Waterbury Landfill Associates v. the Eastern Co., No. 0122318 (Mar. 4, 1996)

1996 Conn. Super. Ct. 1729
CourtConnecticut Superior Court
DecidedMarch 4, 1996
DocketNo. 0122318
StatusUnpublished

This text of 1996 Conn. Super. Ct. 1729 (Waterbury Landfill Associates v. the Eastern Co., No. 0122318 (Mar. 4, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waterbury Landfill Associates v. the Eastern Co., No. 0122318 (Mar. 4, 1996), 1996 Conn. Super. Ct. 1729 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION This action was commenced by Waterbury Landfill Associates to foreclose a mechanics lien filed upon the property of The Eastern Company. Pursuant to General Statutes § 49-37 a bond was substituted for the lien, in the amount of $45,000, with The Eastern Company as principal and Aetna Casualty and Surety Company as surety. Hence this action proceeds on the bond which was given in substitution of the lien.

The facts are as follows. The Eastern Company owned property on Bridge Street in the Town of Naugatuck, Connecticut. The property included a foundry complex consisting of old CT Page 1730 buildings constructed of concrete and brick and wooden beams varying in height from one to three stories. The company had been attempting to sell the property for a year and a half prior to the events described herein, with no success. It was therefore determined that it would be best to, most economical, to demolish the buildings and sell the land unencumbered by these old buildings.

In the spring of 1993 this decision to demolish was made. There is nothing to indicate that The Eastern Company had any prior experience concerning building demolition. A Mr. John Pelloquin submitted a proposal to do the entire work of demolition and debris removal for a total contract price of $180,000. Mr. Donald Whitmore, vice-president, secretary and principal financial officer determined this to be a competitive price. Mr. Pelloquin had done some interim clean-up work for The Eastern Company and had accomplished that work in a satisfactory fashion. There is no evidence to indicate whether Mr. Pelloquin had previous experience with demolition work of this scale, or for that matter whether he had any significant experience with demolition work in general.

On May 9, 1993 The Eastern Company, acting by Mr. Whitmore, V/P Treas., signed the contract for this work. The contract was executed on a proposal form captioned "John Paul Ent. Proposal, 400 Detrich St., Dayton, Ohio 45404 (513) 224-0851. The contract was signed by "John Pelloquin" without identification of a representative capacity. The contract contains a provision that "Workers' Compensation and Public Liability Insurance on above work to be taken out by NEW START DEMOLITION". Thus three names appear on the document for the contractor.

The contract provided that payments were to be made as follows: "$40,000 when 25% is completed; $40,000 when 50% is completed; $40,000 when 75% is completed; $60,000 when completed and passed final inspection". No means or method is set forth in the contract to objectively determine when a particular level of completion, percentage of completion, has taken place. Although there are various activities required to take place, such as removal of a fuel tank, removal of contaminated soil, pumping out and disposal of transformers and the like, as part of the general demolition and disposal of debris, no percentage of completion is related to any specific item of activity. There is no evidence to indicate any oral agreement or understanding between Eastern Company and the contractor as to an CT Page 1731 event or events which would thereby constitute a particular percentage of completion of the contract.

It was the responsibility of Mr. Whitmore on behalf of The Eastern Company to form an opinion as to percentages of completion as the work progressed. The contract does not give to either party the right to make a final or conclusive decision as to percentages of completion. Mr. Whitmore viewed his function in this ongoing decision making process as being on the basis of "a reasonable man", using a "reasonable estimate" as to the achievement of percentages of completion. He viewed the progress of the work from his own office window and did on occasion actually walk on the property.

On July 9, 1993 Eastern received an invoice from New Start Demolition Co., Inc. in the amount of $40,000 on the basis that 25% of the job had been completed. Eastern issued its check to New Start Demolition Co. on July 12 in the amount of $40,000. On July 14, 1993 Eastern received an invoice from New Start Demolition Co., Inc in the amount of $40,000 claiming that 50% of the job had been completed. Eastern paid this second installation of $40,000 by its check to New Start Demolition Co., Inc. on July 28. On August 12, 1993 New Start Demolition Co., Inc. sent a third invoice to Eastern, claiming that 75% of the job had now been completed. Mr. Whitmore felt that additional work had to be done to accomplish 75% completion. Consequently Eastern sent its check on August 27, 1993 for one-half of the invoice, twenty thousand dollars, payable to Nu-Start Demolition Co., Inc. On September 17, 1993 The Eastern Company sent its check for the second payment on the invoice of August 12, 1993 payable to New Start Demolition or John Pelloquin. Mr. Pelloquin had requested the check be made out in that fashion. Mr. Whitmore thought that Mr. Pelloquin and New Start Demolition were one and the same, and all of his dealings were with Mr. Pelloquin.

At this point there remained $60,000 to be paid on the contract, to be paid "when completed and passed final inspection". On December 19, 1993 an additional invoice was received requesting an additional payment of $20,000 as "partial payment on demo". The invoice requested payment be made to "NEW START DEMOLITION CO. or John Pelloquin". On December 20, 1993 The Eastern Company issued its check to "New Start Demolition Co., Inc. or John Pelloquin" per the instruction on the invoice, the check bearing the contract proposal address of 400 Detrich CT Page 1732 Street, Dayton, Ohio 45404, which is the same address that all the other checks had been issued to. This December 20, 1993 check is unquestionably an advance payment, as no part of the $60,000 balance was payable until the job was completed and passed final inspection.

At this point in time, December 20, 1993, there was one subcontractor or other person known to the defendant to have furnished materials or rendered services on the job. A company by the name of Phoenix Soil Treatment did some oil removal work at some point in time. It is not specified in the evidence exactly when that occurred, though best recollection of the defendant places that activity at approximately July 9, 1993. There is no reason to believe that "Phoenix" has, or is making, any claim of non-payment. By the time the plaintiff entered the project in February 1994, some additional demolition work, oil tank removal, compacting of holes, removal of debris and grading remained to be accomplished (Defendant's Exhibit 14).

The plaintiff Waterbury Landfill Associates is a partnership which is and has been in the business of debris removal since 1982. It is a partnership consisting principally of the brothers Bartholomew and Vincent LoRusso. In the fall of 1993 Vincent LoRusso became aware of the accumulation of debris on the subject property.

In January 1994 Vincent LoRusso telephoned Mr. Whitmore stating that they were interested in doing the debris removal work. They had previously done some work for Eastern. Mr. Whitmore informed Mr. LoRusso that Eastern already had the contract for the entire job and that Mr. LoRusso would have to take the matter up with Mr. Pelloquin.

On February 1, 1994 Waterbury Landfill Associates transmitted to "New Start Demolition, 400 Detrich Street, Dayton, OH 45404, Atten. Mr. Pelloquin", a detailed written proposal to do the debris rubbish removal work. Several days later Mr. Bart LoRusso received a call from Mr. Pelloquin agreeing to the plaintiff's proposal. The plaintiff commenced work on February 8, 1994 and continued the work until February 22, 1994.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pawlinski v. Allstate Insurance
327 A.2d 583 (Supreme Court of Connecticut, 1973)
Rene Dry Wall Co. v. Strawberry Hill Associates
438 A.2d 774 (Supreme Court of Connecticut, 1980)
New Haven Orphan Asylum v. James A. Haggerty Co.
142 A. 847 (Supreme Court of Connecticut, 1928)
Tice v. Moore
73 A. 133 (Supreme Court of Connecticut, 1909)
Hubbell, Hall & Randall Co. v. Pentecost
93 A. 672 (Supreme Court of Connecticut, 1915)
J. L. Purcell, Inc. v. Libbey
149 A. 225 (Supreme Court of Connecticut, 1930)
Phillipe v. Thomas
489 A.2d 1056 (Connecticut Appellate Court, 1985)
Cianelli v. Levy
276 A.2d 912 (Connecticut Appellate Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 1729, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waterbury-landfill-associates-v-the-eastern-co-no-0122318-mar-4-connsuperct-1996.