Biemann & Rowell Co. v. Donohoe Companies

556 S.E.2d 1, 147 N.C. App. 239, 124 A.L.R. 5th 763, 2001 N.C. App. LEXIS 1138
CourtCourt of Appeals of North Carolina
DecidedNovember 20, 2001
DocketCOA00-1177
StatusPublished
Cited by15 cases

This text of 556 S.E.2d 1 (Biemann & Rowell Co. v. Donohoe Companies) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Biemann & Rowell Co. v. Donohoe Companies, 556 S.E.2d 1, 147 N.C. App. 239, 124 A.L.R. 5th 763, 2001 N.C. App. LEXIS 1138 (N.C. Ct. App. 2001).

Opinion

THOMAS, Judge.

This breach of contract case between prime contractors is based on a claim of delay in the construction of the University of North Carolina Neuropsychiatric Hospital on the Chapel Hill campus. Plaintiff, Biemann and Rowell Company, was the heating and ventilating contractor, while defendant, The Donohoe Companies, Inc., D/B/A Donohoe Construction Company, was the general contractor.

In a bench trial, the trial court entered judgment in favor of defendant on all of plaintiffs claims. Plaintiff appeals, advancing the following four arguments: (1) the trial court erred in its determination of the architect’s role in apportioning liability among the prime contractors; (2) it is not necessary to prove that defendant proximately caused injury to plaintiff; (3) the evidence establishes that plaintiff incurred damages for which defendant is liable; and (4) defendant’s actual knowledge of potential claims against it was sufficient notice. For the reasons herein, we affirm the decision of the trial court.

*241 On or about 1 July 1992, plaintiff and defendant entered into separate contracts with the State of North Carolina, through the University of North Carolina at Chapel Hill (owner), to build the multi-million dollar Neuropsychiatric Hospital. The parties operated under a multiple-prime contract pursuant to N.C. Gen. Stat. § 143-128, which requires that separate contracts be awarded for the major branches of work when a public building project’s expected costs exceed $500,000. N.C. Gen. Stat. § 143-128 (1999). Each separate contractor is directly liable to the State of North Carolina and to the other contractors. N.C. Gen. Stat. § 143-128(b) (1999). Accordingly, a prime contractor may be sued by another prime contractor for economic loss resulting from the first prime contractor’s failure to fully perform its duties under the terms of the separate contracts. See Bolton v. T.A. Loving Co., 94 N.C. App. 392, 397, 380 S.E.2d 796, 800, disc. review denied 325 N.C. 545, 385 S.E.2d 496 (1989).

As the general contractor, defendant was assigned the role of project expediter. While the owner hired a schedule coordinator to develop the progress schedule of the contractors, under Article 14(j) of the general conditions of the separate contracts defendant remained responsible for “maintain[ing] the progress schedule, making monthly adjustments, updates, corrections, etc., that are necessary, keeping all Contractors and the [architect] fully informed.”

The original critical path method progress schedule provided for completion of the project within 1004 days. Delays, ultimately totaling 369 days, occurred throughout the project. They were at least partially attributable to poor weather, logistical problems due to the number of contractors working within the limited area of the site, a structural defect which caused the building to settle, and revisions made by the owner to the sixth floor plans during the course of the project. As a result, the contractors were frequently forced to complete work out of the anticipated sequence.

To accelerate completion of the project, it was the understanding of the contractors, architect, and schedule coordinator that defendant would “dry-in” the building by installing a moisture seal at the fifth floor level. Normally, work is restricted until the roof is built because lower levels would otherwise be exposed to moisture accumulation in inclement weather. This temporary building seal was intended to allow work to take place at the lower levels before the roof was installed. None of those involved who testified had previously seen a building seal, however, or knew of an agreement among *242 the parties as to what specifically would be done to create one. Defendant never installed the building seal.

Letters and summaries written by HKS Architects (architect) indicate that defendant was failing to complete work according to the project schedule and to fulfill its duties as project expediter. Neither the architect nor the owner, however, ever assigned any direct liability for delay to defendant. Meeting minutes and observation reports, which list delays of plaintiffs activities, indicate that plaintiff also contributed to overall project delay. Substantial completion of the project occurred on 15 May 1996, and the owner took beneficial occupancy on that date.

Plaintiff maintains that defendant’s failure to install the building seal, as well as defendant’s failure to supervise and properly schedule its subcontractors, caused delays to plaintiff’s work and as a consequence plaintiff suffered economic loss. Plaintiff did not notify defendant of its claims against them until October of 1996. By that time, plaintiff had released 78 of its 80 subcontractors.

Initially, we note that a trial court’s findings of fact in a bench trial have the force of a jury verdict and are conclusive on appeal if there is competent evidence to support them, even though there may be evidence that would support findings to the contrary. State v. Coronel, 145 N.C. App. 237, 250, 550 S.E.2d 561, 510 (2001). However, conclusions of law reached by the trial court are reviewable de novo. Mann Contractors v. Flair with Goldsmith Consultants —II, Inc., 135 N.C. App. 772, 775, 522 S.E.2d 118, 121 (1999).

I.

Plaintiff first assigns as error the trial court’s determination of the architect’s role in apportioning liability for delays among prime contractors. The trial court held that the architect’s failure to allocate liability to defendant for delays in the performance of plaintiff’s work constituted an implicit determination that defendant was not directly responsible. Plaintiff contends that, under the prime contractors’ separate contracts, the architect is not authorized to decide disputes among the prime contractors. Rather, plaintiff argues, it is only the court that is authorized to determine the proper allocation of delay damages among the prime contractors. We disagree.

Multiple prime contractors co-exist in a delicate state of symbiosis, in which the quality of a contractor’s work often depends on the quality of the work of another contractor, and the delay of one con-

*243 tractor results in the delay of other contractors’ work. See Bolton, 94 N.C. App. 392, 402, 380 S.E.2d 796, 803. This Court in Bolton held that, under the contract in that case, the architect determined responsibility for delay among the prime contractors. Id. When an architect is vested with the authority to render judgment on a contractor’s performance, the determination is prima facie correct, and the other parties have the burden of proving fraud or mistake. Id. (quoting Barnes Constr. Co. v. Washington Township, 134 Ind. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sawyer v. Billups
Court of Appeals of North Carolina, 2025
Glover Construction Co. v. Sequoia Servs., LLC
2020 NCBC 49 (North Carolina Business Court, 2020)
Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
Heron Bay Acquisition, LLC v. United Metal Finishing, Inc.
2014 NCBC 15 (North Carolina Business Court, 2014)
Southern Seeding Service, Inc. v. W.C. English, Inc.
735 S.E.2d 829 (Court of Appeals of North Carolina, 2012)
Finish Line v. J.F. Pate & Associates Contractors, Inc.
90 So. 3d 749 (Court of Civil Appeals of Alabama, 2012)
Cleveland Construction, Inc. v. Ellis-Don Construction, Inc.
709 S.E.2d 512 (Court of Appeals of North Carolina, 2011)
ELDER BROACH PROPERTIES, INC. v. McNeel
671 S.E.2d 596 (Court of Appeals of North Carolina, 2008)
Carolina First Bank v. Stark, Inc.
660 S.E.2d 641 (Court of Appeals of North Carolina, 2008)
Weaverville Partners, LLC v. Town of Weaverville Zoning Board of Adjustment
654 S.E.2d 784 (Court of Appeals of North Carolina, 2008)
Lincoln Terrace Associates, Ltd. v. Kelly
635 S.E.2d 434 (Court of Appeals of North Carolina, 2006)
Fix v. City of Eden
622 S.E.2d 647 (Court of Appeals of North Carolina, 2005)
D.W.H. Painting Co. v. D.W. Ward Construction Co.
620 S.E.2d 887 (Court of Appeals of North Carolina, 2005)
County of Moore v. Humane Society of Moore County, Inc.
578 S.E.2d 682 (Court of Appeals of North Carolina, 2003)
RPR & Associates, Inc. v. University of North Carolina-Chapel Hill
570 S.E.2d 510 (Court of Appeals of North Carolina, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
556 S.E.2d 1, 147 N.C. App. 239, 124 A.L.R. 5th 763, 2001 N.C. App. LEXIS 1138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/biemann-rowell-co-v-donohoe-companies-ncctapp-2001.