Clemens Construction Co. v. United States

160 Ct. Cl. 675, 1963 U.S. Ct. Cl. LEXIS 46, 1963 WL 8585
CourtUnited States Court of Claims
DecidedFebruary 6, 1963
DocketNo. 421-56
StatusPublished
Cited by2 cases

This text of 160 Ct. Cl. 675 (Clemens Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clemens Construction Co. v. United States, 160 Ct. Cl. 675, 1963 U.S. Ct. Cl. LEXIS 46, 1963 WL 8585 (cc 1963).

Opinion

Per Curiam :

On April 7, 1961, 153 Ct. Cl. 170, this court entered judgment for plaintiff and remanded the case to Trial Commissioner Mastín G. White under Rule 38(c) to determine the amount plaintiff is entitled to recover. The commissioner has done so in- a supplemental report filed March 7, 1962. Briefs were filed by both parties. Exceptions to the commissioner’s findings were taken by both parties and the [676]*676case was submitted to the court on oral argument by counsel. Since the court is in agreement with the supplemental findings and recommendations of the trial commissioner, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is therefore entitled to recover the sum of three hundred fourteen thousand five hundred two dollars and seventy-four cents ($314,502.74) and judgment will be entered accordingly.

SUPPLEMENTAL OPINION OE COMMISSIONER

Introduction

In connection with the construction of a 26.2-mile levee, known as Levee L-40, in the Everglades region of Florida under a contract with the Corps of Engineers, the plaintiff was paid at the specified unit prices for 1,039,599 cubic yards of “Excavation, unclassified” (Item No. 1), and for 3,230,436 cubic yards of “Embankment” (Item No. 2.). The plaintiff contended in prior proceedings before- this court that it placed additional “Embankment” for which it should have been paid by the Corps of Engineers. The court, in a decision dated April 7, 1961, 153 Ct. Cl. 170, upheld the plaintiff’s contention, and remanded the case to the trial commissioner under Rule 38(c) for a determination regarding the amount of the additional “Embankment” placed by the plaintiff for which it should be compensated.

It was necessary to hold a further 3-day trial as part of' the proceedings under Rule 38(c).

The contract in question covered the construction of 26.2 miles of continuous levee, running generally from north to south. For the purpose of computing the compensation due the plaintiff, the contract divided the levee into two sections, a northern section slightly more than 2 miles in length and a southern section slightly more than 24 miles in length. Only the southern section is involved in the controversy between the plaintiff and the Government.

Both the plaintiff and the Corps of Engineers, at the time when they entered into the contract that is involved in the present litigation, were experienced in levee-construction work within the Everglades region of Florida, and they were generally familiar with the conditions that would be en[677]*677countered during the course of constructing Levee L-40. Both were aware tbat tbe levee was to traverse a low, flat, wet area; that the surface of the area was characterized by a varied assortment of vegetation, including sawgrass, brush, small trees, and cypress stumps; that beneath the surface vegetation there was a layer of peat; that the layer of peat was more than 4 feet thick at some places; that peat is a compressible and rather unstable soil; and that, beneath the peat, there was a mixture of sand, shell, and conglomerate rock. The parties contracted with each other in the light of this knowledge that was common to both of them.

Material Left on the Berm

Levee L-40 was constructed with material excavated from a continuous borrow pit running along the west side of, and parallel to, the levee. The borrow pit was separated from the levee by a 40-foot strip of land, known as the berm.

Extensive use was made of the berm by the plaintiff, by the plaintiff’s suppliers, and by the Corps of Engineers during the construction of Levee L-40. In the first place, the plaintiff’s three large draglines — which, working in tandem, transferred material from the borrow pit to the levee— rested wholly or partially on the berm while excavating material from the borrow pit and adding it to the levee embankment ; and then they moved along the berm in changing locations. Also, the berm was used as a roadway by tractors, bulldozers, trucks, jeeps, and other vehicles.

In order to prepare the berm for use by equipment of the sort referred to in the preceding paragraph, the berm was first cleared of brush, small trees, stumps, etc. Then, because the peat surface of the berm was compressible and rather unstable, the plaintiff excavated sand, shell, and rock from the borrow pit and spread such material over the peat surface of the berm in order to provide a sufficiently stable surface for the passage of the equipment previously mentioned. Thereafter, at a comparatively late stage in the process of constructing the levee, some — but not all — of the sand, shell, and rock which had been spread over the peat surface of the berm was recovered by the plaintiff and used in completing the levee embankment to the required specifi[678]*678cations. One of the problems before the court in the proceedings under Eule 38(c) is to determine how much of the sand, shell, and rock from the borrow pit was ultimately-left on the southern section of the berm at the conclusion of the construction process and was never used as part of the levee embankment.

Several persons who were present at the time when Levee L-40 was being constructed and who observed the plaintiff’s operations in spreading sand, shell, and rock from the borrow pit over the peat surface of the berm, and later in recovering some of this material for inclusion in the levee embankment, made estimates at the trial with respect to the quantity of this material that was finally left on the southern section of the berm. There was a wide variance in these estimates, ranging from a low of about 10,000 cubic yards to a high of approximately 375,000 cubic yards.

In view of the wide variance in the estimates based on personal observations, as outlined in the preceding paragraph, I believe that the most reliable estimate regarding the amount of the material from the borrow pit that was finally left on the berm is to be derived from the results of an investigation which the Corps of Engineers made in preparation for the trial sessions under Rule 38 (c). During the course of that investigation, which was made in the summer of 1961, trenches were cut across the 40-foot width of the berm at 1-mile intervals. Twenty-five such trenches were cut in the 24-mile length of the southern section of the berm. The sites for the trenches were selected in relation to the locations of control monuments that had been established before the contract for the construction of Levee L-40 was entered into between the plaintiff and the Corps of Engineers. Within each trench, measurements were made to determine the average thickness of the material overlaying the original peat surface of the berm along the 40-foot length of the particular trench; and the 25 averages thus calculated were, in turn, used as a basis for computing an overall average. The last figure mentioned was then used as representing the average thickness of the material overlaying the original peat surface of the berm throughout the entire 24-mile length of the southern section of the berm, and, on that basis, it appeared that such material totaled 274,787 cubic yards in the summer of 1961.

[679]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Branning v. United States
6 Cl. Ct. 618 (Court of Claims, 1984)
Phillips Construction Co., Inc. v. The United States
394 F.2d 834 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
160 Ct. Cl. 675, 1963 U.S. Ct. Cl. LEXIS 46, 1963 WL 8585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clemens-construction-co-v-united-states-cc-1963.