Vesper Construction Company, Inc., a New Mexico Corporation v. Rain for Rent, Inc., an Arizona Corporation

602 F.2d 238
CourtCourt of Appeals for the Tenth Circuit
DecidedSeptember 6, 1979
Docket77-1711
StatusPublished
Cited by13 cases

This text of 602 F.2d 238 (Vesper Construction Company, Inc., a New Mexico Corporation v. Rain for Rent, Inc., an Arizona Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vesper Construction Company, Inc., a New Mexico Corporation v. Rain for Rent, Inc., an Arizona Corporation, 602 F.2d 238 (10th Cir. 1979).

Opinion

MARKEY, Chief Judge.

Appeal from judgment of the United States District Court for the District of New Mexico, on a jury verdict awarding Vesper Construction Co. (Vesper) $300,000 for breach of contract by Rain For Rent, Inc. (Rain). Denial of a jury trial on Rain’s Miller Act counterclaim, exclusion of certain reports, and jury instructions on damages in construction cases, are involved. We affirm.

Background

The Contract

Vesper held a subcontract for excavation and road building on the Bureau of Reclamation’s Navajo Indian Irrigation Project near Farmington, New Mexico. Part of that work requires wetting of land areas. Vesper contracted with Rain for “prewetting” services. Vesper and Rain later substituted a new contract, under which Rain agreed to lease to Vesper the irrigation equipment then in use on the job, plus a high-pressure pump, and an AC diesel unit. Vesper was totally responsible for operation of all equipment. Repeated interruptions of the wetting operation impeded Vesper’s performance of its subcontract on the Project. Rain’s failure to install a pressure line of adequately high pressure was alleged as the cause of the interruptions and the breach of contract forming the basis for Vesper’s suit.

Vesper’s complaint alleged that Rain’s breach resulted in damages of $1,300,000. Rain separately sued the United States and *240 Vesper for $37,894, under the Miller Act, 40 U.S.C. §§ 270a et seq. When the district court ordered the suits consolidated, Rain converted its complaint into a counterclaim.

Vesper filed a timely jury demand. Rain did not. Two months before trial, Judge Payne wrote both counsel that the Miller Act claims “will have to be a non-jury .,” adding, “I have tried to get counsel in to dicuss [sic] this matter personally but I haven’t had any success,” and inviting counsel once more to discuss with him the problems engendered by the Miller Act claims. That invitation was ignored.

On the first day of trial, just prior to jury selection, the court reminded counsel that it, not the jury, would decide the Miller Act claims. Rain objected, and, for the first time, demanded a jury trial. The court overruled the objection and denied the demand, because “a jury is not proper in a Miller Act case,” and because no jury had been timely requested.

The sequence was thus:

DATES VESPER v. RAIN FOR RENT RAIN FOR RENT v. VESPER
U. S. v. ROSIER
05/07/76 Vesper files its
complaint.
06/04/76 Vesper files its jury demand. Rain files its complaint.
06/28/76 Vesper answers.
07/08/76 Time for filing jury demand expires under F.R.Civ.P. 38(b).
08/04/76 THE CASES ARE CONSOLIDATED BY ORDER OF THE COURT.
10/18/76 Rain files its answer.
03/25/77 Judge’s letter announcing that Rain’s claims would not be tried to the jury.
05/23/77 Judge repeats, at first day of trial, that Rain’s claims would not be tried to the jury.

The Trial

Vesper’s expert itemized damages total-ling $670,554. Its accountant described a loss of $763,037 as the difference between Vesper’s income from the job and its costs.

Rain’s defense was Vesper’s improper operation of the pressure line. As proof, it offered reports on pump operation. The reports were made, at the request of Vesper’s manager, by George Coffelt, who owned the land on which the pump was located, and who was hired by Vesper to operate the pump.

As foundation for the Coffelt reports, Rain attempted to read Coffelt’s deposition, taken ex parte, without notice but with court permission, after Rain filed suit but before Vesper was served. Vesper objected. After a day’s delay, Rain called Vesper’s manager as an adverse witness. Coffelt having been located, Vesper again objected and requested that Coffelt be called. Though Coffelt was brought to court and interviewed by Rain, it declined to call him, saying his testimony would not be “beneficial to the defendant in this case at this point.” The court then permitted continued examination of the manager.

The manager said the reports were on Vesper’s stationery, were signed by Coffelt, and “should have been” kept in his business records. The court sustained Vesper’s hear *241 say objection to admission of the reports, and Rain rested.

Declining Rain’s proffered instructions, the court gave this “uncertainty” instruction:

Uncertainty as to amount of damages does not preclude recovery if the fact of damage is established and if a reasonable basis of computation is provided or if there is a basis for a reasoned conclusion;

and this “substantial factor” instruction:

Plaintiff’s damages must have been caused by defendant’s breach of contract. To find that the breach caused the injury, you must find that the breach was a substantial factor in bringing about the harm.

After the jury retired, Rain renewed requests for certain instructions and objected to the “uncertainty” instruction.

The jury returned a verdict of $300,000 in favor of Vesper. The court dismissed Rain’s counterclaim, because Rain had breached its contract with Vesper, and had neither given the required Miller Act notice “setting forth with substantial accuracy the amount alleged to be owed by Vesper,” nor proved that Vesper owed $37,894.

Issues

The issues are whether the district court erred in: (1) denying a jury trial of Rain’s counterclaim, (2) excluding the Coffelt reports, or (3) its jury instructions.

OPINION

1. Denial of jury trial on Rain’s counterclaim was proper.

. Rain’s failure to file a timely jury demand pursuant to F.R.Civ.P. 38(b), 1 constituted a waiver of its right to jury trial. F.R.Civ.P. 38(d). 2 A subsequent consolidation cannot alone revive Rain’s right to a jury trial. Cf. Walton v. Eaton Corp., 563 F.2d 66 (3rd Cir. 1977) (right to demand jury trial in second, duplicative action cannot be revived where plaintiff expressly waived jury trial in first action); Roth v. Hyer, 142 F.2d 227 (5th Cir. 1944) (right to demand jury in new trial not revived by reversal where plaintiff waived jury at first trial by failure to make timely demand).

Rain’s reliance here on its at-trial jury demand is unavailing. Prior to trial, the court gave Rain more than ample opportunity to make the demand available to it under F.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. RGA Home Health Services, Inc.
713 F. App'x 732 (Tenth Circuit, 2017)
Nutraceutical Corp. v. Von Eschenbach
459 F.3d 1033 (Tenth Circuit, 2006)
Grundberg v. Upjohn Co.
137 F.R.D. 365 (D. Utah, 1991)
In Re Kaiser Steel Corporation, Debtor
911 F.2d 380 (Tenth Circuit, 1990)
In re D.M.C.
503 A.2d 1280 (District of Columbia Court of Appeals, 1986)
Block v. Fishman
610 F. Supp. 282 (E.D. Wisconsin, 1985)
Tuttle/White Constructors v. MONTGOMERY, ETC.
385 So. 2d 98 (District Court of Appeal of Florida, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
602 F.2d 238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vesper-construction-company-inc-a-new-mexico-corporation-v-rain-for-ca10-1979.