Blount Brothers Construction Company v. The United States

348 F.2d 471, 172 Ct. Cl. 1
United States Court of Claims·Decided September 28, 1965·No. 249-61·Published·Cited by 18 cases

Opinion

COLLINS, Judge.

This action arises out of a contract entered into by plaintiff and the Department of the Navy’s Bureau of Yards and Docks. The contract provided for the construction by plaintiff of a rotating arm and maneuvering basin at the David W. Taylor Model Basin, Carderock, Mainland. The claims set forth in plaintiff’s petition are made on behalf of certain of plaintiff’s subcontractors.

Defendant has moved for summary judgment. The “Severin doctrine,” upon which defendant’s motion is based, derives its name from Severin v. United States, 99 Ct.Cl. 435 (1943), cert. denied, 322 U.S. 733, 64 S.Ct. 1045, 88 L.Ed. 1567 (1944). The rule has been explained as follows:

* * * a prime contractor may sue the Government for damages incurred by one of its subcontractors through the fault of the Government * * * only when the prime contractor has reimbursed its subcontractor for the latter’s damages or remains liable for such reimbursement in the future. These are the only ways in which the damages of the subcontractor can become, in turn, the damages of the prime contractor, for which recovery may be had against the Government. [Citations omitted.] * * *

J. L. Simmons Co. v. United States, 158 Ct.Cl. 393, 397, 304 F.2d 886, 888 (1962). Regarding the case at bar, defendant asserts that the pertinent subcontracts relieved plaintiff of any liability *472 with respect to the claims being asserted. 1

Since plaintiff acquiesces in the Government’s attack upon count two of the petition, we need not consider the issues raised by that count. Plaintiff denies, however, that count one comes within the Severin rule. The facts relevant to count one can be summarized as follows: The contract was awarded to plaintiff on May 25, 1956, and plaintiff immediately commenced work. Thereafter, the Navy determined that revision of the design of the project would be necessary. By letter of February 19, 1957, Commander J. M. Page, the Resident Officer in Charge of Construction, directed plaintiff to stop work on the manufacture of certain wave-maker parts which would “be eliminated if the contemplated change order to the wavemakers is consummated.” On April 11, 1957, the hold order was extended to other parts of the wavemakers.

Plaintiff’s written acknowledgment, sent to Commander Page on May 7, 1957, stated in part:

Allis-Chalmers Mfg. Co. through Waiter Truland Corp., our subcontractor for this work, have [sic] agreed to accept a hold order on this equipment at no additional cost to the Government, subject to the condition that this work shall not be reentered at a later date. If at a later date, it is requested that the analog study, or engineering for, or manufacture of the equipment for the wavemaker valve drive system be reinstated, a charge will be made to compensate for increased costs of manufacture between the effective date of this hold order and the date of re-entry.
If this portion of our contract should be cancelled, a charge will be made to cover design costs of this equipment to effective date of hold order.
We have placed a temporary hold on this work, pending your advice as to your acceptance of the conditions noted herein.

On May 10, 1957, Commander Page replied, “It is considered that the condition by which you accept the subject hold order is adequately covered by the change order provisions of the contract.”

Ultimately, the Navy determined not to effect redesign of the project. On February 7, 1958, 12 days short of 1 year after issuance of the initial hold order, the resident officer in charge of construction advised plaintiff that the hold orders were rescinded. Plaintiff was instructed to proceed on the components of the wavemaker system in accord with the original drawings and specifications, and plaintiff did so.

Subsequently, plaintiff requested that the contracting officer issue a change order to compensate plaintiff and its subcontractors for the additional costs which resulted from the cessation of work. On September 10, 1958, the contracting officer denied plaintiff’s claim. Plaintiff then took an appeal to the Armed Services Board of Contract Appeals (hereinafter the “ASBCA” or “Board”). The Board, in a decision dated June 29, 1960, sustained plaintiff’s appeal in part. However, the ASBCA held that certain items, such as additional overhead, were not of the type compensable under the contract; and, to that extent, the claim of plaintiff was dismissed. There followed the present action.

As indicated previously, plaintiff rejects the assertion of defendant that the Severin doctrine applies to count one of the petition. First, it is plaintiff’s position that the exculpatory clause contained in the subcontracts relates solely to delay damages resulting from breaches of the *473 contract. 2 Secondly, according to plaintiff, count one alleges not an action for "breach of contract, but rather a claim which comes within the terms of the contract. It follows, under this view, that, with regard to the subject matter of count one, plaintiff has not been relieved of liability to its subcontractor. Therefore, plaintiff concludes that the Severin rule, which is premised upon the non-liability of the general contractor, does not bar the present action. 3

The initial question to be determined is whether plaintiff’s construction of the exculpatory language is correct. On no prior occasion has this court been faced with the necessity of deciding this issue. 4

The Severin doctrine has been discussed in cases involving claims which arose under the respective contracts. E. g., Garod Radio Corp. v. United States, 158 Ct.Cl. 596, 601, 307 F.2d 945 (1962); J. W. Bateson Co. v. United States, 143 Ct.Cl. 228, 229, 163 F.Supp. 871 (1958). However, in each of the cited cases, the prime contractor was permitted to maintain an action on behalf of a subcontractor, since there was no evidence that the prime contractor had been relieved of liability. Thus, in neither case was the court required to construe exculpatory language. Cf. Blount Bros. Constr. Corp. v. United States, Ct.Cl., 346 F.2d 962 (June 11, 1965). 5

Defendant cites a number of decisions in which a suit for the benefit of a subcontractor was held to be barred because the general contractor had been absolved of liability to the subcontractor. F. H. McGraw & Co. v. United States, 131 Ct.Cl. 501, 509, 130 F.Supp. 394 (1955); Continental Ill. Nat’l Bank & Trust Co. v. United States, 126 Ct.Cl. 631, 640, 115 F.Supp. 892 (1953); Continental Ill. Nat’l Bank & Trust Co. v. United States, 121 Ct.Cl. 203, 245, 101 F.Supp. 755, cert. denied, 343 U.S. 963, 72 S.Ct. 1057, 9 L.Ed. 1361 (1952); Pearson, Dickerson, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Blount Brothers Construction Company v. The United States, 348 F.2d 471, 172 Ct. Cl. 1 (cc 1965).

348 F.2d 471 (Blount Brothers Construction Company v. The United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2020
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
Board of County Commissioners v. CAM Construction Co.
480 A.2d 795 (Court of Appeals of Maryland, 1984)
Warren Bros. v. North Carolina Department of Transportation
307 S.E.2d 836 (Court of Appeals of North Carolina, 1983)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)
B-E-C-K Constructors v. United States
571 F.2d 25 (Court of Claims, 1978)
Ukrainian Nat. Urban Renewal Corp. v. Joseph L. Muscarelle, Inc.
376 A.2d 1299 (New Jersey Superior Court App Division, 1977)
University of Alaska v. Modern Construction, Inc.
522 P.2d 1132 (Alaska Supreme Court, 1974)
Seger v. United States
469 F.2d 292 (Court of Claims, 1972)
Morrison-Knudsen Company, Inc. v. The United States
397 F.2d 826 (Court of Claims, 1968)
Blount Bros. Construction Co. v. United States
180 Ct. Cl. 35 (Court of Claims, 1967)