United Pacific Insurance Company v. Roche

401 F.3d 1362, 2005 U.S. App. LEXIS 4494, 2005 WL 627783
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 18, 2005
Docket2004-1334
StatusPublished
Cited by19 cases

This text of 401 F.3d 1362 (United Pacific Insurance Company v. Roche) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Pacific Insurance Company v. Roche, 401 F.3d 1362, 2005 U.S. App. LEXIS 4494, 2005 WL 627783 (Fed. Cir. 2005).

Opinion

MAYER, Circuit Judge.

United Pacific Insurance Company (“United”) appeals the decisions of the Armed Services Board of Contract Appeals, ASBCA Nos. 52419, 54270, 54271 (Feb. 7, 2001 & Dec. 29, 2003) (“United I ”). It asserts claims arising from events that occurred before it entered into a takeover agreement with the government, as well as two claims stemming from the takeover agreement. Because the board lacks jurisdiction, we cannot consider the merits of United’s pre-takeover claims. As to the remaining two claims, we affirm.

*1364 Background

On September 28, 1995, the government executed Contract No. F28609-95-C-0037 with Castle Abatement Corp. (“Castle”). The contract was for all necessary work and material for repair of a Secondary Containment System at McGuire Air Force Base, New Jersey, for a fixed-price of $1,957,630. The contract also encompassed removal and disposal of contaminants at fixed unit prices, with a total not-to exceed price of $2,312,367. Castle obtained a payment and performance bond from United for $2,312,267, and a labor and material payment bond for $1,156,134, with the government as obligee. Prior to securing the bonds, Castle executed an indemnity agreement for the benefit of United and other insurance companies.

On July 22, 1997, the government terminated the rights of Castle to proceed under the contract for default. In an earlier appeal, we addressed Castle’s default involving a related series of contracts with the Air Force. See United Pac. Ins. Co. v. Roche, 380 F.3d 1352, 1354-55 (Fed.Cir.2004) (“United II”). Castle had no pending claims against the government at the time of default and it did not appeal the termination. Within a month, the government made demand upon United as surety, to fulfill its obligations under the performance bond.

United entered into a written takeover agreement with the government on August 5, 1997, in which it agreed to complete the work remaining under the contract. The takeover agreement was incorporated into the original contract and United was substituted as the contractor. Certain “Whereas” clauses within the takeover agreement detailed the background and purpose of the agreement. One such “Whereas” clause stated that a contract balance of $998,863.64 remained to be paid by the government for the fixed price portion of the original contract. The stated contract balance was based upon the payments made to Castle as of the date of termination, and United drafted the takeover agreement incorporating the amount. The recited amount turned out to be incorrect. The takeover agreement understated the amount paid to Castle prior to the termination, and thus overstated the contract balance available to United to complete the Castle contract by $46,288.37.

In a letter dated October 23, 1998, United submitted a request for equitable adjustment to the government containing ten claims. On May 21, 1999, the parties met to discuss possible settlement. United’s representative alleges, but the government disputes, that an oral settlement of certain claims on which the parties agreed was entered into for $214,745.

After settlement negotiations reached an impasse, the contracting officer denied all claims and United appealed to the Armed Services Board of Contract Appeals (“board”). It alleged four counts: (1) for an equitable adjustment based upon pre-takeover events; (2) for a cardinal change; (3) for a contract balance; and (4) for the specific enforcement of the settlement agreement. On December 29, 2003, the board concluded that it lacked jurisdiction over United’s claims based upon contaminated soil and other site conditions that arose prior to the takeover agreement. Similarly, the board determined that the indemnification agreement between Castle and United could not serve as a vehicle to assign Castle’s unliquidated claims to United.

The board did, however, address the merits of United’s post-takeover claims. It denied the contract balance claim, although adjustment was made for a minor mathematical error. It determined that the amount of the contract balance in the “Whereas” clause was not controlling because the clause was a mere recital of an *1365 undisputedly erroneous fact; and it rejected United’s assertion that a settlement had been reached at the May 21, 1999 meeting. United timely appealed the board’s decision and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

Discussion

Like the board, we are precluded from reviewing the merits of United’s pre-takeover claims. The board determined that United lacked standing and, therefore, that it lacked jurisdiction to entertain United’s pre-takeover claims because United was not a “contractor” as defined by the Contract Disputes Act, 41 U.S.C. §§ 601-613, at the time those claims arose. Our subsequent decision in United II addressing an identical takeover agreement between the same parties leaves no dispute that United’s pre-takeover claims are not subject to the board’s jurisdiction. See United II, 380 F.3d at 1354-57. As we reasoned in United II, “the remainder of United’s claims suffer from the same infirmity that made the claims in Fireman’s Fund [Insurance Co. v. England, 313 F.3d 1344 (Fed.Cir.2002) ] not subject to the Board’s jurisdiction: they relate to and depend upon events that occurred before the takeover agreement and with respect to which United was not a ‘contractor’ under the Contract Disputes Act when the claims arose.” Id. at 1356. Therefore, we turn to the post-takeover claims. *

Our review of a board decision is based upon the standards set out in the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613. E.L. Hamm & Assocs., Inc. v. England, 379 F.3d 1334, 1338 (Fed.Cir.2004). We review questions of law de novo. Eastman Kodak Co. v. Rumsfeld, 317 F.3d 1377, 1379 (Fed.Cir.2003). “Contract interpretation is a question of law; therefore, the board’s decisions regarding this matter are not binding.” M.A. Mortenson Co. v. Brownlee, 363 F.3d 1203, 1205 (Fed.Cir.2004). “Because ‘the board has considerable experience and expertise in interpreting government contracts,’ however, ‘its interpretation is given careful consideration and great respect.’ ” Id. (quoting Cmty. Heating & Plumbing Co. v. Kelso,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luo v. District of Columbia Department of Employment Services
District of Columbia Court of Appeals, 2025
Nova group/tutor-saliba v. United States
87 F.4th 1375 (Federal Circuit, 2023)
Dynamic Systems Technology, Inc.
Armed Services Board of Contract Appeals, 2023
Asset Protection & Security v. United States
5 F.4th 1361 (Federal Circuit, 2021)
ECC International, LLC
Armed Services Board of Contract Appeals, 2020
Lea v. United States
Federal Claims, 2014
Northrop Grumman Corporation
Armed Services Board of Contract Appeals, 2014
Lublin Corp. v. United States
106 Fed. Cl. 669 (Federal Claims, 2012)
Doe v. United States
95 Fed. Cl. 546 (Federal Claims, 2010)
Environmental Safety Consultants, Inc. v. United States
95 Fed. Cl. 77 (Federal Claims, 2010)
Englewood Terrace Ltd. Partnership v. United States
84 Fed. Cl. 649 (Federal Claims, 2008)
Rick's Mushroom Service, Inc. v. United States
76 Fed. Cl. 250 (Federal Claims, 2007)
Kaeper Machine, Inc. v. United States
74 Fed. Cl. 1 (Federal Claims, 2006)
Craig-Buff Ltd. Partnership v. United States
69 Fed. Cl. 382 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
401 F.3d 1362, 2005 U.S. App. LEXIS 4494, 2005 WL 627783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-pacific-insurance-company-v-roche-cafc-2005.