Mann Contractors, Inc. v. Flair With Goldsmith Consultants-II, Inc.

522 S.E.2d 118, 135 N.C. App. 772, 1999 N.C. App. LEXIS 1244
CourtCourt of Appeals of North Carolina
DecidedDecember 7, 1999
DocketCOA98-1549
StatusPublished
Cited by23 cases

This text of 522 S.E.2d 118 (Mann Contractors, Inc. v. Flair With Goldsmith Consultants-II, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mann Contractors, Inc. v. Flair With Goldsmith Consultants-II, Inc., 522 S.E.2d 118, 135 N.C. App. 772, 1999 N.C. App. LEXIS 1244 (N.C. Ct. App. 1999).

Opinion

MARTIN, Judge.

Plaintiff Mann Contractors, Inc., brought this action to recover monies allegedly owed by reason of an alleged contract with defendant Flair with Goldsmith Consultants-II to construct improvements *773 upon property owned by defendant in Greensboro, N.C. In its amended complaint, plaintiff alleged that it had fully performed its obligations under the contract and that it was owed a balance of at least $80,000 for the work. Defendant answered, denying that it had entered into the contract, denying that plaintiff had performed the work required by the contract, and, alternatively, alleging that it had paid plaintiff in full for all of the work done by plaintiff. By counterclaim, defendant asserted that plaintiff had “wrongfully and negligently failed in the performance of” the renovations to defendant’s property in a number of respects, resulting in damages to defendant exceeding $10,000.

Neither party having requested a jury trial, the case was heard by Judge Lamm sitting without a jury. After hearing the evidence, the trial court found facts as follows:

1. This Court has jurisdiction over the parties and the subject matter of this case, and the case is properly before the Court.
2. Although the written contract introduced by the Plaintiff has not been properly executed, it is the document under which the parties proceeded and to which by their conduct they have agreed to be bound.
3. The contract between the parties provided that the Plaintiff was to perform upfitting of the Defendant’s gym facility in Greensboro, North Carolina for a contract price of $246,850.00, together with the cost, plus ten (10%) per cent [sic], of any change orders and overages.
4. The contract also provided that all unpaid balances would bear interest at the rate of 1 and 1/2% per month, or 18% per annum.
5. The Plaintiff presented evidence and contended that it was entitled to recover from the Defendant damages in the sum of $140,969.02, plus interest. The Defendant presented evidence and contended that the Plaintiff was entitled to recover nothing from the Defendant.
6. The Defendant has failed to pay all sums due the Plaintiff under the contract. However, the Plaintiff has failed to carry its burden of proof as to the amount of claimed change orders and overages except regarding those changes mandated by the governmental officials of Guilford County.
*774 7. The Defendant failed to present evidence in support of its counterclaim against the Plaintiff.

Based upon those findings of fact, the trial court made the following conclusions of law:

1. The Defendant has breached its contract with the Plaintiff.
2. The Plaintiff is entitled to recover from the Defendant damages in the amount of $36,000.00, together with interest thereon at the rate of eighteen (18%) per cent [sic] per annum from July 14, 1998 until the date of this judgment, and at the legal rate thereafter.
3. The Defendant’s counterclaim should be dismissed for lack of evidence in support thereof.

The trial court entered judgment in favor of plaintiff in the amount of $36,000, plus interest at 18% from 14 July 1998 until the date of the judgment, 6 August 1998, and at the legal rate thereafter, and dismissed defendant’s counterclaim. Defendant gave notice of appeal.

On 20 October 1998, upon motion of plaintiff asserting a clerical error in the judgment, Judge Patti amended the judgment to provide that the principal amount of the judgment was to bear interest at 18% from 14 July 1994 until 6 August 1998, and then at the legal rate. Defendant also gave notice of appeal from that order.

On appeal, defendant asserts that the trial court’s second conclusion of law is not supported by its findings of fact. When the parties waive a jury, the trial judge functions in the dual capacity of judge and jury. Reid v. Johnston, 241 N.C. 201, 85 S.E.2d 114 (1954). As such, the judge is required to find the facts on all issues raised by the pleadings, state separately its conclusions of law drawn from the facts found, and enter its judgment. N.C. Gen. Stat. § 1A-1, Rule 52(a)(1); Coggins v. City of Asheville, 278 N.C. 428, 180 S.E.2d 149 (1971). Rule 52(a)(1) does not require the trial court to recite all of the evidentiary facts; it is required only to find the ultimate facts, i.e., those specific material facts which are determinative of the questions involved in the action and from which an appellate court can determine whether the findings are supported by the evidence and, in turn, support the conclusions of law reached by the trial court. Farmers Bank v. Brown Distributors, Inc., 307 N.C. 342, 298 S.E.2d 357 (1983).

*775 The purpose of the requirement that the court make findings of those specific facts which support its ultimate disposition of the case is to allow a reviewing court to determine from the record whether the judgment — and the legal conclusions which underlie it — represent a correct application of the law.

Id. at 347, 298 S.E.2d at 360 (quoting Coble v. Coble, 300 N.C. 708, 268 S.E.2d 185 (1980)). The trial court’s findings have the force of a jury-verdict if they are supported by competent evidence even though there may be evidence which would support findings to the contrary, Williams v. Pilot Life Insurance Company, 288 N.C. 338, 218 S.E.2d 368 (1975), but where there is conflicting evidence, the failure of the trial court to make specific findings upon which to base its conclusions is reversible error. The conclusions of law drawn by the trial court from its findings of fact are fully reviewable de novo by the appellate court. Humphries v. City of Jacksonville, 300 N.C. 186, 265 S.E.2d 189 (1980).

In this case, the facts found by the trial court do not support its conclusion that plaintiff is entitled to recover damages of $36,000. The trial court found that plaintiff had carried its burden of proof only as to the amount which it claimed was due by reason of “changes mandated by the government officials of Guilford County.” The evidence was conflicting with respect to the cost of changes necessitated by the Guilford County inspectors’ alleged enforcement of more stringent fire and building code requirements than had been anticipated by the contract; neither party contended for the figure which the trial court ultimately concluded plaintiff was entitled to recover.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wheeler v. Wheeler
Court of Appeals of North Carolina, 2026
Sawyer v. Billups
Court of Appeals of North Carolina, 2025
State v. Hollars
Court of Appeals of North Carolina, 2025
Farrington v. WV Invs.
Court of Appeals of North Carolina, 2024
In re: C.T.M. & C.S.F.
Court of Appeals of North Carolina, 2015
Embark, LLC v. 1105 Media, Inc.
753 S.E.2d 166 (Court of Appeals of North Carolina, 2014)
Wilson v. Wilson
714 S.E.2d 793 (Court of Appeals of North Carolina, 2011)
In re S.N.
669 S.E.2d 55 (Court of Appeals of North Carolina, 2008)
Carolina First Bank v. Stark, Inc.
660 S.E.2d 641 (Court of Appeals of North Carolina, 2008)
KROGER LTD. PARTNERSHIP I v. Guastello
628 S.E.2d 841 (Court of Appeals of North Carolina, 2006)
D.W.H. Painting Co. v. D.W. Ward Construction Co.
620 S.E.2d 887 (Court of Appeals of North Carolina, 2005)
Hartwell v. Mahan
609 S.E.2d 497 (Court of Appeals of North Carolina, 2005)
MEHRIZI v. ROMERO-BAEZA
605 S.E.2d 742 (Court of Appeals of North Carolina, 2004)
Currituck Associates—Residential Partnership v. Hollowell
601 S.E.2d 256 (Court of Appeals of North Carolina, 2004)
Clark v. City of Asheville
589 S.E.2d 384 (Court of Appeals of North Carolina, 2003)
RPR & Associates, Inc. v. University of North Carolina-Chapel Hill
570 S.E.2d 510 (Court of Appeals of North Carolina, 2002)
Harllee v. Harllee
565 S.E.2d 678 (Court of Appeals of North Carolina, 2002)
Cochrane v. City of Charlotte
559 S.E.2d 260 (Court of Appeals of North Carolina, 2002)
Biemann & Rowell Co. v. Donohoe Companies
556 S.E.2d 1 (Court of Appeals of North Carolina, 2001)
Washington v. Mitchell
553 S.E.2d 919 (Court of Appeals of North Carolina, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
522 S.E.2d 118, 135 N.C. App. 772, 1999 N.C. App. LEXIS 1244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mann-contractors-inc-v-flair-with-goldsmith-consultants-ii-inc-ncctapp-1999.