Stone v. Moomjian

103 A. 635, 92 Conn. 476, 1918 Conn. LEXIS 57
CourtSupreme Court of Connecticut
DecidedApril 30, 1918
StatusPublished
Cited by6 cases

This text of 103 A. 635 (Stone v. Moomjian) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stone v. Moomjian, 103 A. 635, 92 Conn. 476, 1918 Conn. LEXIS 57 (Colo. 1918).

Opinion

Prentice, C. J.

Under the pleadings in this case the issues presented for determination and the contentions of counsel in argument relate: (1) to the apportionment, among the plaintiff and the four defendant lienors adjudged to have valid liens, of the fund of $1,050 in the defendant Moomjian’s hands as the balance of the contract price unpaid to the contractor Ruderman, together with the interest thereon; (2) to the right of the defendant lienors to share with the plaintiff in the apportionment of a larger sum, to wit, one made up- of the $1,050 with interest and $1,200, the total of the payments made by Moomjian to Ruderman subsequent to the receipt of the plaintiff’s notice of intention to file a lien; (3) to the personal responsibility incurred by Moomjian by reason of these payments to Ruderman, and the extent of it; and (4) to the bearing of that responsibility, if any, upon any apportionment to be made. These issues divide the interested parties into three contending factions, to wit, the plaintiff, the four defendant lienors, and Moomjian, the property owner.

All parties apparently concede that the plaintiff is entitled to have his claim in some manner paid in full. Whether or not this concession is one which the law compels to be accepted as a starting point in the determination of the rights of the several claimants, we shall have occasion to inquire later on in connection with a consideration of the position which the plaintiff occupies. He at least asserts that such is the case, and that is the burden of the argument made in his behalf. As for other incidental questions touching the source or sources from which he is to obtain such pay *481 ment, which were the main subjects of discussion before us, he expresses little concern.

The defendant lienors present two alternative contentions. The first is that what they are entitled to share in, is a pro rata division among all the lienors of the unpaid fund of $1,050 and interest thereon, plus the $1,200 paid by Moomjian following his receipt of the plaintiff’s notice. The second is that the plaintiff, for the extinguishment of the indebtedness to him, should be relegated to his claim against the property-owner Moomjian growing out of the latter’s payments, greater in amount than that indebtedness, which he made to Ruderman subsequent to his receipt of the plaintiff’s notice, thereby leaving the $1,050 fund ‡0 be divided between them to the substantial satisfaction of their claims.

Moomjian, on the other hand, asserts that no apportionment of the $1,050 fund should be made which will leave any portion of the plaintiff’s claim unsatisfied, and, therefore, that so much of that fund as may be necessary for the purpose be first apportioned to its satisfaction in full, and only the balance be shared by the other lienors.

The result of Moomjian’s contention, as will readily be seen, is that he will escape with the payment of the contract price and no more, while the lienors, other than the plaintiff, will go substantially unpaid. The lienors’ contentions, on the other hand, lead to an almost diametrically opposite result, in that they will be paid in full or substantially so, and Moomjian be required to make a second or double payment of the $1,200 or some considerable portion of it.

The trial court adopted the view that the plaintiff was entitled to payment in full, and in accordance with the contention of Moomjian’s counsel ordered that the plaintiff take so much of the $1,050 fund as was *482 necessary to satisfy his claim with interest and costs, and that the other lienors share pro rata the infinitesimal balance.

Whatever equitable considerations may be urged in support of the apportionment thus made, the outstanding fact remains that such division of the fund formed by the unpaid balance of the contract price earned, is directly opposed to the plain and positive mandate of the statute. Section 4138 of the General Statutes, which deals with this subject, expressly provides that the unpaid price, in the event that it is insufficient to satisfy the claims of all subcontractor lienor claimants, shall be apportioned among them “in proportion.to the amount of the debts due them respectively.” This statutory direction has no limitation or exception, and is explicit in forbidding the recognition of any precedence among subcontractor lienors in so far as the division of the $1,050 in Moomjian’s hands is concerned

What, then, should be done in the adjustment of the conflicting claims of the parties in order that our statutory regulations may be complied with? Whatever it be, some one or more must suffer loss, and the question is as to where that loss must fall. It is evident that the plaintiff and defendant lienors do not occupy the same position in all respects, although they are by statute placed upon an equality as regards the division of any unpaid balance. The plaintiff filed notice of his intention to claim a lien when only $1,000 had been paid by the owner and $2,250 of the contract price remained to become payable. When the defendants took like action, $2,200 had been paid the contractor, and only $1,050 remained to become payable. When the intervening $1,200 payments were made, the property owner owed the defendants no duty in respect to them. He was free to make them since they were not made in advance of the terms of the contract. Clearly they *483 have no right to look for the satisfaction of their claims beyond the unpaid balance in Moomjian’s hands. It was not so with the plaintiff. He had filed his notice, and by that act had come into a position in which, as prospective lienor, Moomjian, by force of statute, owed him some duty and assumed some corresponding burden of responsibility and liability. What was that duty and burden?

The answer to this question depends upon the provisions of our statutes and the interpretation to be given to them. The defendant Moomjian contends that his duty, which he fulfilled, was to retain in his hands out of the moneys due the original contractor a sum equal in amount to the plaintiff’s claim as, in the progress of the work, it should prove to be. This might well be if our law gave to the plaintiff, as the subcontractor who first served his notice of intention duly followed by the filing of his certificate of lien, or the one who had first filed his certificate of lien, or the first to take both steps, a priority of lien of such a nature that he would be entitled to have his claim first satisfied out of any unpaid balance in Moomjian’s hands. But such is not the provision of our law. A subcontractor lienor, who serves his notice of intention to file a lien, does not, by reason of the promptness of his action, acquire any right or inchoate right of precedence over one taking a similar step later, save as intervening payments may be concerned. Neither does one, by filing a certificate of lien, thereby come into a position superior in any respect to that which others, who may follow his example, will come to occupy. The consequence in neither case is to cause any sum already due or to become due to the original contractor to be set aside as security through the resulting lien for the payment of the lienor’s particular claim and that alone. No way to accomplish that result is provided.

*484 Whatever lack of clarity and.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Electric Supply Co. v. Southern New England Telephone Co.
441 A.2d 581 (Supreme Court of Connecticut, 1981)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
Saul Ritzenberg v. Noland Company, Inc.
364 F.2d 667 (D.C. Circuit, 1966)
Biller v. Harris
161 A.2d 187 (Supreme Court of Connecticut, 1960)
J. L. Purcell, Inc. v. Libbey
149 A. 225 (Supreme Court of Connecticut, 1930)
New Haven Orphan Asylum v. James A. Haggerty Co.
142 A. 847 (Supreme Court of Connecticut, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
103 A. 635, 92 Conn. 476, 1918 Conn. LEXIS 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stone-v-moomjian-conn-1918.