METRO. SEWERAGE COMM. v. RW Const., Inc.

255 N.W.2d 293, 78 Wis. 2d 451
CourtWisconsin Supreme Court
DecidedJune 14, 1977
Docket76-221
StatusPublished

This text of 255 N.W.2d 293 (METRO. SEWERAGE COMM. v. RW Const., Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
METRO. SEWERAGE COMM. v. RW Const., Inc., 255 N.W.2d 293, 78 Wis. 2d 451 (Wis. 1977).

Opinion

78 Wis.2d 451 (1977)
255 N.W.2d 293

METROPOLITAN SEWERAGE COMMISSION OF COUNTY OF MILWAUKEE, Cross-Appellant and Respondent,
v.
R. W. CONSTRUCTION, INC., Appellant: FIDELITY & DEPOSIT COMPANY OF MARYLAND, Respondent.

No. 76-221.

Supreme Court of Wisconsin.

Argued March 29, 1977.
Decided June 14, 1977.

*452 For the appellant there were briefs by Elwin J. Zarwell, Peter W. Bunde, Ronald L. Wallenfang and Quarles & Brady, attorneys, and Joseph Swietlik and Laikin, Swietlik & Laikin, of counsel, and oral argument by Mr. Zarwell, all of Milwaukee.

For the cross-appellant and respondent there were briefs by Ewald L. Moerke, Jr., Robert Arthur Melin, *453 and Schroeder, Gedlen, Riester & Moerke, and oral argument by Mr. Melin, all of Milwaukee.

HEFFERNAN, J.

The question on this appeal is whether the trial judge on remand for determination of damages properly followed the mandate of this court in Metropolitan Sewerage Commission of County of Milwaukee v. R. W. Construction, Inc., 72 Wis.2d 365, 241 N.W.2d 371 (1976), and made a reasonable assessment of damages on the basis of a "jury type" verdict. We conclude that he did and affirm the judgment.

This is the second appeal involving this case. In the original trial, the trial judge found that R. W. Construction, Inc., in constructing a section of the Milwaukee sewerage system under bid contract, did not encounter subsurface conditions differing materially from those indicated in the bid documents. Thus, he concluded, it was not entitled to an equitable adjustment in its original contract price. Instead, the court held that Metropolitan Sewerage Commission of the County of Milwaukee, plaintiff, was entitled to a judgment of approximately $5,500,000 for breach of contract.

On appeal this court, in Metropolitan Sewerage Commission of County of Milwaukee (hereinafter M.S.C. 1), supra, found changed conditions as a matter of law and reversed. We remanded for determination of the amount of equitable adjustment (damages) to which R. W. Construction, Inc. (hereinafter R.W.) was entitled. Metropolitan Sewerage Commission's motion for rehearing on grounds that this court had applied incorrect engineering principles was denied.

On the remand, the trial judge rendered a "jury type" verdict for R.W. in the amount of $1,500,000. R.W. has now appealed, claiming the amount should have been nearly $3,000,000. Metropolitan Sewerage Commission (hereinafter M.S.C.) cross-appealed, claiming the amount should have been zero.

*454 The background to this litigation is set forth extensively in the opinion of this court dated May 4, 1976. To briefly recapitulate the facts however, M.S.C. and R.W. on May 6, 1969, entered into a $3,900,000 contract for the construction of a sewer to be located one hundred feet below the surface of the ground. After commencing work, R.W. encountered artesian water, which resulted in extensive flooding. This required unanticipated and expensive dewatering procedures. R.W. attempted to control the flooding by the use of compressed air. Compressed air from the tunnel escaped from abandoned but unplugged wells and carried carbon dioxide into neighboring homes. Because of the health hazard, the West Allis Health Commissioner on March 3, 1971, ordered the work stopped on the tunnel. R.W.'s efforts to secure an equitable adjustment to compensate for the unforeseen costs were refused by M.S.C. R.W., therefore, ceased all work and depressurized and blocked the tunnel. M.S.C. terminated the contract in June of 1971 and sued for a breach of contract.

M.S.C. was awarded damages in the sum of approximately $5,500,000.

R.W.'s counterclaim for equitable adjustment was dismissed. R.W. appealed from the judgment, and R.W. and Fidelity and Deposit Company, its surety, appealed dismissal of a counterclaim. M.S.C. cross-appealed, claiming judgment should be entered against Fidelity in the same amount as against R.W.

On May 4, 1976, this court decided that R.W., as a matter of law, had encountered changed conditions and was entitled to an equitable adjustment. We said:

"In this case R.W. argues that its damages are readily determinable, and sets forth a summary of damages amounting to nearly 3 million dollars. However, this summary does not take account of the fact that the contractor must absorb those costs, if any, due to its inefficiency *455 in planning and performance. Under these circumstances our holding here is limited to concluding that the MSC is liable for an equitable adjustment under the changed-conditions clause, and therefore we remand the case to the trial court for a hearing to determine the amount of the equitable adjustment to which R.W. is entitled. In so doing, we follow the same general procedure followed by the 7th Circuit in the Fattore Cases, which were diversity actions applying Wisconsin law in which the MSC was a party." (M.S.C. 1, at 383-84)

This court remanded the case to the trial court for entry of judgment and assessment of damages against M.S.C.

On July 15, 1976, in the trial court, R.W. filed notice of motion and motion for entry of judgment in its favor and for entry of findings of fact as follows:

Direct job costs                                          $1,473,031.05
Equipment costs                                              375,827.96
Office overhead costs                                        104,732.51
                                                          _________________
Less payment to R.W. by M.S.C.                               478,957.23
NET LOSS                                                   1,474,634.29
Bid profit without changed condition                         348,555.00
10% profit on equitable adjustment                           143,813.15
10% profit on equitable adjustment after
 contract termination                                        624,597.44
                                                           _____________
TOTAL DAMAGES                                             $2,591,599.88
Interest at $355.05 daily from Feb. 8,
  1974, to date of judgment at 7%

As a conclusion of law, R.W. asked that judgment for $2,953,613.28 be entered, reflecting the above amount plus interest. These proposed findings are derived from R.W.'s Exhibit A.[1]

M.S.C. moved for reopening of the trial to take testimony on damages. After hearing and in a decision rendered *456 August 24, 1976, the trial judge found both motions "inappropriate" and denied them.

In his decision, the trial judge interpreted M.S.C. 1 to mandate only a hearing on damages. Judge Decker, the trial judge, wrote:

"The Supreme Court neither intended to deny to the trial court the right to reopen the case for further testimony nor to compel the reopening of the case. As this court views the mandate, the trial court was to review the record with respect to the equitable adjustment (damages) to be awarded to R.W., and if it felt that it could do so on the record, it was to proceed to an adjudication on the merits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
Union Fish Co. v. Erickson
248 U.S. 308 (Supreme Court, 1919)
Kaiser Industries Corporation v. The United States
340 F.2d 322 (Court of Claims, 1965)
Phillips Construction Co., Inc. v. The United States
394 F.2d 834 (Court of Claims, 1968)
Paul Hardeman, Inc. v. The United States
406 F.2d 1357 (Court of Claims, 1969)
Guy H. Briscoe v. The United States
442 F.2d 953 (Court of Claims, 1971)
Great Lakes Dredge & Dock Co. v. United States
96 F. Supp. 923 (Court of Claims, 1951)
Metropolitan Sewerage Commission v. R. W. Construction, Inc.
241 N.W.2d 371 (Wisconsin Supreme Court, 1976)
Johann v. Milwaukee Electric Tool Corp.
72 N.W.2d 401 (Wisconsin Supreme Court, 1955)
United States v. Consolidated Elevator Co.
141 F.2d 791 (Eighth Circuit, 1944)
F. H. McGraw & Co. v. United States
130 F. Supp. 394 (Court of Claims, 1955)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
255 N.W.2d 293, 78 Wis. 2d 451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metro-sewerage-comm-v-rw-const-inc-wis-1977.