ECC International, LLC

Armed Services Board of Contract Appeals·Decided February 24, 2022·No. ASBCA No. 58993, 60167, 60283·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) ECC International, LLC ) ASBCA Nos. 58993, 60167, 60283 ) Under Contract No. W912DQ-11-C-4009 )

APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq. Amy M. Kirby, Esq. Cohen Seglias Pallas Greenhall & Furman, PC Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Sarah L. Hinkle, Esq. Michael E. Taccino, Esq. Matthew Tilghman, Esq. Kathryn G. Morris, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE O’SULLIVAN

ECC International, LLC (ECCI or appellant), appeals from deemed denials of its claims arising from the performance of a contract with the U.S. Army Corps of Engineers (USACE, Corps, or government) to construct a Military Police School and a Signal School for the Afghan National Army at Camp Shaheen, Afghanistan. Three primary issues are presented in these appeals: (1) the “collapsible soils claim” contends that ECCI is entitled to be compensated for the cost of mitigating collapsible soils found at the site because, by accepting ECCI’s offer which excluded collapsible soil mitigation from its bid, the Corps awarded a contract that excluded that work; (2) the “BCOE claim” contends that USACE unreasonably imposed and enforced a period of performance that it had reason to know would be difficult to impossible to accomplish, and is liable for the damages caused; and (3) the “DBA insurance claim” contends that USACE wrongly deprived ECCI of reimbursement for DBA insurance premiums that ECCI actually paid, and for which it was entitled to be reimbursed. We have jurisdiction under the Contract Disputes Act, 41 U.S.C. §§ 7101-7109. We sustain the appeals. FINDINGS OF FACT

Background and Contract Provisions

1. The United States Army Corps of Engineers, Kansas City District (NWK), awarded Contract No. W912DQ-11-C-4009 (the contract) to ECCI on April 8, 2011. The contract was for the construction of a Military Police School and a Signal School for the Afghan National Army as part of a planned expansion of Camp Shaheen in the Mazar-e-Sharif area, Balkh Province, Afghanistan. The contract price as awarded was $27,613,870.20. (R4, tab 11 at GOV000322-24)

2. USACE, through the Afghanistan Engineer District – North (AED or AEN), performed contracting functions for the Combined Security Transition Command – Afghanistan (CSTC-A), for the design and construction of facilities for the Afghan National Army (ANA) throughout Afghanistan. In late 2010, with an increasing workload, AEN looked to certain Engineer Districts back in the United States for help in awarding contracts. (Tr. 10/20, 167-69) AEN specifically asked the Northwestern Division, Kansas City District (NWK or Kansas City), for help in awarding contracts for the Camp Shaheen expansion because many Corps employees working at NWK had previously deployed to Afghanistan and were familiar with the unique issues Afghanistan projects could present. (Tr. 7/143, 10/20, 172) In addition to the Military Police and Signal Schools, the Camp Shaheen expansion included a project called the Group A Expansion.

3. ECCI was one of several bidders on the Military Police (MP) and Signal School project, which was solicited by Kansas City on February 24, 2011 (R4, tab 4). ECCI also bid on the Group A Expansion, which was solicited on March 29, 2011 (R4, tab S-733). The Group A project was also awarded to ECCI, on May 17, 2011 (R4, tab S-48 at 36).

4. The MP/Signal School and Group A Expansion project sites were adjacent to one another (R4, tab S-545 at 8). The projects were similar in that both employed arch span structures 1 for most of the project square feet. The MP/Signal School contract called for a total of 20,039 square meters of arch span buildings (R4, tab 11 at GOV000380, GOV000484). The Group A Expansion contract called for a total of

1 Arch span construction, also known as K-span construction (a proprietary term of M.I.C. Industries), is a streamlined process of erecting structures using machines to corrugate rolled steel and cranes to place the arch on top of a slab. The process speeds up construction and requires less material and labor than conventional brick and mortar construction. (Tr. 4/204-05, 217-18)

• A Glossary of Acronyms used throughout this opinion is appended at the end. 2 29,934 square meters of arch span buildings (R4, tab S-48 at 94-97). Both contracts called for the use of austere design standards 2 (R4, tab 11 at GOV000369, GOV000475, R4, tab S-48 at 83). The designs for the two projects were similar enough that at one point both projects were combined in the design review process (tr. 9/103-04).

5. The MP/Signal School contract contained two separate specifications, one for the MP School and one for the Signal School. The specification for the MP School called for 29 design-build facilities and 12 site adapt facilities to be constructed. The Signal School specification called for the construction of 19 design-build facilities and 8 site adapt facilities. 3 (R4, tab 11 at GOV000380-81, GOV000484) Both specification sections required that the contractor complete the designs for the design build facilities. For the site adapt facilities, the contractor was to complete construction in conformance with the standard design drawings provided. (Id. at GOV000380-81, GOV000484)

6. The MP/Signal School solicitation and contract as awarded contained “Design Concept Documents” that were not standard designs but were to be used by the contractor as “the basis for the project design and construction documents.” Following award, the contractor was to complete the design and construction documents and construct the project in accordance with the completed documents. The design review process contemplated four submittals before the final design submission and encouraged the contractor to develop and submit “multiple cost saving proposals for innovative design alternatives.” (R4, tab 9 at GOV000174, tab 11 at GOV000359) The contract contains the following Order of Precedence clause with respect to design:

5.2 ORDER OF PRECEDENCE In case of conflict, duplication, or overlap of design criteria specified in the documents referenced in this section, the following order of precedence shall be followed:

1. Contract Award Document and referenced publications therein; 2. Written requirements and specifications; 3. Drawings.

2 “Austere design” is a design philosophy employed in Afghanistan that embraces minimalistic design of facilities that are easily operated, have low maintenance requirements, and use construction methods tailored to the local workforce (R4, tab S-587 at 2). 3 Generally speaking, design-build means that the contractor designs the building to the project owner’s criteria and then constructs it to the approved design. Site-adapt means that the contractor receives an existing design from the project owner and adapts the design to fit a specific site, taking into account the existing physical characteristics of the land. 3 (R4, tab 11 at GOV000362-63) This section further provides that only the work plan, boundary survey plan, and topographic survey plan are mandatory design criteria, and that all other criteria are considered non-mandatory and may be enhanced, improved, or substituted to better suit design requirements (id. at 363).

I. The Collapsible Soils Claim, ASBCA No. 58993

7. Soils in Afghanistan include a type known as loess. To oversimplify, loess is a kind of fine silt left behind as glaciers melt.

Free access — add to your briefcase to read the full text and ask questions with AI

ECC International, LLC, (asbca 2022).

ECC International, LLC (ECC International, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Nationwide Bank v. United States
431 F.3d 1342 (Federal Circuit, 2005)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Laburnum Construction Corporation v. The United States
325 F.2d 451 (Court of Claims, 1963)
Perry and Wallis, Inc. v. The United States
427 F.2d 722 (Court of Claims, 1970)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Air-Sea Forwarders, Inc. v. United States
166 F.3d 1170 (Federal Circuit, 1999)
Jowett, Incorporated v. United States
234 F.3d 1365 (Federal Circuit, 2000)
Christos v. United States
300 F.3d 1381 (Federal Circuit, 2002)
Leonard Hinton v. Alan M. Uchtman
395 F.3d 810 (Seventh Circuit, 2005)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
Cresswell v. United States
173 F. Supp. 805 (Court of Claims, 1959)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Agility Public Warehousing Co. KSCP v. Mattis
852 F.3d 1370 (Federal Circuit, 2017)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)
United Pacific Insurance v. United States
497 F.2d 1402 (Court of Claims, 1974)
American Ship Building Co. v. United States
654 F.2d 75 (Court of Claims, 1981)