Connecticut, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
122 A. 76, 99 Conn. 343, 1923 Conn. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-builders-finish-co-v-anderson-conn-1923.