Metropolitan Sewerage Commission v. R. W. Construction, Inc.

241 N.W.2d 371, 72 Wis. 2d 365, 1976 Wisc. LEXIS 1413
CourtWisconsin Supreme Court
DecidedMay 4, 1976
Docket676 (1974)
StatusPublished
Cited by24 cases

This text of 241 N.W.2d 371 (Metropolitan Sewerage Commission v. R. W. Construction, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Sewerage Commission v. R. W. Construction, Inc., 241 N.W.2d 371, 72 Wis. 2d 365, 1976 Wisc. LEXIS 1413 (Wis. 1976).

Opinion

Wilkie, C. J.

This appeal involves a controversy over the construction on behalf of the plaintiff-respondent Metropolitan Sewerage Commission of the County of Milwaukee (MSC) of an 8,300-foot segment of underground concrete sewer beneath South 84th Street in West Allis, Wisconsin, running from West Adler to West Grant. The sewer was to have a diameter of 8 feet and was to be located about 100 feet below ground. It was to be one segment of a gravity-flow sewer system discharging at the South Shore Sewerage Treatment Plant in Oak Creek.

The most important parts of the plans and specifications provided to bidders were drawings which depicted the results of borings which the MSC caused to be made into the subsurface along the sewer route. Such borings are the typical means of apprising bidders of subsurface conditions which they are likely to encounter in tunneling underground. Sixteen test borings were made by Milwaukee Testing Laboratory, Inc., at about 500-foot intervals along the sewer route. The typed logs of these *367 borings were eventually delivered to Alvord, Burdick & Howson, a Chicago consulting firm which prepared the contract drawings from these logs.

The contract drawings of the 16 borings showed the 100 feet at and above the level of the tunnel to be composed of the glacial till deposited by the retreating glaciers which covered Wisconsin millions of years ago. This glacial till is an irregular, chaotic type of soil. In very general terms, however, the borings indicated a clay layer interspersed with pockets of silt and sand in the first 50-70 feet below the ground. Clay is an impermeable soil which does not hold a great deal of water and through which water does not easily pass. Beneath this layer a layer of more permeable soils like sand and gravel was indicated, although substantial pockets of clay were also shown. Sand and gravel are permeable soils which can contain a great deal of water and through which water easily flows. Just below the glacial till (and the level of the tunnel) was limestone bedrock.

The contract drawings also indicated that a great deal of ground water was present. In general, the water table was shown as about 40-50 feet below ground. The presence of water increases the difficulty of underground construction, because the water must be controlled by using compressed air in the tunnel to force the water away from the construction, or by using deep wells to draw down the water table, or by a combination of these two methods. But artesian water creates many more construction problems than static water. Artesian water is water under hydrostatic pressure because it is confined between impermeable layers of soil. Such a water-containing layer is called an artesian aquifer and it has a recharging capacity which frustrates easy dewatering. Static water, on the other hand, is ground water that is not under pressure and is not replaced once removed or drawn down. None of the contract drawings affirmatively indicated the presence of artesian water. The drawings stated only “water at” a certain level, whereas *368 the accepted manner of indicating artesian water is to note “water encountered at” a certain level and then to state that the water “rose” in the boring to another higher level. In fact, although the log of boring No. 8 typed by Milwaukee Testing Laboratory, Inc., stated “Water encountered at 35'/Rose in hole to 16'6",” this information was deleted from the contract drawing of boring No. 8, which stated only “water at el. 120.7.”

Several bids were submitted and R. W. Construction, the defendant-appellant here, was the successful bidder, having bid 3.9 million dollars. Three other contractors (Peter Kiewit Sons’ Company, W. J. Lazynski, Inc., and S & M Constructors) bid, respectively, 4.5, 4.9, and 4.95 million dollars.

The contract (MSC Contract No. 222) contained the following changed-conditions clauses:

“20. Changed Conditions. Should the Contractor encounter, or the Sewerage Commission discover during the progress of the work, subsurface and (or) latent conditions at the site materially differing from those shown on the drawings or indicated in the specifications, the attention of the Engineer shall be called immediately to such conditions before they are disturbed. The Engineer shall thereupon promptly investigate the conditions and, if he finds that they materially differ from those shown on the drawings, or indicated in the specifications, he shall at once, make such changes in the drawings and (or) specifications as he may find necessary and any increase or decrease of and (or) difference in time resulting from such changes shall be adjusted as provided in Paragraph 19 of this contract.”

Paragraph 19 of the contract provided:

“19. Changes. The Engineer may at any time, by a written order and without notice to the sureties, make changes in the drawings and/or specifications of this contract and within the general scope thereof. If such changes cause an increase or decrease in the amount due under this contract, or in the time required for its performance, an equitable adjustment shall be made and the contract shall be modified in writing accordingly. No *369 changes shall be made without first obtaining the approval in writing of the Engineer or his duly authorized representative. Any claim for adjustment under this article must be asserted within ten (10) days from the date the change is ordered, unless the Engineer shall for proper cause extend such time. But nothing provided in this article shall excuse the Contractor from proceeding with the prosecution of the work so changed.”

The parties entered into the contract on May 6, 1969, and R. W. began to sink its workshaft in August. Almost immediately, R. W. ran into artesian water, a condition which persisted throughout the construction period. When the shaft was down only 37 feet, water “boiled up” and broke through under the sheeting, bringing with it running silt and sand. Similar problems were encountered all the way to the level of the sewer tunnel, causing delays and costing R. W. much more than its bid estimates.

The next major encounter with this artesian condition occurred in January 1970, after the shaft had been sunk 100 feet to tunnel grade, and as R. W. was attempting to “turn the eye” horizontally in order to begin mining for the tunnel. A mixed face of running silt and sand above and clay below was encountered. After even the extraordinary method of freezing the soil with liquid nitrogen did not work, R. W. consulted Arthur Chase, an engineering consultant with extensive tunneling experience. He recommended lowering the tunnel grade three feet into the clay in order to avoid the top layer of running silt and sand. This change was approved by the MSC and made under the changed-conditions clause.

Between May and September of 1970, R. W. mined about 950 feet of the tunnel. Water was controlled by a combination of compressed air and deep wells. On September 29, 1970, however, as the workers were locking out, water broke through the tunnel heading, bringing with it a great deal of soil and flooding the heading. This breakthrough virtually halted mining progress. The running water and soil could not be controlled by R. W.’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kostal v. Life Insurance Co. of North America
834 F. Supp. 2d 882 (E.D. Wisconsin, 2011)
Milwaukee Transport Services, Inc. v. Department of Workforce Development
2001 WI App 40 (Court of Appeals of Wisconsin, 2001)
Dan Nelson Construction, Inc. v. Nodland & Dickson
2000 ND 61 (North Dakota Supreme Court, 2000)
Management Computer Services, Inc. v. Hawkins, Ash, Baptie & Co.
557 N.W.2d 67 (Wisconsin Supreme Court, 1996)
Mooney's, Inc. v. South Dakota Department of Transportation
482 N.W.2d 43 (South Dakota Supreme Court, 1992)
Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Beco Corp. v. Roberts & Sons Construction Co.
760 P.2d 1120 (Idaho Supreme Court, 1988)
PT & L. CONST. v. Dept. of Transp.
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
P.T. & L. Construction Co. v. State, Department of Transportation
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
Zontelli & Sons, Inc. v. City of Nashwauk
373 N.W.2d 744 (Supreme Court of Minnesota, 1985)
Highland Construction Co. v. Union Pacific Railroad
683 P.2d 1042 (Utah Supreme Court, 1984)
United Pacific Insurance v. Metropolitan Sewerage Commission
338 N.W.2d 298 (Court of Appeals of Wisconsin, 1983)
S & M Constructors, Inc. v. City of Columbus
434 N.E.2d 1349 (Ohio Supreme Court, 1982)
In Matter of Complaint Against Seraphim
294 N.W.2d 485 (Wisconsin Supreme Court, 1980)
Joseph F. Trionfo & Sons, Inc. v. BD. OF EDUC. OF HARFORD CTY.
395 A.2d 1207 (Court of Special Appeals of Maryland, 1979)
METRO. SEWERAGE COMM. v. RW Const., Inc.
255 N.W.2d 293 (Wisconsin Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
241 N.W.2d 371, 72 Wis. 2d 365, 1976 Wisc. LEXIS 1413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-sewerage-commission-v-r-w-construction-inc-wis-1976.