ECC International, LLC

Armed Services Board of Contract Appeals·Decided August 25, 2020·No. ASBCA No. 58875·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) ECC International, LLC ) ASBCA No. 58875 ) Under Contract No. W917PM-07-D-0015-0006 )

APPEARANCE FOR THE APPELLANT: Michael A. Richard, Esq. Obermayer Rebmann Maxwell & Hippel LLP Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Sarah L. Hinkle, Esq. Geoffrey A. Mueller, Esq. Matthew Tilghman, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE STINSON

Appellant, ECC International, LLC (ECCI), appeals a contracting officer’s (CO) deemed denial of its June 6, 2013, certified claim in the amount of $925,216.00 (R4, tab 2). The parties agreed to submit this appeal for a decision on the record without a hearing pursuant to Board Rule 11. Each party submitted initial and reply briefs. Also pending are the parties’ cross-motions for summary judgment, as well as respondent’s motion to dismiss for lack of jurisdiction. For the reasons stated below, we deny the government’s motion to dismiss, dismiss the parties’ cross-motions for summary judgment as moot, and deny the appeal.

FINDINGS OF FACT

The MATOC Contract

1. On August 15, 2007, the Government awarded ECCI Multiple Award Task Order Contract (MATOC) No. W917PM-07-D-0015, an Indefinite-Delivery, Indefinite-Quantity contract, “for general construction and construction related requirements such as repairs, and/or new construction, including the execution of design-build construction work throughout Afghanistan.” The contract anticipated award of task orders in the range of $5 million to $25 million. (R4, tab 3 at 142)

2. Paragraph 1.1 of the MATOC Scope of Work states, in part, that “[t]he vast majority of these projects will be new construction of relatively simple, one-and two-story living and working facilities similar to other ‘normal’ construction in Afghanistan, designed to be simple, durable, and easy/inexpensive to maintain” (R4, tab 3 at 147).

3. MATOC Scope of Work paragraph 1.4 states, in part:

Where design-build services are required, the contractor shall employ the services of architect/engineering professional established in coordination with multi-discipline architectural/engineering design efforts. The Contractor’s architect/engineering team shall be responsible for the coordination of all these disciplines in the performance of task order work.

(R4, tab 3 at 147)

4. Section 01335 of the MATOC is entitled “SUBMITTAL PROCEDURES FOR DESIGN-BUILD PROJECTS” (R4, tab 3 at 186). Paragraph 1.2.1, “DESIGN SUBMITTALS,” states, in part:

Contractor Furnished design submittals are the various design documents which primarily consist of specifications, drawings and design analysis and calculations. The Design-Build Contractor shall not begin construction work until the Government has reviewed the Design-Build Contractor’s final design and has cleared it for construction. Clearance for construction shall not be construed as meaning Government approval. Unless otherwise indicated, the risk for the design is the sole responsibility of the Design-Build Contractor.

As a minimum, design submittals shall be submitted at the following intervals:

Concept design (35%): In addition to submission requirements, a design analysis/basis of design shall be required, including a proposed listing of specification sections.

2 General design (65%): In addition to submission of designs, the contractor shall provide the design analysis, design specifications and design calculations.

Final (100%): In addition to submission requirements, a final draft of specifications and design analysis/basis of design shall be required.

(R4, tab 3 at 187-88)

5. MATOC paragraph 1.2.2.1, “Contractor Furnished Government Approved Construction Submittals,” states:

Government approved construction submittals are primarily related to plans (Contractor Quality Control, Accident Prevention, Resident Management System, Area Use, etc.) schedules (Project Schedule/Network Analysis), and certificates of compliance. They may also include proposed variations to approved design documents in accordance with the paragraph entitled “VARIATIONS”.

(R4, tab 3 at 188)

6. MATOC paragraph 1.3, “SUBMITTAL CERTIFICATION,” states:

The CQC organization shall be responsible for certifying that all submittals and deliverables have been reviewed in detail for completeness, are correct, and are in strict conformance with the contract drawings, specifications, and reference documents.

(R4, tab 3 at 188)

7. MATOC paragraph 1.3.1.2, “CQC System Manager Review and Approval,” states:

Prior to submittal, all items shall be checked and approved by the Design-Build contractor’s Quality Control (CQC) System Manager. If found to be in strict conformance with the contract requirement, each item shall be stamped, signed, and dated by the CQC System Manager. Copies of the CQC organizations review comments indicating action taken shall be included within each submittal.

3 (R4, tab 3 at 188)

8. MATOC paragraph 1.3.1.3, “Determination of Compliance,” states:

Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements by the Contracting Officer. The contractor shall submit all required documentation with submittals. The U.S. Army Corps of Engineers (USACE) will not accept partial submittals.

(R4, tab 3 at 188)

9. MATOC paragraph 1.3.2, “Responsibility for Errors or Omissions,” states:

It is the sole responsibility of the Design-Build Contractor to ensure that submittals do or do not comply with the contract documents. Government review, clearance for construction, or approval by the Contracting Officer shall not relieve the Design-Build Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract.

(R4, tab 3 at 188)

10. MATOC paragraph 1.3.2.1, “Government Review,” states:

Government review, clearance for construction, or approval of post design construction submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.

(R4, tab 3 at 188-89)

11. MATOC paragraph 1.3.3, “Substitutions,” states:

After design submittals have been reviewed and cleared for construction by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be

4 considered unless justified as indicated in the paragraph entitled VARIATIONS.

(R4, tab 3 at 189)

12. MATOC paragraph 3.2.2, “Construction Submittal Register (ENG Form 4288),” states:

Attached to this section is ENG Form 4288 which the Contractor is responsible for developing for this contract. All construction submittals shall be shown on this register. The submittal register shall be the controlling document and will be used to control all construction submittals throughout the life of the contract. The Contractor shall maintain and update the register on a monthly basis for the Contracting Officer’s approval.

(R4, tab 3 at 198)

13. MATOC paragraph 3.6.4, “Variations,” states, in part:

If design documents or construction submittals show variations from the contract parameters and/or requirements, the Contractor shall justify such variations in writing, at the time of submission. Additionally, the contractor shall also annotate block “h” entitled “variation” of ENG FORM 4025.

Free access — add to your briefcase to read the full text and ask questions with AI

ECC International, LLC, (asbca 2020).

ECC International, LLC (ECC International, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mabus v. General Dynamics C4 Systems, Inc.
633 F.3d 1356 (Federal Circuit, 2011)
Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
United Pacific Insurance Company v. Roche
401 F.3d 1362 (Federal Circuit, 2005)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Tecom, Inc. v. The United States
732 F.2d 935 (Federal Circuit, 1984)
George Hyman Construction Company v. The United States
832 F.2d 574 (Federal Circuit, 1987)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Hejran Hejrat Co. Ltd v. US Army Corps of Engineers
930 F.3d 1354 (Federal Circuit, 2019)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Fluor Enterprises, Inc. v. United States
64 Fed. Cl. 461 (Federal Claims, 2005)
Gresham & Co. v. United States
470 F.2d 542 (Court of Claims, 1972)