Absher Construction Co. v. Kent School District No. 415

890 P.2d 1071, 77 Wash. App. 137
Court of Appeals of Washington·Decided January 23, 1995·No. 33489-1-I·Published·Cited by 45 cases

Opinion

Webster, J.

Absher Construction Co., Chapman Mechanical, Inc., and Emerald Aire, Inc., appeal a summary judgment and the award of attorneys’ fees in a breach of contract case. They claim genuine issues of fact were in dispute. We affirm.

Facts

Kent School District 415 awarded Absher a contract to build Daniel Elementary School, August 8, 1991. Absher subcontracted with Chapman for the mechanical work, and Chapman subcontracted with Emerald for the air conditioning system (HVAC). Lee Architectural Group and BJSS Group (Lee) contracted with the District to perform the architecture work and subcontracted with Hargis Engineers for the HVAC/mechanical design.

The Absher contract contained alternative dispute resolution procedures. During contract negotiation, Absher acknowledged that these provisions were mandatory. Absher was required to give the District prompt and detailed written notice of any claims 14 days after events giving rise to claims, enter into structured dispute resolution procedures, and mediate any remaining disputes before any lawsuit could be commenced. This requirement could not be waived except by an *140 explicit written waiver signed by the owner. Failure to provide complete written notification was an absolute waiver of any claims arising from or caused by delay. 1 Acceptance of final payment would also constitute a waiver of all unidentified claims. 2

Construction began in August 1991. Emerald completed installation of the HVAC system in September 1992. A number of claims arose during construction. Absher submitted 102 claims and the District paid 70 of those claims. Six claims were credits back to the District, and the remaining 26 claims were canceled. Three of the submitted claims involved Emerald’s work, and were paid through Absher. Absher invoked the dispute resolution procedure on other claims seven times, and all resulted in settlements and agreed contract change orders.

The District approved "substantial completion” on the building and site improvements during August/September 1992 and final acceptance on March 10, 1993. The District forwarded final payment to Absher on March 10, 1993. As a condition of "final acceptance”, Absher certified on February 19, 1993, that it had paid in full all known claims for which the District might in any way be held responsible. Two days prior to making its affidavit, Absher received a February 12, 1993, letter from Emerald to Chapman indicating that Emerald anticipated making a claim/request for equitable adjustment for $150,000 to $200,000 within the next week, and that it anticipated filing a claim against the public works bond and retainage. 3

*141 The District received from Absher a copy of the Emerald letter February 23, 1993. In its transmittal, Absher stated that it "was not notified of this claim prior to this letter”. Absher did not modify its affidavit that all known claims had been paid. On April 7,1993, Emerald filed a lien against the statutory retainage and payment bond.

Absher filed suit May 10,1993, 2 months after final acceptance. Two days later the District received Emerald’s request for an "equitable adjustment”, seeking more than $200,000 on its original contract price of $286,978. Emerald claimed the District breached its contract with Absher by providing overwhelmingly defective plans.

I

Absher claims there were material issues of fact in dispute regarding notice, agency, waiver, prejudice, futility, the amount of the claim, and responsibility for nonoccurrence of dispute resolution. The Washington Supreme Court recently reiterated the rules governing review of summary judgment.

A motion for summary judgment may be granted only if, "after viewing all the pleadings, affidavits, depositions, admissions and all reasonable inferences drawn therefrom in favor of the nonmoving party”, the trial court finds, "(1) there is no genuine issue as to any material fact, (2) that all reasonable persons could reach only one conclusion, and (3) that the moving party is entitled to judgment as a matter of law”.

Higgins v. Stafford, 123 Wn.2d 160, 168-69, 866 P.2d 31 (1994).

The District contends that summary judgment was proper because even taking all of the facts as true, Absher explicitly waived the claims asserted pursuant to numerous provisions of the contract. Voorde Poorte v. Evans, 66 Wn. App. 358, 362, 832 P.2d 105 (1992). Interpretation of an unambiguous contract is a question of law. Thus, "[i]f a contract is unambiguous, summary judgment is proper even if the parties dispute the legal effect of a certain provision.” Voorde Poorte, 66 Wn. App. at 362. Mere unsupported conclusory allegations and argumentative assertions will not defeat summary *142 judgment. Vacova Co. v. Farrell, 62 Wn. App. 386, 395, 814 P.2d 255 (1991). Although the issues framed by Absher are denoted factual disputes, they are actually conclusions of law as to the legal effect of the undisputed facts. We review the facts to determine whether the District was entitled to summary judgment as a matter of law.

Notice

Washington law requires contractors to follow contractual notice procedures, unless those procedures are waived. Sime Constr. Co. v. WPPSS, 28 Wn. App. 10, 15, 621 P.2d 1299 (1980), review denied, 95 Wn.2d 1012 (1981); Lindbrook Constr., Inc. v. Mukilteo Sch. Dist. 6, 76 Wn.2d 539, 540-43, 458 P.2d 1 (1969). Absher admits that it was not notified and did not provide written notice of Emerald’s claim until months after Emerald had completed all of its work. Thus, Absher did not submit Emerald’s claims in writing within 14 days of the events giving rise to the claim, as required by the contract. 4

Absher contends that attendance of District and subcon-sultant engineers at project meetings where HVAC design problems were discussed constituted notice. Alternatively, it asserts that addressing problems and comments to, and receiving guidance from subconsultant Regan Corwin, of Hargis Engineers, constituted a waiver of the notice provision by the District. 5

*143 Under the contract, claims must include the amount of the claim and the length of delay sought. Careful review of the record reveals no claim was made. Emerald uses a "Field Request and Information” form for its design questions.

Free access — add to your briefcase to read the full text and ask questions with AI

Absher Construction Co. v. Kent School District No. 415, 890 P.2d 1071, 77 Wash. App. 137 (Wash. Ct. App. 1995).

890 P.2d 1071 (Absher Construction Co. v. Kent School District No. 415) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Skanska Usa Building Inc., V. 1200 Howell Street, Llc
Court of Appeals of Washington, 2025
A.B., J.L., V. Kiwanis International
Court of Appeals of Washington, 2024
Pease & Sons, Inc. v. Turner Construction Company
Court of Appeals of Washington, 2024
C.A. Carey Corporation, V. City of Snoqualmie
Court of Appeals of Washington, 2024
Graham Contracting, Ltd., V. City Of Federal Way
Court of Appeals of Washington, 2023
Tadych v. Noble Ridge Constr., Inc.
Washington Supreme Court, 2022
Gary G. Gregg v. JRCC Inc.
Court of Appeals of Washington, 2022
EPIC, a non-profit corporation v. CliftonLarsonAllen LLP
199 Wash. App. 257 (Court of Appeals of Washington, 2017)
Shepler Construction, Inc. v. Leonard
306 P.3d 988 (Court of Appeals of Washington, 2013)
Shepler Construction v. Gary And Susan Leonard
Court of Appeals of Washington, 2013
Mattingly v. Palmer Ridge Homes, LLC
157 Wash. App. 376 (Court of Appeals of Washington, 2010)
American Safety Casualty Insurance v. City of Olympia
162 Wash. 2d 762 (Washington Supreme Court, 2007)