Graham Contracting, Ltd., V. City Of Federal Way

CourtCourt of Appeals of Washington
DecidedMay 30, 2023
Docket83494-1
StatusUnpublished

This text of Graham Contracting, Ltd., V. City Of Federal Way (Graham Contracting, Ltd., V. City Of Federal Way) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graham Contracting, Ltd., V. City Of Federal Way, (Wash. Ct. App. 2023).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

GRAHAM CONTRACTING, LTD., a No. 83494-1-I Washington corporation, DIVISION ONE Appellant,

v. UNPUBLISHED OPINION CITY OF FEDERAL WAY, a Washington municipal corporation,

Respondent.

BOWMAN, J. — Graham Contracting Ltd. appeals the trial court’s order

dismissing its claims for additional compensation relating to a “Public Works

Contract” with the city of Federal Way (City). Because Graham did not follow the

disputes and claims procedures in the contract, Graham waived its ability to bring

a claim for additional compensation. We affirm and remand for further

proceedings.

FACTS

In June 2016, the City requested bids for “Phase V” of the Pacific Highway

South improvement project. The project involved placing utilities underground,

improving drainage, installing and modifying traffic signals and lighting,

landscaping, laying new pavement, and building curbs, gutters, sidewalks,

medians, and retaining walls. The City assigned its “Street Systems Project No. 83494-1-I/2

Engineer” John Mulkey to oversee the bidding process. Graham submitted the

lowest bid for the project at $16,701,329.60.

On August 23, 2016, the City executed a “Construction Management

Services” contract with KPG PS.1 The services KPG specified in the contract

included design support, project management, documentation control, inspection,

materials testing, public involvement, and “contract administration during the

construction of the [Phase V] project.” KPG named Ken Gunther as the “Project

Engineer,” or “Resident Engineer,” of the Phase V project.

On August 25, 2016, the City awarded Graham the project and the parties

executed a Public Works Contract. The contract allocated Graham “350 working

days” to complete the project. It defined the scope of the work and incorporated

into the contract the 2016 edition of Washington State Department of

Transportation’s STANDARD SPECIFICATIONS FOR ROAD, BRIDGE, AND MUNICIPAL

CONSTRUCTION (Standard Specifications).

Graham began work on September 12, 2016.2 On November 3, 2016,

Graham sent Mulkey and Gunther a “Notice of Delay,” explaining that the joint

utility trench (JUT) unexpectedly needed to be complete before workers could

remove or relocate the existing utility lines from overhead poles. Graham

believed the issue would “significantly impact the project schedule,” but it would

have to later advise the City and KPG “regarding the actual extension of time and

impact costs when we are better able to assess the effect of the occurrence.”

1 Now KPG Psomas. 2 September 12, 2016 plus 350 working days results in an end date around February 9, 2018.

2 No. 83494-1-I/3

On November 8, 2016, Gunther e-mailed Graham a letter in response. He

explained that under the contract, “power and communication distribution lines

will remain on these poles until the entire underground distribution system is in

place,” and that

[t]he Contractor [(Graham)] is responsible for coordinating and planning adjacent work with the appropriate utility to avoid impacts and delays to the project schedule. . . . [T]herefore; the City of Federal Way is denying Graham Contracting’s [Notice of Delay] dated 11/03/16.

On December 2, 2016, Graham replied to Gunther and Mulkey. Graham

disagreed with KPG’s interpretation of the contract, explained its position in more

detail, and requested a meeting to discuss the issue. Two weeks later, Gunther

responded that the City “maintains its position as per [his letter] dated November

8, 2016.” Meanwhile, Graham kept working on the project.

On December 22, 2016, Graham met with the City to discuss the delay

and added expense related to the JUT work. On January 20, 2017, Marwan

Salloum, the director of the Public Works Department for the City, sent Graham a

letter stating that “the City’s position remains unchanged.” Salloum explained

that Graham “is not entitled to any additional working days to complete the

Project,” and as much as Graham is claiming a “changed condition” under the

contract, it “failed to properly protest the City’s determination in accordance with”

the Standard Specifications, “waiv[ing] any claims related thereto by failing to

follow the protest and claim requirements of the Contract.”

On February 3, 2017, Graham sent Mulkey a “Supplemental to Notice of

Protest re: Joint Utility Trench (JUT) Construction Delays Pursuant to Standard

3 No. 83494-1-I/4

Specification Section 1-04.5,”3 arguing that the City “incorrectly determined” that

Graham has no right to any additional working days to complete the project and

that it waived any claims related to changed conditions under the contract. It

notified the City that “Graham protests both determinations” and that it estimated

the extra work would delay the project around 110 days, amounting to

$973,101.80 in additional costs.

Over the next several months, Graham continued to send the City notices

of protest related to the JUT delay, requesting more time and money. On July 7,

2017, Gunther sent Graham a letter, saying the City “understand[s] that Graham

is protesting the Engineer’s denial of Graham’s request to extend the Contract,”

but “[i]f Graham was unhappy with the City’s determinations on this issue, it was

required to protest those decisions and file a Claim in strict accordance with the

Contract notice and claim procedures.” The City explained that Graham should

follow the “dispute and claim procedures” under the contract for those issues and

claims “that have not already been waived or previously determined by the City

or its Engineer.”

A week later, Graham responded. It claimed that it need not follow the

disputes and claims procedures under the contract to contest Gunther’s

November 8, 2016 decision because the procedures apply to only determinations

made by the “Project Engineer.”4 And, according to Graham, “the City identified

3 The letter appears to be a supplement to a notice of protest Graham submitted on January 27, 2017 for an unrelated issue. 4 The Standard Specifications define “Engineer” as the “Contracting Agency’s representative who directly supervises the engineering and administration of a construction Contract.” The contract clarifies that “Project Engineer” is the “[s]ame as Engineer.”

4 No. 83494-1-I/5

John Mulkey in the contract documents as the Project Engineer for this Project,”

not Gunther. Graham told the City it “intends to file a Claim against the City of

Federal Way for recovery of all current and future losses incurred by Graham

resulting from the impacts and issues noted in this and [earlier] letters.”

On December 22, 2017, Graham filed a claim for damages with the City,

seeking $10,777,440.22 for the “cumulative impact” of “extensive and ongoing

changes required on the Project, including but not limited to differing site

conditions, design conflicts/omissions, untimely third-party utility performance,

and undisclosed utility conflicts.” The City denied the claim. It noted the claim

amounts to “a conglomerate of various issues” that it already rejected. It

determined that Graham did not follow the proper disputes and claims

procedures or timely provide the minimum information required to accompany a

claim under the contract. Still, the City reviewed the “limited material” Graham

provided and found the claim “is without merit.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kruse v. Hemp
853 P.2d 1373 (Washington Supreme Court, 1993)
JDFJ CORP. v. International Raceway, Inc.
970 P.2d 343 (Court of Appeals of Washington, 1999)
REALM, INC. v. City of Olympia
277 P.3d 679 (Court of Appeals of Washington, 2012)
Elcon Construction, Inc. v. Eastern Washington University
273 P.3d 965 (Washington Supreme Court, 2012)
AMER. SAF. CAS. INS. CO. v. City of Olympia
174 P.3d 54 (Washington Supreme Court, 2007)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
Owen v. Burlington Northern and Santa Fe RR Co.
108 P.3d 1220 (Washington Supreme Court, 2005)
Renfro v. Kaur
235 P.3d 800 (Court of Appeals of Washington, 2010)
Rsd Aap Llc v. Alyeska Ocean Llc& Jeff & Jane Doe Hendrick's
358 P.3d 483 (Court of Appeals of Washington, 2015)
Bryan Kelley And Dorre Don Llc v. Beverly L. Tonda
393 P.3d 824 (Court of Appeals of Washington, 2017)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Owen v. Burlington Northern Santa Fe Railroad
153 Wash. 2d 780 (Washington Supreme Court, 2005)
American Safety Casualty Insurance v. City of Olympia
162 Wash. 2d 762 (Washington Supreme Court, 2007)
Renfro v. Kaur
235 P.3d 800 (Court of Appeals of Washington, 2010)
Realm, Inc. v. City of Olympia
277 P.3d 679 (Court of Appeals of Washington, 2012)
GMAC v. Everett Chevrolet, Inc.
179 Wash. App. 126 (Court of Appeals of Washington, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Graham Contracting, Ltd., V. City Of Federal Way, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graham-contracting-ltd-v-city-of-federal-way-washctapp-2023.