C.A. Carey Corporation, V. City of Snoqualmie

CourtCourt of Appeals of Washington
DecidedFebruary 20, 2024
Docket84602-7
StatusUnpublished

This text of C.A. Carey Corporation, V. City of Snoqualmie (C.A. Carey Corporation, V. City of Snoqualmie) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.A. Carey Corporation, V. City of Snoqualmie, (Wash. Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

C.A. CAREY CORPORATION, a Washington corporation, No. 84602-7-I

Appellant, DIVISION ONE

v. UNPUBLISHED OPINION

CITY OF SNOQUALMIE, a Washington municipal corporation,

Respondent.

HAZELRIGG, A.C.J. — C.A. Carey Corporation appeals from the trial court’s

grant of the City of Snoqualmie’s motion for summary judgment dismissal of its

claims against the municipality based on a public works contract. Because there

is no issue of material fact as to the contractor’s lack of compliance with the

mandatory notice, protest, and claim provisions of standard specifications

expressly incorporated into the contract, its causes of action are barred as a matter

of law. We affirm.

FACTS

In February 2014, the City of Snoqualmie advertised construction bids for

the public works contract of the “Town Center Infrastructure Improvements Phase

2A Project” (project). The project involved improvements to downtown

Snoqualmie, including installation of a new water main, storm drainage system, No. 84602-7-I/2

undergrounding of power, cable, and phone lines, and roadway paving. Following

the public bidding process, the contract was awarded to C.A. Carey Corporation

(Carey) on April 28, 2014 as the lowest responsive, responsible bidder. On May

12, 2014, the City and Carey entered into a public works agreement (contract) for

the project. Pursuant to the contract, Carey was obligated to “achieve substantial

completion of all [w]ork required by the [c]ontract [d]ocuments[1] within 180 working

days” for the principal sum of $4,282,653.42.

The contract incorporated the 2012 Washington State Department of

Transportation (WSDOT) publication “Standard Specifications for Road, Bridge,

and Municipal Construction” (standard specifications). The standard specifications

are uniform requirements for public works agreements that provided the general

terms of the contract between the City as the contracting agency and the

contractor, Carey. Among the requirements are mandatory notice and claim

procedures that govern the specific process that must be followed when a

contractor seeks additional time or payment on a project.

On May 12, 2017, Carey filed a complaint against the City for breach of

contract, breach of the implied covenant of good faith and fair dealing, and breach

of implied warranty of design. In its breach of contract claim, Carey alleged that

the City failed to acknowledge known defects in the project design, failed to pay

for the increased costs of construction, and failed to award additional contract time

Carey said became necessary due to numerous design changes. On June 26, the

1 The contract provided that “Contract Documents” included, among other things, contract

plans and standard specifications, as well as amendments to the standard specifications.

-2- No. 84602-7-I/3

City filed its answer to the complaint and a counterclaim that asserted Carey had

breached the contract by “failing to timely and/or properly perform its work.”

On September 27, 2019, both parties moved for summary judgment. A

hearing on the motions took place on October 25 and the trial court heard argument

from counsel for the City and Carey. Carey conceded that all three causes of

action in its complaint arose from the contract and thus would rise and fall together.

On November 4, the judge entered a written order that granted the City’s motion

for summary judgment and dismissed each of Carey’s claims. The trial court

concluded that Carey had waived the right to pursue its claims because it failed to

comply with the standard specifications, particularly the mandatory notice, protest,

and claim provisions in sections 1-04.5 and 1-09.11 of the standard specifications.

Because the requirements of those provisions are “conditions precedent to

litigation,” the trial court concluded that dismissal of Carey’s complaint was

required.

On November 13, Carey moved for reconsideration pursuant to CR 59(7)

and (9) and requested that the trial court vacate its summary judgment order. The

following day, Carey submitted an amended motion for reconsideration. In support

of its motion, Carey included additional evidence in the form of numerous exhibits

attached to a declaration. On December 3, the judge denied reconsideration. In

the written order, the court explained that it did not consider the supplemental

exhibits submitted with the motion because Carey offered “no grounds to support

consideration of additional evidence” as required by CR 59(a)(4).

Carey timely appealed.

-3- No. 84602-7-I/4

ANALYSIS

I. Summary Judgment Dismissal

Carey assigns error to the trial court’s order granting the City’s motion for

summary judgment dismissal. According to Carey, the court erred by applying a

strict compliance standard to determine whether Carey adhered to the standard

specifications, improperly interpreting the claim limitation and final contract

voucher certification provisions, and “enforcing strict contractual notice and claim

requirements against Carey” when “the City was the first party to breach.”

“On appeal of summary judgment, the standard of review is de novo, and

the appellate court performs the same inquiry as the trial court.” Lybbert v. Grant

County, 141 Wn.2d 29, 34, 1 P.3d 1124 (2000). “The court must consider all facts

submitted and all reasonable inferences from the facts in the light most favorable

to the nonmoving party.” Weyerhaeuser Co. v. Aetna Cas. & Sur. Co., 123 Wn.2d

891, 897, 874 P.2d 142 (1994). “A court may grant summary judgment if the

pleadings, affidavits, and depositions establish that there is no genuine issue as to

any material fact and the moving party is entitled to judgment as a matter of law.”

Lybbert, 141 Wn.2d at 34; see also CR 56(c). “A genuine issue of material fact

exists where reasonable minds could differ on the facts controlling the outcome of

the litigation.” Ranger Ins. Co. v. Pierce County, 164 Wn.2d 545, 552, 192 P.3d

886 (2008). “However, bare assertions that a genuine material issue exists will not

defeat a summary judgment motion.” Trimble v. Wash. State Univ., 140 Wn.2d 88,

93, 993 P.2d 259 (2000).

-4- No. 84602-7-I/5

“The ‘touchstone of contract interpretation is the parties’ intent.’” GMAC v.

Everett Chevrolet, Inc., 179 Wn. App. 126, 134, 317 P.3d 1074 (2014) (internal

quotation marks omitted) (quoting Realm, Inc. v. City of Olympia, 168 Wn. App. 1,

4-5, 277 P.3d 679 (2012)). “Washington courts follow the objective manifestation

theory of contracts, imputing an intention corresponding to the reasonable

meaning of the words used.” Realm, 168 Wn. App. at 5. “Contract interpretation

is a question of law when, as here, the interpretation does not depend on the use

of extrinsic evidence.” Id. When the contract is unambiguous, “summary judgment

is proper even if the parties dispute the legal effect of a certain provision.” Voorde

Poorte v. Evans, 66 Wn. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trimble v. Washington State University
993 P.2d 259 (Washington Supreme Court, 2000)
Voorde Poorte v. Evans
832 P.2d 105 (Court of Appeals of Washington, 1992)
Wagner Development, Inc. v. Fidelity & Deposit Co.
977 P.2d 639 (Court of Appeals of Washington, 1999)
Weyerhaeuser Co. v. Aetna Casualty & Surety Co.
874 P.2d 142 (Washington Supreme Court, 1994)
REALM, INC. v. City of Olympia
277 P.3d 679 (Court of Appeals of Washington, 2012)
Cook v. Brateng
262 P.3d 1228 (Court of Appeals of Washington, 2010)
AMER. SAF. CAS. INS. CO. v. City of Olympia
174 P.3d 54 (Washington Supreme Court, 2007)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Hearst Communications v. Seattle Times Co.
115 P.3d 262 (Washington Supreme Court, 2005)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
Ranger Ins. Co. v. Pierce County
192 P.3d 886 (Washington Supreme Court, 2008)
NOVA Contracting, Inc. v. City of Olympia
426 P.3d 685 (Washington Supreme Court, 2018)
Lybbert v. Grant County
1 P.3d 1124 (Washington Supreme Court, 2000)
Trimble v. Washington State University
140 Wash. 2d 88 (Washington Supreme Court, 2000)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Hearst Communications, Inc. v. Seattle Times Co.
154 Wash. 2d 493 (Washington Supreme Court, 2005)
American Safety Casualty Insurance v. City of Olympia
162 Wash. 2d 762 (Washington Supreme Court, 2007)
Ranger Insurance v. Pierce County
164 Wash. 2d 545 (Washington Supreme Court, 2008)
Satomi Owners Ass'n v. Satomi, LLC
225 P.3d 213 (Washington Supreme Court, 2009)
Weber Construction, Inc. v. Spokane County
98 P.3d 60 (Court of Appeals of Washington, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
C.A. Carey Corporation, V. City of Snoqualmie, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ca-carey-corporation-v-city-of-snoqualmie-washctapp-2024.