D.W.H. Painting Co. v. D.W. Ward Construction Co.

620 S.E.2d 887, 174 N.C. App. 327, 2005 N.C. App. LEXIS 2366
CourtCourt of Appeals of North Carolina
DecidedNovember 1, 2005
DocketCOA04-1220
StatusPublished
Cited by13 cases

This text of 620 S.E.2d 887 (D.W.H. Painting Co. v. D.W. Ward Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.W.H. Painting Co. v. D.W. Ward Construction Co., 620 S.E.2d 887, 174 N.C. App. 327, 2005 N.C. App. LEXIS 2366 (N.C. Ct. App. 2005).

Opinion

CALABRIA, Judge.

D.W. Ward Construction Company, Inc., third-party plaintiff, (“plaintiff’) appeals a judgment denying recovery for subcontractor D.W.H. Painting Company, Inc.’s (“D.W.H.”) painting services rendered to a State of North Carolina construction project. We affirm.

Plaintiff and Diversified Mechanical Limited, Inc. (“defendant”) were two of the four prime contractors for the State of North Carolina on a renovation project to Summerset Cottage at Murdock Center in Butner (the “project”). Plaintiff was the prime contractor responsible for installation of the ceilings, walls, trim, and flooring. In addition, the State designated plaintiff as the general contractor and “project expediter” which encompassed the following responsibilities: (1) scheduling of all the contractors’ work; (2) maintaining a progress schedule for all contractors; (3) providing all contractors with adequate notice to ensure efficiency in all phases of the work; and (4) notifying the State’s project designer (the “designer”) of any changes in the project schedule. The defendant was the prime contractor responsible for all electrical work on the project. Rural Heating and Plumbing, Inc. (“Rural”) was the prime contractor responsible for all *329 heating, ventilation, and air conditioning work on the project, and Britt Plumbing, Inc. (“Britt”) was the prime contractor responsible for the plumbing.

The project started in June 2000 and ended in either August or September 2001. During that time, the four prime contractors worked on the project simultaneously. In March 2001, plaintiff discovered damage to the walls and paint finishes and suspected the damage occurred as a result of mistakes by defendant, Rural, and Britt. Plaintiff notified the designer and was instructed to repair the damage. Since plaintiff had contracted with D.W.H. to provide painting services for the project, D.W.H. agreed to repaint all of the damaged areas on a labor and materials basis outside of their original contract. Between 30 April and 27 June 2001, D.W.H. repainted the damaged areas and billed plaintiff weekly. The final cost of D.W.H.’s work was $15,784.11.

Plaintiff failed to notify defendant about the damage and repainting costs until August 2001. On 21 August 2001, at plaintiffs request, the designer sent letters to all three of the prime contractors: defendant, Britt, and Rural. The letters informed them of the damage to the paint finishes and asked them to pay D.W.H. for the repainting. Subsequently, plaintiff forwarded several invoices to defendant, totaling $8,156.81, and requested defendant pay D.W.H. directly for the repainting. Plaintiff similarly invoiced and requested payment from Rural and Britt for the balance of D.W.H.’s work. Defendant, Rural, and Britt refused to pay D.W.H. for the repainting.

On 4 June 2002, since plaintiff failed to pay D.W.H., D.W.H. filed a complaint against plaintiff demanding payment for the repainting in the amount of $13,926. plus interest from 14 February 2002. Plaintiff filed a third-party complaint against defendant, Rural, and Britt demanding payment for negligent damage to plaintiff’s work or, in the alternative, restitution for the repainting costs on the basis of unjust enrichment. Plaintiff settled with D.W.H. for $17,284.11 and agreed to settle its claim against Rural and Britt for a combined sum. of $5,000.

Plaintiff and defendant’s dispute proceeded to trial, with plaintiff seeking $12,284.11 in damages from defendant. On 9 June 2004, the trial court found plaintiff improperly notified defendant about the damage and defendant was not responsible for the damages. Based on these findings, the trial court concluded “[plaintiff] failed to prove by the greater weight of the evidence that it is entitled to any contribution or reimbursement from [Diversified [defendant] for *330 any work done by D.W.H.” and entered judgment in favor of defendant. Plaintiff appeals.

N.C. Gen. Stat. §,143-128(b) (2003) authorizes the State to enter into “separate-prime contracts” for construction projects and provides in pertinent part:

(b) Separate-prime contracts. — When the State ... or other public body uses the separate-prime contract system, it shall accept bids for each subdivision of work for which specifications are required . . . and shall award the respective work specified separately to responsible and reliable persons, firms or corporations regularly engaged in their respective lines of work. . . . Each separate contractor shall be directly liable to the State of North Carolina ... or other public body and to the other separate contractors for the full performance of all duties and obligations due respectively under the terms of the separate contracts and in accordance with the plans and specifications, which shall specifically set forth the duties and obligations of each separate contractor.

By referring to each prime contractor’s contract with the State, N.C. Gen. Stat. § 148-128(b) “contemplates that a contractor who breaches his statutory duty to fulfill his contractual duties and obligations shall be liable for contract damages.” Bolton Corp. v. T. A. Loving Co., 94 N.C. App. 392, 404-05, 380 S.E.2d 796, 804 (1989). Under N.C. Gen. Stat. § 148-128(b), although the prime contractors did not enter into separate contracts with each other, “each contracted with the [State], and in that contract each affirmed its statutory duty to be liable to the other for damage to the other’s property or work.” Bolton, 94 N.C. App. at 397, 380 S.E.2d at 800. Accordingly, “a prime contractor may be sued by another prime contractor working on a construction project for economic loss foreseeably resulting from the first prime contractor’s failure to fully perform ‘all duties and obligations due respectively under the terms of the separate contracts.’ ” Id. (quoting N.C. Gen. Stat. § 143-128(b)).

Plaintiff first asserts the trial court improperly interpreted Article 15(e) of each party’s contract with the State to require notice of damage to the prime contractor allegedly responsible prior to repair of the damage. An issue of contract interpretation is a question of law reviewed de novo. Harris v. Ray Johnson Constr. Co., 139 N.C. App. 827, 829, 534 S.E.2d 653, 654 (2000).

*331 In pertinent part, Articles 14c and 15e of each party’s contract with the State provide the following:

ARTICLE 14
c. All contractors shall be required to cooperate and consult with each other during the construction of this project. . . . Each contractor shall be responsible for any damage to other contractor’s work....
ARTICLE 15
e. Should a contractor cause damage to the work or property of another contractor, he shall be directly responsible, and upon notice, shall promptly settle the claim or otherwise resolve the dispute.

Interpreted together, Articles 14c and 15e require accountability for damages and settlement after timely and effective notice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N. State Envtl., Inc. v. Town of Mooresville
Court of Appeals of North Carolina, 2025
Stratifyd, Inc. v. Wang
W.D. North Carolina, 2023
The Ascot Corp., LLC v. I&R Waterproofing
Court of Appeals of North Carolina, 2022
Brown v. Between Dandelions
Court of Appeals of North Carolina, 2020
Ernst v. North American Co. for Life & Health Insurance
245 F. Supp. 3d 680 (M.D. North Carolina, 2017)
Ivey v. ES2, LLC (In re ES2 Sports & Leisure, LLC)
544 B.R. 833 (M.D. North Carolina, 2015)
JPMorgan Chase Bank, National Ass'n v. Browning
750 S.E.2d 555 (Court of Appeals of North Carolina, 2013)
Koch Measurement Devices, Inc. v. Armke Ex Rel. Armke
2013 NCBC 48 (North Carolina Business Court, 2013)
M Series Rebuild, LLC v. Town of Mount Pleasant
730 S.E.2d 254 (Court of Appeals of North Carolina, 2012)
Sellers v. Morton
661 S.E.2d 915 (Court of Appeals of North Carolina, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
620 S.E.2d 887, 174 N.C. App. 327, 2005 N.C. App. LEXIS 2366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dwh-painting-co-v-dw-ward-construction-co-ncctapp-2005.