Mooney's, Inc. v. South Dakota Department of Transportation

482 N.W.2d 43, 1992 S.D. LEXIS 21, 1992 WL 41373
CourtSouth Dakota Supreme Court
DecidedMarch 4, 1992
Docket17397
StatusPublished
Cited by19 cases

This text of 482 N.W.2d 43 (Mooney's, Inc. v. South Dakota Department of Transportation) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mooney's, Inc. v. South Dakota Department of Transportation, 482 N.W.2d 43, 1992 S.D. LEXIS 21, 1992 WL 41373 (S.D. 1992).

Opinions

SABERS, Justice.

Contractor appeals partial summary judgment. We affirm.

FACTS

Mooney's, Inc. (Mooney’s) is a Minnesota based contractor. Mooney’s received notices soliciting bids on three asphalt resurfacing projects from the South Dakota Department of Transportation (DOT). The first was for resurfacing Highway 273 in Lyman County, the second and third were for resurfacing Route 6154 and Highway 26 in Sully County. Mooney’s received the notices three weeks prior to the time the bids were due. The notices did not include the plans and specifications of the projects, which Mooney’s then requested. This information arrived a week later.

The plans and specifications designated two gravel pits as sources of aggregate for the respective projects. Aggregate, or gravel, is an important material in road construction. Two qualities of aggregate are significant in determining its acceptability for use in building a highway: plasticity and gradation. Plasticity is a measure of the aggregate’s cohesiveness. Gradation refers to the distribution of particle sizes in the aggregate, from coarse to fine. The South Dakota Standard Specifications for Roads and Bridges specify acceptable ranges of values for both plasticity and gradation for aggregate to be used on the State’s highways.

The bid information contained extensive “pit data” on the designated pits for Lyman County and both Sully County projects. DOT employees had taken samples from 20 locations at the Sully County pit and 8 and 22 locations respectively from areas A & B in the Lyman County pit. The samples were tested for gradation and plasticity with the results detailed in the bid information. The data sent by DOT to all prospective bidders not only showed the test results, but also DOT’s evaluations as to the pit averages, haul distances, areas of the pits that should be excavated and the quantities of material that would need to be processed or crushed. The prices and restoration requirements from each pit were also shown. Several financial incentives were provided for using the material from these pits, including no payment required for rejected material.

The pit data sent by DOT consisted of 12 pages on Lyman and 24 pages on Sully and contained two printed disclaimers:

[On the top]:
THIS IS NOT A SPECIAL PROVISION FOR INFORMATION ONLY
[On the bottom]:
The information covering the pit for the project are given to you for informational purposes only. The Department of Transportation does not guarantee the quantity or the quality of the material listed in the above information. Interested Contractors should investigate the area before considering it for bidding purposes. (Emphasis in original).

Due to time constraints, Mooney’s relied upon the pit data and did not perform its own testing on the pits. Neither pit contained the types and quantities claimed by the DOT pit data. Mooney’s was forced to process approximately double the amount of material that would have been required had the pit data been accurate.

Mooney’s states that both Sully County Engineer Norman Konechne and Lyman [45]*45County Engineer Larry Engebrect were present at the respective pits throughout the excavation process. The engineers were aware of Mooney’s difficulties in obtaining conforming aggregate and both made recommendations as to processing methods. DOT contends that industry practice requires the splitting of materials and blending them to maintain better control over gradation and plasticity. Therefore, DOT claims that it was only Mooney’s that perceived the extra processing as unforeseen or unanticipated.

Mooney’s did not provide DOT with written notice of a claim for additional compensation or otherwise follow the claims procedure outlined in the contract. Mooney’s sued DOT for the additional compensation arising out of the three projects. The trial court granted DOT’s motion for partial summary judgment as to Mooney’s claims stating that, as a matter of law: (1) DOT had not breached any implied warranty of accuracy as to the bid information; (2) Mooney’s had not complied with the notice provisions of the contract; and (3) Mooney’s was not entitled to recover on the basis of quantum meruit due to the existence of an express contract between the parties.

1. IMPLIED WARRANTY AS TO ACCURACY

The standard of review of a motion for summary judgment is “whether the moving party demonstrated the absence of any genuine issue of material fact and showed entitlement to judgment on the merits as a matter of law.” Gasper v. Freidel, 450 N.W.2d 226, 228 (S.D.1990) (iquoting Pickering v. Pickering, 434 N.W.2d 758, 760-61 (S.D.1989)). Based on the evidence presented to the trial court, we must decide whether an implied warranty of accuracy was created by inclusion of the pit test data in the bid information, and if so, whether such an implied warranty was negated by the printed disclaimers.

At the outset, it is important to note that G.H. Lindekugel & Sons, Inc. v. South Dakota State Highway Commission, 87 S.D. 32, 202 N.W.2d 125 (1972), which forbid recovery of damages in excess of the contract price where there had been no specific appropriation, was overruled by Candee Const. v. Dept. of Transportation, 447 N.W.2d 339, 345 (S.D.1989), cert. denied, 494 U.S. 1067, 110 S.Ct. 1785, 108 L.Ed.2d 786 (1990). Therefore, there is no precedent barring a claim for compensation in excess of the contract. However, whether an implied warranty of accuracy exists depends on the facts of the case.

The validity of an implied warranty of accuracy was recognized by the United States Supreme Court in United States v. Spearin, 248 U.S. 132, 136, 39 S.Ct. 59, 61, 63 L.Ed. 166 (1918). In Spearin, the contractor was required to build, in accordance with plans and specifications furnished by the Government, a by-pass sewer system as part of the construction of a dry-dock. The sewer proved to be inadequate, flooded the worksite and caused the contested damages. The Court stated:

Where one agrees to do, for a fixed sum, a thing possible to be performed, he will not be excused or become entitled to additional compensation, because unforeseen difficulties are encountered. Thus one who undertakes to erect a structure upon a particular site, assumes ordinarily the risk of subsidence of the soil. But if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications. This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and to inform themselves of the requirements of the work.

Id. (Citations omitted). The Court then stated that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Larson
2010 SD 20 (South Dakota Supreme Court, 2010)
Bryan v. City of Cotter
2009 Ark. 457 (Supreme Court of Arkansas, 2009)
Northern Valley Communications, LLC v. Qwest Communications Corp.
659 F. Supp. 2d 1062 (D. South Dakota, 2009)
Burch v. Bricker
2006 SD 101 (South Dakota Supreme Court, 2006)
Missouri Consolidated Health Care Plan v. Community Health Plan
81 S.W.3d 34 (Missouri Court of Appeals, 2002)
Morris
1999 SD 95 (South Dakota Supreme Court, 1999)
Bruske v. Hille
1997 SD 108 (South Dakota Supreme Court, 1997)
Sundt Corp. v. SD Dept of Transportation
1997 SD 91 (South Dakota Supreme Court, 1997)
Elrod v. General Casualty Co. of Wisconsin
1997 SD 90 (South Dakota Supreme Court, 1997)
Grand State Property, Inc. v. Woods, Fuller, Shultz, & Smith, P.C.
1996 SD 139 (South Dakota Supreme Court, 1996)
Parkhurst v. Burkel
1996 SD 19 (South Dakota Supreme Court, 1996)
Henry v. Henry
534 N.W.2d 844 (South Dakota Supreme Court, 1995)
Farmers & Merchants State Bank v. Teveldal
524 N.W.2d 874 (South Dakota Supreme Court, 1994)
Mooney's, Inc. v. South Dakota Department of Transportation
482 N.W.2d 43 (South Dakota Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
482 N.W.2d 43, 1992 S.D. LEXIS 21, 1992 WL 41373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mooneys-inc-v-south-dakota-department-of-transportation-sd-1992.